Tunbridge Wells Borough Council
Cabinet, Thursday 6 February 2020 at 10.30am

Calverley Square Closedown

Approved Executive 2 papers

Cabinet approved this item on Thursday 6 February 2020. Below is the council's own wording, with the papers it was decided on.

ItemCAB127/19

Resolved

RESOLVED – 1. That the final expenditure figures related to the development and delivery of the Calverley Square project in accordance with Full Council decisions be approved. 2. That the closure of the Calverley Square project be noted. And it be noted that the planning permission remained valid until 14 June 2021, and the CPO remained valid until 9 May 2022, in accordance with statutory requirements. 3. That the planning or CPO consents that are in place be not implemented. REASON FOR DECISION: To implement the decision made by Full Council on 8 October 2019 to terminate the Calverley Square project.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Cabinet

Cabinet 6 February 2020 Is the final decision on the recommendations in this report to be made at this meeting? Yes

Calverley Square Development Closure Final Decision-Maker Cabinet Portfolio Holder(s) David Scott, Portfolio Holder for Property, Major Projects and Strategic Engagement Tom Dawlings, Portfolio Holder for Finance and Governance Lead Director Lee Colyer, Director of Finance, Policy and Development Head of Service David Candlin, Head of Economic Development and Property Lead Officer/Report Author David Candlin, Head of Economic Development and Property Classification Non Exempt Wards affected All

This report makes the following recommendations to the final decision-maker: 1. To approve the final expenditure figures related to the development and delivery of the Calverley Square project in accordance with Full Council decisions. 2. To note the closure of the Calverley Square project and that the planning permission remains valid until 14 June 2021 and the CPO remains valid until 9 May 2022 in accordance with the statutory requirements. 3. Resolve not to implement the planning or CPO consents that are in place.

 A Prosperous Borough  A Green Borough  A Confident Borough

The proposals that comprise the Calverley Square project supported the delivery of priorities contained within the Council’s Five-Year Plan through the development of a new enhanced theatre, the provision of new office space and a new car park, and improvements to the public realm at the entrance to Calverley Grounds.

Timetable Meeting Date Management Board 3 January 2020 Discussion with Portfolio Holder 7 January 2020 Cabinet Advisory Board 14 January 2020 Cabinet 6 February 2020 Calverley Square Development Closure

1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY

1.1Full Council on 8 October 2019 decided to terminate the Calverley Square project. The report provides an update on the consequences of the decision and the financial sums involved.

2 INTRODUCTION AND BACKGROUND

2.1Full Council took the decision on the 8 October 2019 to terminate the Calverley Square project. The project as developed was for the Great Hall Car Park and Mount Pleasant Avenue Car Park on the edge of Calverley Grounds to be redeveloped for:

 A new 1,200 seat theatre that would be able to stage high quality touring shows;  A new shared-use building including accommodation for civic functions and offices for TWBC and third party organisations;  An underground car park (approximately 260 car park spaces) partly under the office building and extending under part of Calverley Grounds; and  Local remodelling of the public realm associated with the above buildings and car park.

2.2The project was rooted in the Council’s Five-Year Plan and was taken forward in a staged approach with the decision to proceed to each stage being ratified by Full Council.

2.3The development was proposed to release the Town Hall, Assembly Hall Theatre and 9/10 Calverley Terrace for alternative uses to provide economic, environmental and social benefits for the town centre and for the Borough as a whole. As a result of October decision, steps have been taken to close it down. This report provides information on the consequences of the Council decision.

3 FULL COUNCIL DECISION

3.1The report considered by Full Council contained eight recommendations. The first recommendation which was taken in isolation was:

“That, given the importance of culture and leisure to the town’s economy and social environmental and economic wellbeing, and in recognition of the planned growth to the Borough’s population, this Council endorses the principle that it wishes to provide a theatre that meets the needs of residents, visitors and producers”.

3.2This recommendation was rejected by Full Council. The implication of the decision is essentially that Full Council does not endorse the need for a theatre that meets the needs of visitors, residents or producers meaning that a theatre is not required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Calv Expenditure cab /19Appendix A 194 KB Download
PDF
Calverley Square ClosedownReport 284 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Calverley Square ClosedownThis decision
  2. Calverley Square Development UpdateDecided
  3. *Calverley Square Delivery RIBA Stages 5-7Decided
  4. Independent Audit of cancelled Calverley Square ProjectAgreed
  5. *Calverley Square Delivery RIBA Stages 5-7Approved
  6. Calverley Square - Council MotionsNoted

More from Tunbridge Wells Cabinet

All decisions
MeetingDecisionOutcome
24 Sep 2026 Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... Noted Open
24 Sep 2026 Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... Noted Open
24 Sep 2026 Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... Noted Open
24 Sep 2026 New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... Approved Open
24 Sep 2026 Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies