RESOLVED – 1. That the summary of priority projects performance over quarter 3 at Appendix A be noted. 2. That the summary of service performance over quarter 3, at Appendix B be noted. 3. That the performance indicator Recovery Plans for quarter 3 at Appendix C-F be noted. REASON FOR DECISION: To monitor the effectiveness of the Council’s actions and plans to meet all the objectives within the Five Year Plan, highlight underperforming areas, and propose actions to remedy any underperformance to ensure the key objectives are met.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 12 March 2020 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Performance Summary: Quarter 3 Final Decision-Maker Cabinet Portfolio Holder(s) Cllr Tom Dawlings, Portfolio Holder Finance & Governance Lead Director Lee Colyer, Director of Finance, Policy and Development Head of Service Jane Clarke, Head of Policy and Governance Lead Officer/Author Jane Clarke, Head of Policy and Governance Classification Non-exempt
Wards affected Not applicable
This report makes the following recommendations to the final decision-maker: 1. That Cabinet notes the summary of priority projects performance over quarter 3 at appendix A. 2. That Cabinet notes the summary of service performance over quarter 3, at appendix B. 3. That Cabinet notes the performance indicator Recovery Plans for quarter 3, at appendices C-F.
Explain how this report relates to the Corporate Priorities in the Five Year Plan This performance report outlines the Council’s progress against the 8 Big Projects and the Corporate Priorities within the Five Year Plan.
Timetable Meeting Date Management Team 29 January 2020 Cabinet Advisory Board 18 February 2020 Cabinet 12 March 2020 Tunbridge Wells Committee Report, version: January 2018 Performance Summary: Quarter 3 1. PURPOSE OF REPORT
1.1This report summarises the performance of the Council’s priority projects and service delivery over quarter 3, and where under-performance is identified, highlights actions to resolve this.
1.2The performance management framework is part of the overall governance framework within the Council, which ensures that risks are managed whilst results are delivered.
1.3Quarterly performance management helps the Council to improve services and deliver better results for residents, and Cabinet oversight ensures that the framework is robust, and that performance is open to challenge from those with political responsibility for the delivery of services. Providing a publicly available quarterly report allows Council members, stakeholders and residents to engage with the work of the Council, and to provide further challenge where it is appropriate and effective to do so.
2. INTRODUCTION AND BACKGROUND
2.1The report is divided into three main sections:
o Projects performance (appendix A) o Service performance (appendix B) o Actions for improving under-performance (appendices C-F)
2.2Delivery of the priority projects is corporately monitored on a weekly basis by the Project Management Office, and is reviewed every two weeks by the Programme Management Board, which consists of the Chief Executive and his Directors. Progress is also monitored informally by Portfolio Holders in regular update meetings with Directors, and once a month at Leadership Board.
2.3Quarterly reporting through Cabinet ensures openness and transparency of the Council’s projects and plans, and ensures significant oversight and scrutiny of the Council’s actions.
2.4Service delivery is monitored on a day-to-day basis by line managers, and reported to Heads of Service and Management Board on a quarterly basis. Quality control checks on the data gathered are conducted by line managers, the Performance and Governance team and by Heads of Service through Management Team meetings. 3. PROJECTS PERFORMANCE
3.1On 27 September 2017 the Full Council agreed a new Five Year Plan, which set out ‘eight big projects’ that would help it to meet its corporate priorities of a ‘prosperous, well and inclusive borough’. Those eight projects were:
1. The Cultural and Learning Hub (The Amelia) 2. A new theatre (Calverley Square) 3. New offices with underground car parking (Calverley Square) 4. New off-street car parking 5. A new Local Plan 6. New sports facilities 7. New community centres (Community Hubs) 8. New public space (Public Realm Phase 2)
3.2On 6 December 2017 Full Council approved the scheme known as ‘Calverley Square’ for funding and delivery beyond RIBA Stage 3 (developed design stage).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.