Highway Works Programme

Decided Committee 1 paper

Joint Transportation Board decided this item on Monday 19 April 2021. Below is the council's own wording, with the papers it was decided on.

ItemTB32/20

Resolved

RESOLVED – That the ... view the full minutes text for item TB32/20
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Joint Transportation Board

To: Tunbridge Wells Joint Transportation Board

By: KCC Highways, Transportation & Waste

Date: 19th April 2021

Subject: Highway Forward Works Programme – 2020/21 onwards

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2020/21.

Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.

This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D • Casualty Reduction Measures • Externally funded schemes • Local Growth Fund

Developer Funded Works – see Appendix E

Bridge Works – see Appendix F

Traffic Systems – see Appendix G

Combined Member Fund – see Appendix H

Conclusion

1. This report is for Members’ information. Contact Officers:

The following contact officers can be contacted on 03000 418181

Richard Emmett Highway Manager West Kent Julian Cook Tunbridge Wells District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Emma Green Schemes Programme Manager Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status

Between Dorset Road and Forest Road Tunbridge Wells Boundary Road Completed

From the A228 to just north Tonbridge Road Pembury of the Hospital Turning Completed

From Mount Pleasant Road Crescent Road Tunbridge Wells to Calverley Road Completed

Talbot Road to A268 Rye A229 Highgate Hill Hawkhurst To be programmed Road Spring 2021

A262 Spelmonden Junction with Spelmonden Goudhurst To be programmed Road Lane Summer 2021 From Crescent Road to Mount Pleasant Tun Wells south side of Grove Hill To be programmed Road Roundabout Summer 2021 Retexturing Angerly Road Cranbrook From Sheafe Drive to just To be programmed past Whitewell Lane Summer 2021 Retexturing A262 Goudhurst Road Lamberhurst From the A21 Junction to To be programmed Horsmonden Road Summer 2021 Retexturing A262 Station Road Goudhurst From Blue Coat Lane to To be programmed Bridge Summer 2021

Surface Treatments – Contact Officer [name removed] Surfacing

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Works ProgrammeReport 341 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Highway Works ProgrammeThis decision
  2. Highway Works ProgrammeNoted
  3. Highway Works ProgrammeDecided
  4. Highway Works ProgrammeNoted
  5. Highway Works ProgrammeNoted
  6. Highway Works ProgrammeAgreed

More from Tunbridge Wells Joint Transportation Board

All decisions
MeetingDecisionOutcome
13 Jul 2026 Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... Decided Open
13 Jul 2026 Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... Decided Open
13 Jul 2026 Active Travel UpdateRESOLVED – The report was noted. Noted Open
20 Apr 2026 Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. Approved Open
20 Apr 2026 Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies