CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tunbridge Wells Borough Council
Joint Transportation Board, Monday 18 October 2021 at 6.00pm

Highway Works Programme

Agreed Committee 1 paper

Joint Transportation Board agreed this item on Monday 18 October 2021. Below is the council's own wording, with the papers it was decided on.

ItemTB9/21

Resolved

It was agreed that a revised business case for the scheme should be presented at the September meeting to demonstrate high value for money in regards to the remaining LGF allocation. In addition, evidence would be provided as to how the project met the conditions for spend for beyond 1 September 2021 as proposed by SELEP. The revised business case, although bold and innovative, unfortunately did not deal with the risk to delivery and realisation of benefits that was a prerequisite for the funding extension granted by SELEP.” - The use of Public Rights of Way might be an option for future cycle paths. It was noted that to take this investigation further would require significant resources and funding. - There remained issues related to Public Realm 2 including measures to make the junctions safer. It was understood that further discussions would take place once traffic had returned to pre-pandemic levels. - It would be helpful to investigate any measures to help remove HGV’s on the A26. Unfortunately the duelling work on the A21 had not removed a significant number of HGV’s from the A26. - The A26 was not a suitable road for a cycle path. - Funding remained a major issue. Central Government had taken £9m from KCC’s Highway budget last year and it was unclear what would happen with the budget this year. RESOLVED – That the report be noted.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Joint Transportation Board

To: Tunbridge Wells Joint Transportation Board

By: KCC Highways, Transportation & Waste

Date: 18th October 2021

Subject: Highway Forward Works Programme – 2019/20 onwards

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2020/21.

Kent County Council has agreed a substantial increase in the budget for planned highway works over the next three years, and as a result we are still in the process of identifying and designing schemes for inclusion in our full Year One to Two (2019/20 and 2020/21) and Year Three to Five (2021/22 to 2023/24) programmes. Because of this, we have decided to publish an interim programme, and to publish the full programmes later this year. For some assets this interim programme covers approximately the first six months of 2019/20, whilst for others it includes most of the works planned for the whole year.

This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect KCC’s changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase.

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D • Casualty Reduction Measures • Externally funded schemes • Local Growth Fund

Developer Funded Works – see Appendix E

Bridge Works – see Appendix F

Traffic Systems – see Appendix G

Combined Member Fund – see Appendix H

Conclusion

1. This report is for Members’ information. Contact Officers:

The following contact officers can be contacted on 03000 418181

Richard Emmett Highway Manager West Kent Julian Cook Tunbridge Wells District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Emma Green Schemes Programme Manager Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status

A229 Highgate Hill Hawkhurst Talbot Road to A268 Rye Road Completed

A262 Spelmonden Completed Goudhurst Junction with Spelmonden Lane Road

From Crescent Road to south Mount Pleasant Tun Wells side of Grove Hill Road To be programmed Roundabout

Surface Treatments – Contact Officer [name removed] Surfacing

Road Name Parish Extent of Works Current Status

Sponden Lane Triangle to A268 Sponden Lane Sandhurst Megrims Hill Complete A262 to Colliers Green School Colliers Green Road Cranbrook (Marden Road) Complete Standen Street to Benenden Iden Green Road Benenden Crossroads (Tie into HFS at each Complete end) Megrims Hill (10mm Megrims Cottage to Sandhurst Sandhurst MA) Gateway (10mm) To be Programmed

Rye Road (10mm Little Fowlers to Conghurst Lane Hawkhurst MA) ("Risden") (10mm) To be Programmed Victoria Road / Bentham Hill / Between A26 London Road to Southborough Stockland Green Speldhurst Hill Completed Road Grosvenor Bridge to Meadow Upper Grosvenor Rd Tunbridge Wells Road Complete Martins Farm/Charity Farm to Swattenden Lane Benenden Barn Store Complete

Peasley Lane Goudhurst Ranters Lane to Bedgebury Road Complete

Brenchley Post Office to 200m Horsmonden Road Brenchley east of j/w Spout Lane Complete

Constitutional Hill From Victoria Road to Holden Southborough Road Pond Complete

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Works ProgrammeReport 401 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Highway Works ProgrammeThis decision
  2. Highway Works ProgrammeNoted
  3. Highway Works ProgrammeDecided
  4. Highway Works ProgrammeNoted
  5. Highway Works ProgrammeNoted
  6. Highway Works ProgrammeDecided

More from Tunbridge Wells Joint Transportation Board

All decisions
MeetingDecisionOutcome
13 Jul 2026 Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... Decided Open
13 Jul 2026 Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... Decided Open
13 Jul 2026 Active Travel UpdateRESOLVED – The report was noted. Noted Open
20 Apr 2026 Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. Approved Open
20 Apr 2026 Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies