RESOLVED – 1. That the actual revenue expenditure outturn and impact on reserves for the year ended 31 March 2021 be noted. 2. That the expected withdrawal from reserves of £1,585,000 to meet the forecast deficit at Quarter 3 would not be needed and a sum of £211,000 to be transferred to the General Fund be noted. 3. That a new charge for the administration of applications from site owners or managers of mobile homes, following new regulations coming into force on 1 July 2021 be approved. REASON FOR DECISION: To show the actual expenditure on services compared to the revised budget for the period ending 31 March 2021, and the forecast outturn position, highlighting significant variances from the revised annual budget.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Officer / Committee recommendations as supported by the Portfolio Holder: 1. That Cabinet note the actual revenue expenditure outturn and impact on reserves for the year ended 31 March 2021. 2. That Cabinet note that the expected withdrawal from reserves of £1,585,000, to meet the forecast deficit at Quarter 3 will not be needed and a sum of £211,000 will be transferred to the General Fund. 3. That Cabinet agree a new charge for the administration of applications from site owners or managers of mobile homes, following new regulations coming into force on 1 July 2021.
Page Tunbridge Wells Borough Council 1 of 12 Revenue Management: Quarter 4 (to 31 March 2021) 1. Introduction and Background 1.1 This report shows the unaudited actual expenditure outturn on services compared to the revised budget for the period ended 31 March 2021, and the forecast outturn position, as at Quarter 3. 1.2 The actual outturn shows an overspend against the revised budget of £5,928,000. This comprises an underspend on expenditure of £1,848,000 offset by an underachievement of income of £7,776,000. The forecast as at Quarter 3 was a net overspend of £6,620,000 so this represents an improvement to the forecast of £692,000. 1.3 The net funding the Council received was £6,139,000 more than the revised budget, and this resulted in a sum of £211,000 (£192,000 from closing the Pensions Earmarked Reserve and £19,000 balancing surplus) being transferred to the General Fund. Overall, considering the huge financial challenges that Covid-19 created in 2020/21, the council has performed magnificently to manage their finances to an £19,000 surplus for the year.
2. Revenue Management to 31 March 2021
Summary Outturn – Appendix A
2.1Appendix A shows the overall income and expenditure on services forecast outturn position as at 31 March 2021. Total income and expenditure on services can be seen in greater detail within Appendix B, which provides information per service area. The approved budget was set by Full Council on 26 February 2020 and does not change. The revised budget is used to record virements amongst service areas and from reserves, whilst the forecast outturn is used to record the reporting of savings, overspends and allocations from reserves. 2.2 The actual outturn for expenditure on services was £18,214,000, £5,928,000 above the approved budget. This is an improvement from Quarter 3 of £692,000 which was forecasting an overspend of £6,620,000. This is the result of various movements as can be seen in Appendix C. 2.3 Investment interest and income was £109,000 under budget for the year, an improvement of £23,000 on the forecast of £132,000 under at Quarter 3. £22,000 of this increase was for investment interest and was due to the rate earned on the Property Fund improving over the last quarter. The Council’s investment in the Fund has generated a net return of 4.98% which has contributed greatly to the interest amount achieved. The PWLB loan of £1 million, was repaid in July
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.