RESOLVED – 1. That in order to set guidelines when calculating and negotiating a commuted sum in lieu of the onsite delivery of affordable housing, the be approved. 2. That delegated authority be given to the Head of Housing, Health and Environment, in consultation with the Portfolio Holder for Housing and Planning to make any minor amendments to the Affordable Housing Commuted Sum Position be approved. REASON FOR DECISION: To provide a transparent mechanism for calculating commuted sums.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Officer / Committee recommendations as supported by the Portfolio Holder: 1. That the Cabinet approves the Affordable Housing Commuted Sum Position Statement in order to set guidelines when calculating and negotiating a commuted sum in lieu of the onsite delivery of affordable housing. 2. That delegated authority be given to the Head of Housing, Health, and Environment, in consultation with the Portfolio Holder for Housing and Planning, to make any minor amendments to the Affordable Housing Commuted Sum Position.
Page Tunbridge Wells Borough Council 1 of 8 Affordable Housing Commuted Sums Spending Policy Report 1. Introduction and Background 1.1 A commuted sum is an affordable housing contribution, paid by a developer to a local authority, where the size or scale of development triggers a requirement for affordable housing, but due to set variables, the delivery of affordable housing on- site isn’t considered to be viable. A commuted sum is therefore paid in lieu of on- site affordable housing to meet local needs. A sum is negotiated and agreed between the council and the developer for the purpose of providing affordable housing on an alternative site in the local authority. 1.2 Acceptance of commuted sums had been a rare occurrence for the council, as affordable housing has generally been delivered on-site. The council had not previously set out procedures on how commuted sums in lieu of affordable housing should be calculated. The council has now received a substantial number of commuted sums within the last couple of years and there is a likelihood that in the future commuted sum payments will happen on a more regular basis due to the economic climate with high increases of labour and material costs resulting in the delivery of onsite affordable housing becoming less financially viable which will lead to the total value of commuted sum continuing to grow. 1.3 The requirement for a commuted sum to be paid in lieu of on-site delivery of affordable housing is secured via S.106 planning agreements. Negotiations between the local planning authority and the developer of a site will usually take place at early pre-planning stage 1.4 The collection, monitoring, reporting and assignment of S106 affordable housing contributions is now at a stage where the processes would benefit from being refined and more structured like with other Kent Council authorities, such as Sevenoaks District Council and Ashford Borough Council
2. Current position of contributions 2.1 The current economic climate poses greater challenges in site viability, as such, there is a greater emphasis on utilising collected commuted sums to meet council objectives to deliver more affordable housing throughout the borough. 2.2 Commuted sums, therefore, provide a valuable opportunity for the council to ensure that where delivery of affordable housing on a site isn’t viable, alternative provisions can contribute towards the councils’ aims of delivering and facilitating more affordable housing to meet local needs. 2.3 The council currently holds a total of £5.083 m in affordable housing contributions. Many of these contributions do not have a date specified within the planning agreement by which they must be spent. Where a date has been specified for the contributions to be spent, these range from April 2027 through to August 2031.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.