RESOLVED – 1. That the summary of project performance over quarter one, 2023/24 at Appendix A be noted. 2. That the summary of service performance over quarter one, 2023/24 at Appendix B be noted. 3. That the Recovery Plans for quarter one, 2023/24 at Appendices C-E be noted. REASON FOR DECISION: To monitor the effectiveness of the Council’s actions and plans to meet all of the objectives within the Five-Year Plan, highlight underperforming areas, and propose actions to remedy any underperformance to ensure the key objectives are met
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Projects Summary and Build a Better Borough Projects
Q1 2023/24 (April-June 2023) Five Year Plan Projects
1. Project Create a new Local Plan for the Borough.
Status AMBER The Local Plan has been submitted to the Secretary of State for Examination, in accordance with the latest timetable. A Planning Inspector has been appointed to undertake the Examination. Examination Hearings were held in March and between May and July 2022. This varies slightly from the published timetable in the Local Development Scheme (October 2021) which had considered that these would be completed by April. The Council has now received the Inspectors post-hearing Initials Findings letter which raises a number of matters that need resolving in order that the Local Plan can progress on to adoption. Officers are working on the matters with consultants and stakeholders and will present an update to members when the work is completed, which will be after the May elections. A review of
Tunbridge Wells Borough Council Projects Summary Page Date of publication – September 2023 1 of 6 Revision: 2 the Local Development Scheme will be undertaken at the same time to set the timetable for the adoption of the Local Plan. As a result of these additional requirements and the need for additional post hearing further work adoption of the Local Plan has been delayed.
2. Project Create new sports facilities for the Borough.
Status GREEN
Update Currently awaiting outcome of Local Plan examination. From the Inspector’s Initial Findings letter no issues of principle were raised with respect to the sport pitches policies. With regards to Hawkenbury Recreation Ground (Policy AL/RTW 19) the Inspector concluded it would be appropriate to consult on the road widening and re-provision of parking spaces that had been provided in a later evidence document provided to the Hearing.
Tunbridge Wells Borough Council Page Projects Summary 2 of 6 Date of publication – September 2023 Revision: 2 3. Project Support the development of community centres in the borough: Cranbrook
Status AMBER
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.