RESOLVED – 1. That the actual gross and net expenditure for the year and the sources of finances as shown in Appendices B to D be noted. 2. That the proposed variations to the Capital programme set out in notes 4.3 to 4.10 be approved. 3. That the inclusion of new schemes into the Capital programme as set out in notes 4.11 to 4.17 be approved. 4. That the proposed movement between years set out in note 4.18 be approved. REASON FOR DECISION Managing and forecasting capital expenditure effectively was vital in order to support all of the services provided by the Council.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Officer / Committee recommendations as supported by the Portfolio Holder: 1. That Cabinet note the actual gross and net expenditure for the year and the sources of finance, as shown in Appendices B to D. 2. That Cabinet approve the proposed variations to the Capital programme, set out in notes 4.3 to 4.10. 3. That Cabinet approve the inclusion of new schemes into the capital programme as set out in notes 4.11 to 4.17.
Page Tunbridge Wells Borough Council 1 of 11 Capital Management: Quarter 2 (to 30 September 2023) 4. That Cabinet approve the proposed movement between years set out in note 4.18.
Page Tunbridge Wells Borough Council 2 of 11 Capital Management: Quarter 2 (to 30 September 2023) 1. Introduction and Background 1.1 This report summarises the actual and forecast outturn expenditure on capital schemes as at the 30 September 2023. The total capital expenditure is forecast to be £18,536,000, a net decrease of £547,000 from the previously approved budgets. This consists of a decrease of £2,151,000 in spending rescheduled to 2023/24 and a net increase in the forecast projected spend of £1,604,000.
2. Capital Management to 30 September 2023 2.1 At their meeting on 23 March 2023, Cabinet approved schemes to be met from the Capital Programme for the years 2023/24 to 2025/26. 2.2 The figures approved by Cabinet were on the basis of the net cost after specific funding to be met by the Council, either from reserves or from the sale of existing assets. The total approved spending was £16,984,000 during that period, of which £12,594,000 was to be spent during 2023/24. 2.3 As shown in Appendix A, the approved programme for 2023/24 moved to £21,956,000 by the end of the 2022/23 financial year, accounting for new schemes, deletions and deferrals into future years and was approved by Cabinet on 22 June 2023. 2.4 As the Capital Programme is a 4 year rolling plan an additional £1,280,000 has been included for approval for 2026/27. This consists of Disabled Facilities Grants and Housing Renewal advances. 2.5 New movements for 2023/24 are now forecasting an outturn of £18,536,000. 2.6 Appendices B and C set out in gross and net terms the actual spend and amounts approved against the forecast outturn to 31 March 2024, while Appendix D summarises the movement in approvals and in sources of finance for the year. 2.7 Approval is sought for a net increase in the capital programme of £1,521,000 for 2023/24 to 2026/27 (see note 4.3 to 4.17). 2.8 Approval is also sought for £2,151,000 gross expenditure to be deferred into 2024/25 and 2025/26 (see note 4.18). 2.9 There may be small differences in the figures within the report and appendices due to rounding.
Page Tunbridge Wells Borough Council 3 of 11 Capital Management: Quarter 2 (to 30 September 2023) 3. Options Considered 3.1 Retain the approved rolling capital programme as at the end of Quarter 1 2023/24. This would not reflect delays, advancements, underspends or new schemes and therefore provide an inaccurate forecast to the end of the financial year. 3.2 Amend the rolling capital programme to reflect changes since the end of Quarter 1 2023/24. These projections help to manage the public finances effectively which support the objectives and priorities of the Council.
4. Preferred Option and Reason
New Budget Approvals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.