RESOLVED – 1. That the summary of project performance over quarter two 2023/24 as at Appendix A be noted. 2. That the summary of service performance over quarter two 2023/24 as at Appendix B be noted; and 3. That the Recovery Plans for quarter two 2023/24 as at Appendices C-D be noted. REASON FOR DECISION: To monitor the effectiveness of the council’s actions and plans to meet all of the objectives within the Five- Year Plan, highlight underperforming areas, and propose actions to remedy any underperformance to ensure the key objectives are met.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Projects Summary and Build a Better Borough Projects
Q1 2023/24 (July-Sept 2023) Five Year Plan Projects
1. Project Create a new Local Plan for the Borough.
Status AMBER The Local Plan has been submitted to the Secretary of State for Examination, in accordance with the latest timetable. A Planning Inspector has been appointed to undertake the Examination. Examination Hearings were held in March and between May and July 2022. This varies slightly from the published timetable in the Local Development Scheme (October 2021) which had considered that these would be completed by April. The Council has now received the Inspector’s post-hearing Initials Findings letter which raises a number of matters that need resolving in order that the Local Plan can progress on to adoption. Officers are working on the matters with consultants and stakeholders and will present an update to members when the work is completed, which will be at the end of 2023. A review of the
Tunbridge Wells Borough Council Projects Summary Page Date of publication – November 2023 1 of 6 Revision: 9 Local Development Scheme will be undertaken at the same time to set the timetable for the adoption of the Local Plan. As a result of these additional requirements and the need for additional post hearing further work adoption of the Local Plan has been delayed.
2. Project Create new sports facilities for the Borough.
Status GREEN
Update We are awaiting the outcome of the Local Plan examination. No issues of principle were raised with respect to sport pitches policies. With regard to Hawkenbury Recreation Ground (Policy AL/RTW 19) the Inspector concluded it would be appropriate to consult on the road widening and re-provision of parking spaces set out in a later evidence document provided to the Hearing. A revised project plan is being developed with a view to delivering the Hawkenbury Hub in two phases, with works starting initially on land in the Council’s ownership.
Tunbridge Wells Borough Council Page Projects Summary 2 of 6 Date of publication – November 2023 Revision: 9 3. Project Support the development of community centres in the borough: Cranbrook
Status AMBER
Update One of the three GPs in the consortium to deliver the community centre is therefore seeking to pass on their NHS contract due to ill health. Following negotiations with a third party the deal has fallen through and we await further news in terms of who is going to be able to take over the contract moving forward. Once this is known and if the new owner remains supportive of the community centre, the final NHS specification can then be signed off to enable the development to move ahead. In the meantime PWLB interest rates have increased significantly, leaving the financials on the project unviable at this time unless rates fall to circa 3%. While this is unlikely in the short to medium term, the parish is now looking to acquire the now closed secondary school sixth form block with a view to determining whether it could be used as a GP surgery, while a smaller community centre is delivered on the current site. The parish is considering additional options. Once confirmed, works could start on a Pre-Construction Services Agreement via the KCC framework. Feasibility picked up c£300k of risk within ground conditions. Geotechnical investigations confirmed that the risk level is low, which would have a corresponding effect on the cost of mitigation. Continuing escalation in the Bank of England interest rate may impact the project’s viability. However the rental rates for the NHS have also increased for the same reason. KCC has written to the parish confirming that they are keen to see the project progress and its support for moving the library into the community centre. KCC has committed to consulting with its Corporate Landlord to determine what degree of investment may be raised. Parish is seeking £500k in addition to all S106 funds sought to date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.