RESOLVED – That the summary of project performance over quarter three 2023/24 as at Appendix A be noted. That the summary of service performance over quarter three 2023/24 as at Appendix B be noted; and That the Recovery Plans for quarter three 2023/24 as at Appendices C-D be noted. REASON FOR DECISION: To monitor the effectiveness of the Council’s actions and plans to meet all of the objectives within the Five- Year Plan, highlight underperforming areas, and propose actions to remedy any underperformance to ensure the key objectives are met.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Projects Summary and Build a Better Borough Projects
Q3 2023/24 (Oct-Dec 2023) Five Year Plan Projects
1. Project Create a new Local Plan for the Borough.
Status AMBER The Local Plan has been submitted to the Secretary of State for Examination, in accordance with the latest timetable. A Planning Inspector has been appointed to undertake the Examination. Stage 1 and Stage 2 Examination Hearings were held last March and between May and July 2022. Following the Hearings, the Council received the Inspector’s post-hearing Initial Findings letter. This raised a number of matters that need resolving in order that the Local Plan can progress on to adoption. Officers have worked on the matters with consultants and stakeholders, and the proposed response to the Inspector’s Initial Findings was agreed at Full Council on 13 December 2023. The Local Development Scheme has been revised to set the timetable for the adoption of the Local Plan.
Tunbridge Wells Borough Council Projects Summary Page Date of publication – February 2024 1 of 5 Revision: 18 The proposed changes to the local plan are subject to consultation in February 2024. As a result of these additional requirements and the need for additional post hearing further work, adoption of the Local Plan has been delayed until late 2024.
2. Project Create new sports facilities for the Borough.
Status GREEN
Update We are awaiting the outcome of the Local Plan examination. No issues of principle were raised with respect to sport pitches policies. With regard to Hawkenbury Recreation Ground (Policy AL/RTW 19) the Inspector concluded it would be appropriate to consult on the road widening and re-provision of parking spaces set out in a later evidence document provided to the Hearing. A revised project plan is being developed with a view to delivering the Hawkenbury Hub in two phases, with works starting initially on land in the Council’s ownership.
Tunbridge Wells Borough Council Page Projects Summary 2 of 5 Date of publication – February 2024 Revision: 18 3. Project Support the development of community centres in the borough: Cranbrook
Status AMBER
Update Kent and Medway ICB have agreed on the 7th December 23 to novate the contract of the GP who is unable to commit to the project and terminate his involvement from the end of March 24. This should now enable whoever takes over the contract to commit to the new project and allows the project to now move into a Pre-Construction Services Agreement (PCSA) which is the beginning of design works. A One Public Estate grant bid was submitted for the project and it beat numerous other bids across Kent to be chosen to progress through to the second round. It seeks a £150k grant towards the PCSA and the parish have confirmed that if successful, they will then fund the remainder of the PCSA. KCC remains tentatively supportive of the project subject to further details and the full business case being put forward. In the meantime, PWLB interest rates are still high, meaning that viability remains an issue. If rates were to fall back slightly, it might make it deliverable. While this is unlikely in the short term, the medium to longer term seems to be more favourable. Once confirmed, works could start on a Pre-Construction Services Agreement via the KCC framework. Feasibility picked up c£300k of risk within ground conditions. Geotechnical investigations confirmed that the risk level is low, which would have a corresponding effect on the cost of mitigation. A sustained increase in the Bank of England interest rate may also impact the project’s viability. However, the rental rates for the NHS have also increased for the same reason. KCC has written to the parish confirming that they are keen to see the project progress and its support for moving the library into the community centre. KCC has committed to consulting with its Corporate Landlord to determine what degree of investment may be raised. Parish is seeking £500k in addition to all S106 funds sought to date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.