RESOLVED (a) that the objectives of the Trust Management Project as identified in paragraph 4.1.3 to report 78/05, be agreed; (b) that the contract term for management of Wantage Civic Hall and Abingdon Guildhall be 8½ years; (c) that it be agreed to proceed with the Trust Management Project with the service specified as it is currently provided, including the democratic function with a view to seeking tenderers proposals on the potential impact of a relocation of this function and the redevelopment of the Guildhall, Abingdon to better meet the cultural needs of the District; (d) that the Chief Executive be delegated authority, in consultation with the Executive Member with responsibility for the Leisure and Community Portfolio, to deliver the project, including the shortlistings for the procurement .
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
2.1The Executive is asked to agree the objectives of the Trust Management project as identified in 4.1.3;
2.2The Executive is asked to agree that the contract term for management of Wantage Civic Hall and Abingdon Guildhall as eight and a half years;
2.3The Executive is asked to agree to proceed with the Trust Management project with the service specified as it is currently provided, including the democratic function, with a view to seeking tenderers proposals on the potential impact of a relocation of this function and the re-development of the Guildhall to better meet the cultural needs of the District; and
2.4The Executive is asked to agree the delegation to the Chief Executive, in consultation with the Executive Member with responsibility for the Leisure and Community, to deliver the project, including the shortlisting for the procurement.
3.0Relationship with the Council’s Vision, Strategies and Policies
(a) The report relates to objectives A, C and G of the Council’s Vision
(b) The report relates to the cleaner, greener, safer and healthier environment priority
(c) The report does not contradict any Council policies
4.0Background and Supporting Information
4.1Objectives for Trust Management of Halls Procurement
4.1.1 Following the success of the transfer of the management of the leisure facilities to a Trust, SOLL (Vale) Limited, the management of the Vale’s Halls (Wantage Civic Hall and Abingdon Guildhall) was identified as a possible extension of this means of operation.
4.1.2 The Council’s budget for 05/06 identified the procurement of Trust Management for the Halls as a project to contribute to the Medium Term Financial Plan (MTFP). A figure of £75,000 was identified as a saving.
D:\moderngov\data\published\Intranet\C00000104\M00000143\AI00000537\CivicHallsProcurementofTrustManagement10.doc 1 24 August 2005 4.1.3 This saving is therefore the primary objective for the project. A broader statement of project objectives is needed. The following additional key objectives are proposed along the lines of those set for the leisure facilities exercise:
a. To maximise the potential reductions in revenue expenditure required by those services
b. To protect existing Civic Halls from the possibility of needing to make further budget reductions in the future; and
c. Subject to not compromising the primary objectives that the following further objectives be set:
i. The identification of the potential for re-siting the Vale’s democratic function and
ii. The identification of opportunities to meet a broader cultural need via the redevelopment of the Abbey Hall or other locations.
4.2Contract Term for Trust Management of Halls
4.2.1 The Council needs to determine the best contract term for the Halls’ management contract. The Council’s two facility management contracts run for ten years to: 2012 for the White Horse Leisure & Tennis Centre, and 2014 for Wantage and Faringdon Leisure Centres and Tilsley Park.
4.2.2 A balance has to be made in deciding on which term to use. A term long enough to provide an incentive to the contractor to develop and potentially invest in the facilities and services versus a contract that is too short where a contractor’s margin will be generated from reducing costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.