RESOLVED (a) that the expenditure on capital projects in the financial year 2005/06 be noted; (b) that the revised expenditure profile for capital projects and carry-forward of budgets to 2006/07 (net total £472,220), as shown in Appendix A of report 286/05, be agreed.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
(a) That Members note the expenditure on capital projects in the financial year 2005/06
(b) That Members agree the revised expenditure profile for capital projects and carry-forward of budgets to 2006/07 (net total £472,220) as shown in Appendix A.
3.0Relationship with the Council’s Vision, Strategies and Policies
(a) Vision Statement objectives A and B.
(b) The report does not conflict with any Council Strategies.
(c) The report complies with existing policies on financial management.
4.0Actual Revenue and Capital Expenditure compared to the Budget
4.1The report sets out at Appendix A the Council’s capital programme for 2005/06 to 2007/08. Details are provided of:
the revised budget for 2005/2006 agreed February 2006 the actual expenditure and income to the end of March 2006 (subject to audit), any unspent budget that the budget-holders wish to carry forward, the agreed budget for 2006/07, proposed expenditure in 2007/08 for continuing schemes.
4.2The original capital budget for 2005/06 was agreed in February 2005 at £2,805,910 with an estimated actual spend of £2,500,000. In July 2006 budget carry-forwards from 2004/2005 of £201,960 were agreed. New schemes agreed during the year amounted to £8,380,000 (£7,600,000 was for acquisition of investment properties). In February 2006 a revised capital budget for 2005/06 of £6,915,200 was agreed.
4.3The column headed “c/fwd to 2006/07 requested” contains unspent budget from 2005/06 where the officer responsible still needs to incur further expenditure to complete the scheme. Many of these sums are committed or unavoidable.
4.4There are also schemes where work has taken place earlier than expected or, for new schemes, preliminary fees or costs have been incurred. These amounts are shown as credits
D:\moderngov\data\published\Intranet\C00000104\M00000201\AI00004011\0605CapMonReportWholeCouncil0.doc 26/04/06 08:38 in the c/fwd requested column which will have the effect of reducing the original budget in 2006/07.
4.5Taken separately the expenditure budget carry forwards requested total £656,770 less grants and contributions of £157,000, less IEG grant carried forward of £4,670 and less budget pulled back from 2006/07 of £22,880 giving a net total of £472,220.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.