RESOLVED (a) that the revised capital programme for 2006/07 and revised estimated cost of £4,307,230 and amended expenditure profile where appropriate and the implications for the budget be noted; and (b) that the new capital projects be approved to be considered in the budget deliberations for 2007/08 onward.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
2.1To agree the revised capital programme for 2006/07 and revised estimated cost of £4,307,230 and amended expenditure profile where appropriate and the implications for the budget.
2.2To approve the new capital projects to be considered in the budget deliberations for 2007/08 onward
3.0Relationship with the Council’s Vision, Strategies and Policies
(a) Vision Statement objectives A and B. (b) The report does not conflict with any Council Strategies. (c) The report complies with existing policies on financial management.
4.0Programme for 2006/07 to 2008/09 and actual expenditure to date
4.1The report sets out in Appendix A the current approved Capital Programme for the Council. Details are provided of the amended budget for 2006/07 agreed May 2006 plus subsequent additions and the actual expenditure to the end of September 2006.
4.2All budget holders have been asked to critically appraise their projects and propose any revision to take account of changing needs, increased or reducing costs or revised expenditure profiles and any proposed re-phasing of the programme for 2006/07 to 2008/09. This has been done on a capital Form 1a. Any proposed, revised spend is indicated on Appendix A and identified in the “comments” column.
4.3Major variations in cost are: a) White Horse Leisure & Tennis Centre – Car Park Remedial Works. Y72 In carrying out the capital project to rectify the block paving defects within the car park, the Council’s consultant engineer and the contractor highlighted that the condition of the car park had degraded far quicker than had been anticipated and that repair works were far more extensive than had been allowed for within the contract. The contingency allowance included was inadequate for the extra repair work now needed. With the contractor on site, it was necessary to seek urgent authority to an increase of £60,000 in the budget. This would allow the complete relaying of the block paving on all the access lanes together with soldier courses thus inhibiting future lateral movement and could not be accommodated within the original capital budget. An urgent decision was taken by Councillor Jerry Patterson on 24 July 2006 to agree the additional works, the basis of urgency being that additional costs would have been incurred had there been a delay in extending the existing contract. 4.0 Green waste wheeled bins. Y61 The Executive resolved 6 October 2006 to extend the brown bin scheme. The budget for the original scheme has been increased for 2006/07 to enable the additional bins to be purchased. There is a bid in for 2007/08.
The rest of the difference between the current estimate for 2006/07 and the proposed revised estimate is largely accounted for by reduced cost due to changing circumstances or the slippage of part or the whole of schemes into next year.
5.0Possible Schemes for inclusion in the Programme for 2007/08 onward
5.1Form 2s for proposed new capital schemes are summarised below. Copies of the completed forms have been placed in the Members’ Lounge at Abbey House and can be discussed with the officer responsible.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.