RESOLVED : (a) To require the council’s contract monitoring officer, the contractor (DC Leisure), and the relevant Cabinet member to attend a future meeting of the Scrutiny Committee to answer questions on the contractor’s performance; and (b) To request that the monitoring report should be amended to include trend analysis on usage of the White Horse Leisure and Tennis Centre, details of the internal services’ response to the survey questionnaire, and an action plan to increase use of the centre and improve the service.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of head of economy leisure and property Report no. 5/11 Author: Chris Webb Tel: 01235 540358 E-mail: [email protected] Cabinet Member responsible: Elaine Ware Tel: 01793 783026 E-mail: [email removed] To: SCRUTINY COMMITTEE DATE: 23 June 2011
Leisure contract monitoring: performance review of DC Leisure Ltd RECOMMENDATION That the committee considers DC Leisure’s performance in delivering the leisure management contract for the period 2010/11 for the White Horse Leisure and Tennis Centre and makes any recommendations to the cabinet member for leisure to enable her to make a final assessment on performance.
PURPOSE OF REPORT 1. The report considers the performance of DC Leisure Ltd in providing the leisure management contract at the White Horse Leisure and Tennis Centre for the period 1 April 2010 to 31 March 2011.
STRATEGIC OBJECTIVES 2. The performance review of DC Leisure Ltd helps ensure that the Vale Council is achieving its strategic objectives and corporate priorities, particularly the following: strategic objective 2: managing our business effectively, and corporate priority EB1: provide value for money services that meet the needs of our residents and service users – through negotiations with DC Leisure the Vale Council has procured an extension to the existing contract, which delivers an income stream up to 2014 when the contract will be aligned with the Vale Council’s other leisure management contract. Annual customer satisfaction surveys are undertaken to monitor that
D:\moderngov\data\published\Intranet\C00000103\M00001475\AI00015881\DCLeisureRe view201020110.doc customer needs are being met and action plans put in place to address areas in need of improvement. strategic objective 2: managing our business effectively, and corporate priority EB2: optimise access to our services – by working collaboratively with DC Leisure and our various customer panels we will increase awareness of the Access to Leisure scheme. With the introduction of schemes such as Go Active into the centre’s programme, officers anticipate that new users will be encouraged to visit the centre, as well as regular users continuing to participate in activities. strategic objective 5: helping to maintain a safe Vale, and corporate priorities SV1: help to maintain, or further reduce, low levels of crime and anti-social behaviour and SV2: reduce the fear of crime and anti-social behaviour – structured leisure activities can divert people from crime and anti-social behaviour. Those participating in regular physical activity tend to have a lower fear of crime and anti-social behaviour.
BACKGROUND 3. The DC Leisure Ltd contract for the White Horse Leisure and Tennis Centre was let from 1 April 2002 for a ten year period ending on 31 March 2012. Due to improved tax benefits, the Vale Council allowed DC Leisure to sub-let the contract to a charitable not for profit organisation, the former Community Leisure Services (now known as Active Nation). Both companies were involved in the centre from the design stage. However, for the purposes of this report, DC Leisure is the main contractor and the organisation that is accountable to the Vale Council for the centre’s performance. The original contract required the Vale Council to pay DC Leisure a small annual grant.
4. In 2009/10 the Vale Council negotiated an extension to the original contract, which allows DC Leisure to continue its arrangements with Active Nation up to 31 August 2014. In return for this extension, the Vale Council receives a monthly payment from DC Leisure from 1 April 2010 until 31 August 2014. The change in end date allows all of the Vale of White Horse and South Oxfordshire leisure management contracts to run conterminously; presenting opportunities for increased shared working in the future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.