Internal audit management report - quarter 3 2012/13

Noted Finance 6 papers

Audit and Governance Committee noted this item on Wednesday 30 January 2013. Below is the council's own wording, with the papers it was decided on.

Item46

Resolved

RESOLVED : To note the report.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Audit and Governance Committee

Audit and Governance Committee Report

30 January 2013 Report of: Audit Manager Author: Adrianna Partridge Wards Affected Telephone: 01235 547615 All Telephone: 01491 823544 E-mail: [email protected] Cabinet member responsible: Councillor Matthew Barber Telephone: [phone removed] E-mail: [email protected] To: Audit and Governance Committee DATE: 30 January 2013

Internal audit management report quarter three 201 2012/2013 /2013 Recommendation

That members note the content of the report

Purpose of report 1. The purpose of this report is:

• to report on management issues within internal audit;

• to summarise the progress against the 2012/2013 audit plan up to 17 January 2013; and

• to summarise the priorities for quarter four 2012/2013.

2. The contact officer for this report is Adrianna Partridge, Audit Manager for South Oxfordshire District Council and Vale of White Horse District Council, telephone (SODC) 01491 823544 and (VWHDC) 01235 547615.

Strategic objectives

3. Managing our business effectively. Background 4. The CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the broad resources required to deliver the plan.

5. The CIPFA Code also states that the audit committee should approve the annual internal audit plan and monitor progress against the plan. This Committee approved the annual internal audit plan on 21 March 2012.

Management issues 6. Following the town and parish council forums in November, internal audit have had strong interest from three town and parish councils to provide their internal audit services from April 2013. Town and parish councillors will decide who will provide their internal audit services at their January finance committee meetings.

7. In accordance with best practice, the audit manager has completed the Audit Commission’s fighting fraud self-assessment checklist which is attached in appendix 1 for information. The assessment has been reviewed by the head of finance, section 151 officer and external audit, and identifies 5 actions which will be implemented by the audit manager.

Progress against the 2012/2013 audit plan 8. Progress against the approved audit plan has been calculated for the quarter and year to date and is summarised in appendix 2 attached.

9. Performance figures are as follows:

Target YTD Q1 Q2 Q3 Q4 12/13 12/13 12/13 12/13 Chargeable 70% 71% 71.5% 71% 68.5% 77% (identifiable client and/or specific IA deliverable) Non-Chargeable 8% 4.5% 5% 4.5% 4.5% 4.5% (corporate, not IA deliverable) Lost 22% 24.5% 23.5 24.5% 27% 18.5% (i.e. leave, study, sickness)

10. As at 17 January 2013 the status of audit work against the 2012/2013 audit plan is as follows:

Planned

Strategic, operational and financial assurance work known and approved by the Audit and Governance Committee. In progress

commence 2012/2013

Complete Planned

Draft

To PLANNED 29 16 2 3 8 Joint 26 14 1 3 8 SODC 2 2 0 0 0 VWHDC 1 0 1 0 0

Adhoc

Unplanned project work based on agreed terms of reference with the audit manager (i.e. implementation of new systems) and responsive work issued and agreed by the section 151 officer, members or senior management team (i.e. investigations).

In progress

commence Requested

2012/2013 Complete

Draft

To ADHOC 3 3 0 0 0 Joint 1 1 0 0 0 SODC 1 1 0 0 0 VWHDC 1 1 0 0 0

Follow up

Work undertaken to ensure that agreed recommendations have been implemented. The number of follow-up audits is a rolling number, all internal audit reports are followed up after six months. In progress

commence Requested

Complete

2012/2013 Draft

To

FOLLOW-UP 36 28 0 0 8 SODC 16 12 0 0 4 VWHDC 20 16 0 0 4

Priorities for 2012/2013 quarter three (October 2012 – December 2012)

11. The priority for quarter three is to: • review the money laundering control environment; and

• to prepare the audit plan 2013/2014.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Progress Against Audit Plan 2012-13: Follow-up auditsAppendix 2 13 KB Download
PDF
Progress Against Audit Plan 2012-13: Planned auditsAppendix 2 18 KB Download
PDF
Progress Against Audit Plan 2012-13: Unplanned auditsAppendix 2 11 KB Download
PDF
Audit Plan Schedule 2012-13Appendix 3 25 KB Download
PDF
IA Mgt Appendix 1: Audit Commission fighting fraud self-assessmentAppendix 68 KB Download
PDF
Internal audit management report: quarter 3 2012/13Report 57 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 24 attended
MB
Councillor Mike BadcockCommittee Member, present
MB
Councillor Matthew BarberGuest, in attendance
SB
Sandy BayleyOfficer, present
SB
Steve BishopOfficer, present
JB
Jayne BoltonOfficer, present
JB
Councillor Julia BricknellCommittee Member, present
AC
Councillor Andrew CrawfordCommittee Member, present
SC
Steve CullifordOfficer, present
AF
Angus FaukesGuest, in attendance
DH
Councillor Dudley HoddinottCommittee Member, present
SH
Councillor Simon HowellVice-Chair, present
WJ
William JacobsOfficer, present

All 24 on the meeting page

On this subject at Vale of White Horse

Search all
  1. Internal audit management report - quarter 3 2012/13This decision
  2. Internal audit management report quarter four 2014/15Noted
  3. Internal audit plan 2015/16Approved
  4. Internal audit management report quarter three 2014/2015Noted
  5. Internal Audit activity report - second quarter 2014/15Noted
  6. Internal Audit management report - second quarter 2014/15Noted

More from Vale of White Horse Audit and Governance Committee

All decisions
MeetingDecisionOutcome
19 Mar 2015 Actions arisingRESOLVED : to retain the following items on the actions arising list: · To call the Building Control manager to a fut... Decided Open
19 Mar 2015 Internal audit management report quarter four 2014/15RESOLVED : to note the internal audit management report for the fourth quarter 2014/15. Noted Open
19 Mar 2015 Internal audit plan 2015/16RESOLVED : to approve the internal audit plan 2015/16. Approved Open
22 Jan 2015 Minutesto defer the approval of the minutes of the meeting held on 24 September 2014 as a correct record and to agree that t... Deferred Open
22 Jan 2015 Actions arisingto retain the amended procedure for monitoring systemic control weaknesses on the actions arising list for one more m... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies