RESOLVED To support the recommendation of the officers’ recommendation of Good for Biffa’s performance for 2016. Action Points Provide benchmarking against other councils Schedule on deep cleansing in inFocus . Put recycling guide on the internet?
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of Chief Executive Author: Ian Matten Tel: 01235 422113 E-mail: [email protected] Vale Cabinet Member responsible: Charlotte Dickson South Cabinet Member responsible: Tony Harbour Tel: 01235 767848 Tel: 01235 810255 E-mail: [email protected] E-mail: [email protected] To: JOINT SCRUTINY COMMITTEE DATE: 22 MAY 2017
Performance review of Biffa Municipal Limited - 2016 RECOMMENDATION That scrutiny committee considers Biffa Municipal Limited’s (Biffa) performance in delivering the household waste collection, street cleansing and ancillary services contract for the period 1 January 2016 to 31 December 2016 and makes any comments before a final assessment on performance is made.
PURPOSE OF REPORT 1. To ask scrutiny committee for its views on the performance of Biffa in providing the household waste collection, street cleansing and ancillary services in South Oxfordshire and the Vale of White Horse for the period 1 January 2016 to 31 December 2016.
STRATEGIC OBJECTIVES 2. The service contributes to Vale’s strategic objective of running an efficient council and continue to improve our environment and South’s objective of delivering services that reflect residents needs and making communities clean and safe. BACKGROUND 3. Managing contractor performance is essential for delivering the council’s objectives and targets. Since a high proportion of the council’s services are outsourced, the council cannot deliver high quality services to its residents unless its contractors are performing well. Using an agreed framework and working jointly with contractors to review performance regularly is therefore essential.
4. The council’s process for managing contractor performance focuses on continuous improvement and action planning. The council realises that the success of the framework depends on contractors and the council working together to set and review realistic, jointly agreed and measurable targets.
5. The overall framework is designed to be
a way for the council to consistently measure contractor performance, to help highlight and resolve operational issues
flexible enough to suit each contract, including smaller contracts which may not require all elements of the framework
a step towards managing risk more effectively and improving performance through action planning.
OVERVIEW OF THE REVIEW FRAMEWORK 6. Evaluating contractor performance has four elements:
1. performance measured against key performance targets (KPT) 2. customer satisfaction with the total service experience 3. council satisfaction as client 4. a summary of strengths and areas for improvement, feedback from the contractor on the overall assessment plus the contractor’s suggestions of ways in which the council might improve performance.
7. The first three dimensions are assessed and the head of service makes a judgement of classification. The fourth element is a summary of strengths and areas for improvement and includes contractor feedback. Where some dimensions are not relevant, or difficult to apply fairly to certain types of contract, the framework may be adjusted or simplified at the discretion of the head of service.
8. A summary of officer’s assessment for 2016 for each dimension, the overall assessment and a comparison against 2015 can be seen in the following table:
2015 2016
Key Performance Target Good Fair
Customer satisfaction Good Good
Council satisfaction Good Good Overall officer assessment Good Good
9. Biffa were awarded the joint waste contract in December 2008 with a commencement date in South Oxfordshire of June 2009. The Vale of White Horse element of the contract commenced in October 2010. The council in 2013 decided, in accordance with the conditions of contract to extend the contract for a seven year period. The contract is now due to end in June 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.