RESOLVED to: (a) approve the procurement process to appoint a main contractor in respect of the White Horse Leisure and Tennis Centre and Wantage Leisure Centre Salix Phase 3b decarbonisation projects following a two-stage procurement process; (b) authorise the head of development and corporate landlord, in consultation with the head of finance and the Cabinet member for finance and property, to award the first stage Pre-construction Services Agreement following the completion of satisfactory design to Royal Institute of British Architects (RIBA) stage 4; and (c) authorise the head of finance, in consultation with the relevant head of service under the constitution, to tender and award the contract for stage 2 (a Joint Contracts Tribunal (JCT) design and build contract) to the most economically advantageous tenderer within up to a five per cent variation of the allocated budget approved by Council.
Word for word from the decision Vale of White Horse published for this meeting.Source: democratic.whitehorsedc.gov.uk
Report of Head of Development and Corporate Landlord – Andrew Busby Author: Ben Whaymand – Leisure Facilities Team Leader Telephone: [phone removed] Textphone: N/A E-mail: [email protected] Wards affected: Wantage and Abingdon Vale Cabinet member responsible: Cllr Andy Crawford - Cabinet member for finance and property Tel: [phone removed] E-mail: [email protected] To: CABINET Dates: Friday 8 March 2024
White Horse Leisure &Tennis Centre and Wantage Leisure Centre Salix Phase 3b Decarbonisation Projects Recommendations (a) To approve the procurement process to appoint a main contractor in respect of the White Horse Leisure and Tennis Centre and Wantage Leisure Centre Salix Phase 3b decarbonisation projects following a two-stage procurement process.
(b) To delegate to Head of Development and Corporate Landlord in consultation with the Head of Finance and with the Cabinet Member for Finance and Property to award the first stage Pre-construction Services Agreement following the completion of satisfactory design to Royal Institute of British Architects (RIBA) stage 4.
(c) To delegate to Head of Finance in consultation the relevant Head of Service under the constitution to tender and award the contract for Stage 2 (a JCT Design and Build contract) to the most economically advantageous tenderer within up to a five per cent variation of the allocated budget approved by Council. Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Yes Yes No
Signing off Anna Winship Pat Connell Jessie Fieth Equalities team officer
Purpose of report 1. To seek Cabinet approval to award of a main contractor in respect of the White Horse Leisure and Tennis Centre and Wantage Leisure Centre Salix Phase 3b decarbonisation projects following a two-stage procurement process by way of delegated authority to the Head of Development and Corporate Landlord in consultation with the Head of Finance and the Cabinet Member for Finance and Property.
Corporate objectives 2. “To tackle the Climate Emergency” to “Build Stable Finances”, and to support “Building Healthy Communities”.
Background 3. The Public Sector Decarbonisation Scheme (PSDS) Phase 3b was announced by Government on 2 August 2022. This scheme allows local authorities and other public sector bodies to apply for funding to install low carbon heating systems at sites where the heating systems are end of life.
4. The Council submitted a bid to install air source heat pumps and solar energy at two sites, WHLTC and WLC with insulation, glazing and pump motor improvements where required.
5. Following a successful bid process, a Grant Offer Letter (GOL) dated 16 January 2023 confirmed that the Department for Energy Security and Net Zero has made funding available of £5,992,916 to enable Salix Finance to assist Vale of White Horse District Council’s decarbonisation programme by carrying out both projects at the White Horse Leisure and Tennis Centre (WHLTC) and Wantage Leisure Centre (WLC).
6. The PSDS also required the council to cover the cost of a like for like fossil fuel heating system or a minimum of 12 per cent of scheme costs, whichever is the higher. The like for like cost for the combined Vale sites is around ten per cent of scheme costs, therefore a small additional council contribution was required to meet this criterion.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.