White Horse Leisure & Tennis Centre and Wantage Leisure Centre Salix Phase 3b Decarbonisation Projects

Approved Committee 1 paper

AI summaryVale of White Horse Council approves £440,000 S106 top-up and £866,375 CIL reallocation to complete the Wantage Leisure Centre decarbonisation project and avoid repaying a government grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo complete Salix Phase 3b decarbonisation works at Wantage Leisure Centre
Money£440,000 plus £866,375 CIL
What happens nextPractical completion of both projectsWLC and WHLTC targeted for November 2025; UKSPF elements by 31 March 2026
Who it affectsWantage and Abingdon wards

What was decided

Council approved a supplementary budget of £440,000 from additional S106 contributions for the Wantage Leisure Centre Phase 3b Decarbonisation Project. Report P4

Council approved the use of £866,375 in underspent CIL contributions from the White Horse Leisure and Tennis Centre project to fund the Wantage Leisure Centre works. Report P4, P11

Council approved the use of £231,060 of the 2025/26 UK Shared Prosperity Fund allocation to support the White Horse Leisure and Tennis Centre project, and delegated authority to the head of development and corporate landlord to allocate further S106 and CIL funds as needed. Report P5, P6, P9, P10

Why

Around 80 per cent of the Wantage Leisure Centre project is complete, but unforeseen issues, including water damaged roofing, outdated wiring and the need for a new air handling unit in a 1976 building, have pushed costs over the original budget. Report P8, P13, P25

If the council did not approve the additional funding, it would risk having to stop the project and repay the Salix grant received. Report P13, P58

The completed upgrades are expected to cut carbon emissions at Wantage Leisure Centre by up to 65 per cent and lower energy bills. Report P13, P56

What happens next

Practical completion of both leisure centre projects is targeted for November 2025, with the new electricity connection at White Horse Leisure and Tennis Centre scheduled for October to November 2025. Report P15

Officers will work through claims with Oxfordshire County Council for its 50 per cent share of variation costs, with repayment due during 2026/27. Report P14, P27

Any UK Shared Prosperity Fund-funded elements at White Horse Leisure and Tennis Centre must be practically completed by 31 March 2026. Report P10, P61

The money

  • £440,000 Additional S106 budget sought for Wantage Leisure Centre completion Report P4, P12
  • £866,375 Underspent CIL funding reallocated from WHLTC to WLC Report P4, P11, P26
  • £231,060 2025/26 UK Shared Prosperity Fund allocation to support WHLTC Report P6, P9, P50
  • £5,992,916 Salix PSDS Phase 3b grant award from Department for Energy Security and Net Zero Report P17
  • £2,154,831 Vale of White Horse financial commitment funded via CIL and OCC contributions Report P18
  • £572,252 OCC contribution for 50 per cent share of roof works at WLC Report P24, P26
  • £286,126 OCC 50 per cent share of council funds allocated prior to £440,000 shortfall Report P27
  • £1,382,882 Budget shortfall for roof works at WLC Report P24
  • £303,000 Additional contingency required for variation items at WLC Report P38
  • £104,046 Original project contingency for WLC Report P25, P38
  • £46,266 Annual revenue savings at WLC from decarbonisation Report P48
  • £92,765 Annual revenue savings at WHLTC from decarbonisation Report P48
  • £699,276 Total S106 secured and sought for the Wantage LC project Report P79

Options considered

  • Chosen: Approve additional S106, reallocate CIL, and use UKSPF to complete the project. Ensures practical completion within the Salix grant timelines and avoids repaying the grant Report P43, P44
  • Rejected: Do not fund the shortfall and terminate the project. 80 per cent of works are already complete and termination would risk losing the Salix grant Report P44

Implications

  • Financial: Oxfordshire County Council, as joint tenant, must meet 50 per cent of variation costs and 50 per cent of the £440,000 shortfall, with repayment due in 2026/27. Report P14, P27
  • Financial: Completed projects are forecast to deliver annual revenue savings of £46,266 at WLC and £92,765 at WHLTC. Report P48
  • Legal: The council is bound by the Salix grant terms; any overspend outside the Project Programme must be met from its own funds unless Salix agrees otherwise. Report P51, P52, P53, P54
  • Climate: Up to 65 per cent carbon reduction at WLC and an estimated 25 per cent reduction across the council's assets. Report P13, P56
  • Equalities: Officers have assessed no equalities implications at this stage of the project. Report P57
  • Risk: Failure to approve funding would breach grant conditions and could leave the council liable to reimburse Salix funding already received. Report P58

Who and where

  • Users of Wantage Leisure Centre and White Horse Leisure and Tennis Centre Report P2, P15
  • Oxfordshire County Council, as joint tenant and 50 per cent cost contributor Report P14, P19, P21
  • Residents of Wantage and Abingdon wards Report P2
  • Ashe Construction Ltd, main contractor under a JCT Design and Build contract Report P23, P24

Timeline

  • 16 January 2023: Salix Grant Offer Letter received for £5,992,916 of PSDS Phase 3b funding Report P17
  • 20 January 2023: ICMD approved to accept the Salix grant and commit £2,154,831 of council funds Report P18
  • 8 March 2024: Cabinet approved award of main contractor contract via delegated authority Report P22
  • 29 November 2024: Cabinet approved additional S106 funds for WLC roofing works Report P16, P68
  • 18 December 2024: Council approved additional budget of £1,144,504 for WLC roof works Report P24, P69
  • 10 October 2025: Cabinet considered the Phase 3b report and recommended it to Council Report P2
  • 22 October 2025: Council approved the supplementary budget, CIL reallocation and UKSPF use
  • October to November 2025: New electricity supply connection scheduled at WHLTC Report P15
  • End of November 2025: Targeted practical completion of WHLTC works programme Report P15
  • November 2025: Targeted practical completion of WLC within Salix PSDS Phase 3b deadlines Report P15
  • 31 March 2026: Deadline for practical completion of UKSPF-funded elements at WHLTC Report P10, P61
  • 2026/27: OCC repayment of its share of costs due Report P14

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
  • S106: Section 106 planning obligation contributions from developers for local infrastructure
  • PSDS: Public Sector Decarbonisation Scheme, a government grant programme for public buildings
  • Salix Finance: Government-funded organisation that provides interest-free loans and grants for public sector decarbonisation
  • UKSPF: UK Shared Prosperity Fund, a central government funding programme for local investment
  • ICMD: Individual Cabinet Member Decision
  • AHU: Air Handling Unit, a building services system that circulates and conditions air
  • DNO: District Network Operator, the company licensed to distribute electricity in an area
  • VWHDC: Vale of White Horse District Council
  • OCC: Oxfordshire County Council, joint tenant at Wantage Leisure Centre
  • JCT: Joint Contracts Tribunal, a standard form of construction contract used in the UK
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item134

Resolved

To approve a supplementary budget of £440,000 from additional S106 contributions and the utilisation of £866,375 in underspent CIL contributions from the White Horse Leisure and Tennis Centre (WHLTC) for works at Wantage Leisure Centre (WLC) Phase 3b Decarbonisation Project, in accordance with 75(c) of the Council’s Financial Procedure Rules.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Council

Cabinet Report

Report of Head of Development and Corporate Landlord Author: Ben Whaymand – Leisure Facilities Team Leader Telephone: [phone removed] E-mail: [email protected] Wards affected: Wantage and Abingdon Vale Cabinet member responsible: Cllr Andy Crawford E-mail: [email protected] To: CABINET Dates: 10 October 2025

Wantage LC and Whitehorse Leisure Tennis Centre Salix Phase 3b Decarbonisation Projects Recommendations To recommend to Council:

(a) To approve a supplementary budget of £440,000 from additional S106 contributions and the utilisation of £866,375 in underspent CIL contributions from the White Horse Leisure and Tennis Centre (WHLTC) for works at Wantage Leisure Centre (WLC) Phase 3b Decarbonisation Project, in accordance with 75(c) of the Council’s Financial Procedure Rules.

(b) To delegate authority to the Head of Development and Corporate Landlord, in consultation with the Head of Finance, to allocate additional S106 contributions and CIL funds for WLC, as necessary and subject to financial procedures rules to enable practical completion of the project.

(c) That £231,060 of the current 2025/26 UK Shared Prosperity Fund (UKSPF) allocation is used to support the project at WHLTC.

Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Only grant Yes No issues as set out in report Signing off Anna Winship Nick Bennett Heather N/A officer Saunders Purpose of report 1. The council is delivering major energy efficiency upgrades at Wantage Leisure Centre (WLC) and White Horse Leisure and Tennis Centre (WHLTC) as part of its commitment to reduce carbon emissions. These works are funded through a government grant from Salix Finance, supported by local developer contributions (S106 and Community Infrastructure Levy CIL) and funding from Oxfordshire County Council (OCC).

2. At WLC, around 80 per cent of the project is already complete, but unforeseen issues, such as water damaged roofing, outdated wiring, and the need for a new air handling unit have resulted in the project’s forecasted costs exceeding budget. These were unknown challenges that have occurred whilst upgrading infrastructure to a building constructed c. 1976. To complete the project, officers are proposing:

• To use £231,060 of the council’s 2025/26 UKSPF allocation for 2025/26 towards the project at WHLTC.

• To recommend use of UKSPF funding to help meet project costs at WHLTC. Project elements funded by UKSPF must be practically completed by 31 March 2026 and deliver a demonstrable reduction in emissions.

• To reallocate £866,375 of CIL funding originally set aside for WHLTC, which is forecast to be underspent (includes UKSPF allocation from financial years 2024/25 and 2025/26) to WLC.

• To recommend that council approve an additional budget of £440,000 from S106 funds for the completion of works at Wantage Leisure Centre (WLC) for the Salix Phase 3b decarbonisation project. This budget is required to provide additional project contingency funds to complete the final stages of the project at WLC, through to the practical completion stage.

3. These changes will ensure the projects are completed on time and in line with the grant conditions. If the council does not approve the additional funding, it risks having to stop the project and repay the grant. Once finished, the upgrades will reduce carbon emissions at WLC by up to 65 per cent, lower energy bills, and improve the building for future use.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
White Horse Leisure & Tennis Centre and Wantage Leisure Centre Salix Phase 3b Decarbonisation ProjectsReport 479 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

31 of 42 attended
PB
Phil BarkerCouncil Staff, expected
BB
Becky BinsteadSecretary, expected
NB
Nick BennettCouncil Staff, expected
KB
Councillor Kiera BentleyCommittee Member, present
RB
Councillor Ron BatstoneCommittee Member, apologies
CB
Councillor Cheryl BriggsCommittee Member, apologies
SC
Councillor Sue CaulCommittee Member, apologies
RC
Councillor Robert CleggCommittee Member, present
MC
Councillor Mark ColemanCommittee Member, present
AC
Councillor Andy CookeCommittee Member, present
JC
Councillor James CoxCommittee Member, present
AC
Councillor Andy CrawfordCommittee Member, present

All 42 on the meeting page

On this subject at Vale of White Horse

Search all
  1. White Horse Leisure & Tennis Centre and Wantage Leisure Centre Salix Phase 3b Decarbonisation ProjectsThis decision
  2. White Horse Leisure & Tennis Centre and Wantage Leisure Centre Salix Phase 3b Decarbonisation ProjectsDecided
  3. Progress towards net zero in Vale of White Horse reportNoted
  4. Response to the Local Government Boundary Commission's Warding Proposals for Vale of White HorseAgreed
  5. Joint South Oxfordshire and Vale of White Horse Waste and Street Cleansing Vehicle Procurement StrategyNoted
  6. White Horse Leisure and Tennis Centre and Wantage Leisure Centre - Salix Phase 3b Decarbonisation ProjectsApproved

More from Vale of White Horse Council

All decisions
MeetingDecisionOutcome
17 Jun 2026 South and Vale Local Development Schemea) To approve the revised Local Development Scheme, June 2026. b) To delegate the making of minor updates to the Join... Approved Open
17 Jun 2026 South and Vale Joint Local Plan 2045 (JLP2)to a) Agree, subject to the agreement of South Oxfordshire District Council, preparation of the next Joint Local Plan... Agreed Open
17 Jun 2026 Independent Persons - Proposed Extension to Term of OfficeTo appoint Mike Boon, Julie Byron, George Green, Andrew Mills-Hick, Chris Smith and Martin Wright as Independent Pers... Decided Open
17 Jun 2026 Appointments to committees, panels and joint committees for 2026/27that for the 2026/27 municipal year to: 1. Appoint the following committees and panels for the 2026/27 municipal year... Decided Open
17 Jun 2026 Councillors' allowances schemethat Council: 1. Accepts the recommendation of the Joint Independent Remuneration Panel; 2. Authorises the director o... Decided Open