Resolved
Cabinet noted the contents of the report
Cabinet noted this item on Friday 18 October 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet noted the contents of the report
Cabinet Report Report of Head of Finance Author: Anna Winship Telephone: [phone removed] E-mail: [email protected] Wards affected: All South Cabinet member responsible: Andrew Crawford Tel: [phone removed] E-mail: [email protected] To: CABINET Date: 18 October 2024
Budget monitoring April 2024 – June 2024 Recommendation Cabinet is recommended to note the contents of the report
Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes/No Yes/No Yes/No Yes/No
Signing off Anna Winship Vivien Jessie Fieth Lorne Grove officer Williams
Purpose of report 1. To report the revenue and capital expenditure outturns for March 2025 as forecasted by heads of service.
Corporate objectives 2. The allocation of financial resources within the revenue and capital budgets needs to match the objectives agreed by the council. The budget monitoring report shows how these resources have been allocated during the first three months of the financial year.
Background 3. This report reviews the council’s revenue and capital expenditure forecast outturn as at the end of month three (June). While some consideration has already been given to year-end outturn forecasts, these will be placed under further scrutiny as the financial year progresses. Revenue budget monitoring
4. On 21 February 2024, Council agreed a net revenue budget for 2024/25 of £22.340 million. This has subsequently increased to £23.172 million. This reflects the carry forward of unspent one-off project budgets from 2023/24.
5. Table 1 below shows, summarised at service level, the current forecast position at year end.
Table 1: Breakdown of forecast variance as at June 2024
Working Forecast Variance Employee Other budget full spend for costs Service year year
£000 £000 £000 £000 £000 Corporate Management Team 1,132 1,132 0 0 0 Communities 1,864 1,864 0 0 Corporate Services 3,586 3,586 0 0 0 Development & Corporate Landlord 1,597 1,637 41 81 (40) Finance 1,038 904 (134) 0 (134) Housing & Environment 7,268 7,830 563 44 518 Legal & Democratic 1,538 1,538 0 0 0 Partnerships 2,493 2,493 0 0 0 Planning 555 555 0 0 0 Policy & Programmes 2,301 1,969 (332) 18 (350) Contingency (200) (200) 0 0 0 Service Expenditure 23,172 23,309 137 143 (6) Investment Income (5,005) (6,339) (1,334) 0 (1,334) Net Expenditure 18,168 16,970 (1,197) 143 (1,340)
6. The projected overspend is forecast to be £0.137 million. Treasury income achieved in year however is anticipated to be ahead of budget by £1.334 million and net expenditure is therefore forecast to be under budget. The effective net position of the council is therefore an underspend of £1.340 million.
Budgets forecast to be carried forward to 2025/26
7. At this early stage in the financial year, managers have not yet formally identified any forecast slippage into 2025/26. Whilst described as slippage, the majority of any sums identified will likely represent multi-year grant awards or ring-fenced funding, where there is planned expenditure for future years, but the terms of the grant require it to be included within the budget each year, until spent in line with the grant conditions.
Employee costs
8. As at the end of June 2024, employee costs are forecast to be overspent by £143,000. Key employee forecast variances are as follows:
• Development and Corporate Landlord is forecasting an overspend within Commercial Property to contribute to costs being incurred in South on agency surveyors who are needed to input into high priority corporate projects. • Housing and Environment is forecasting an overspend within the Homelessness service as a result of there being an additional member of staff above budget in South.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarter 1 Budget Monitoring Report 2024/25Report | 131 KB | DownloadRead as text |
Follow Cabinet at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Jul 2026 | MinutesThe minutes of the Cabinet meeting on 5 June 2026 were agreed as a correct record and the chair would sign them as such. | Agreed | Open |
| 3 Jul 2026 | Business Rates – Local Discretionary Relief scheme for 2026/2027That Cabinet (a) Approves the introduction of a local discretionary relief scheme, providing further relief for eligi... | Approved | Open |
| 3 Jul 2026 | At the Heart of the Vale: Annual Delivery Plan End of Year Report 2025-26That cabinet approves the Annual Delivery Plan End of Year Report 2025-26. | Approved | Open |
| 3 Jul 2026 | Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThat Cabinet: · Notes the establishment of a partnership with the councils covering Oxfordshire, Berkshire and Swindo... | Decided | Open |
| 3 Jul 2026 | Revised Land and Property Asset Disposal PolicyRESOLVED : That Cabinet (a) Approves the revised Joint Property Asset Disposal policy. (b) Approves the revised Joint... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.