Vale of White Horse District Council
Council, Wednesday 22 October 2025 at 7.00pm

Haseley Trading Estate

Decided Committee 1 paper

AI summaryVale of White Horse Council approves extra £2.3m for Haseley waste vehicle depot, taking its share of the joint budget to about £7.95m of a £15.9m total.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCouncil approved £2.3m increase to capital budget
Money£15.9m total, £7.95m Vale share£2.3m added to £13.7m previous envelope
What happens nextAward design and build contractSubject to Council approval of budget rise
Who it affectsWaste collection services across both councilsJoint project with South Oxfordshire District Council

What was decided

Council approved increasing the capital budget envelope by £2.3m to a total of £15.9m, with 50 per cent being the council's share of delivering the waste vehicle depot. Report P6

The contract for design and build is to be awarded to the preferred bidder, who was the only compliant tenderer, subject to the budget increase being agreed. Report P7, P31, P70

Delegated authority was given to the Head of Development and Corporate Landlord to negotiate a direct contract with the District Network Operator and to secure a contingency depot if needed. Report P8, P9

Why

A new depot is needed because the current Culham Number One site is leased from Biffa and is being redeveloped, and neither council owns a waste vehicle depot. Report P22, P23

Costs have risen due to enabling and asbestos works, higher stamp duty, planning and Section 278 works, biodiversity net gain, an electricity network upgrade, and a higher design and build bid than expected. Report P43, P56

Only one of five design and build bids was compliant, and its price of about £7.5m exceeds the original £5.507m construction budget but includes work previously excluded. Report P28, P30, P31

What happens next

Complete contractor procurement by early November 2025, with construction planned from 1 December 2025 to 24 July 2026 and handover between 13 and 24 July 2026. Report P38, P40, P41

Await the planning decision, now expected at South Planning Committee on 8 October 2025, with a verbal update to be given. Report P26, P36

Officers will continue to update members on delivery progress and report back if a contingency depot lease is needed. Report P42, P73

The money

  • £2.3m Increase to the capital budget envelope for the depot project Report P6
  • £15.9m New total capital budget envelope across both councils Report P6, P56
  • £7.95m Vale of White Horse share, being 50 per cent of the total Report P71
  • £13.7m Previous capital budget envelope approved in December 2024 Report P43, P56
  • £5,500,000 Capital cost of purchasing the Haseley site Report P47
  • £9,832,555 Updated projected cost to make the site operational Report P48
  • £200,000 Updated estimate for biodiversity net gain, including off-site mitigation Report P49
  • £150,000 Allowance for planning conditions Report P52
  • £402,000 Updated stamp duty land tax and agents fees Report P53
  • £15,889,055 Updated total capital outlay projection Report P54
  • circa £7.5m Price submitted by the only compliant design and build bidder Report P30
  • circa £3.75m Each council's share of the design and build contract Report P31

Options considered

  • Chosen: Increase capital budget envelope by £2.3m to £15.9m. Needed to cover higher design and build bid, DNO network upgrade, BNG, and other additional costs Report P6, P28, P43, P56
  • Chosen: Award the JCT Design and Build contract to the preferred bidder. Only compliant bidder of five, with strong quality, social value, and carbon scores Report P7, P28, P31, P70
  • Chosen: Delegate direct award of electricity upgrade contract to the DNO. Provides flexibility to engage the DNO directly if that proves the better route Report P8, P32, P72
  • Chosen: Secure a temporary contingency depot site. To protect continued waste collection if the new depot is not ready on time Report P9, P42

Implications

  • Financial: Total capital budget across both councils rises from £13.7m to up to £15.9m, with Vale's share up by about £1.15m, and some of the increase may be part funded from each council's existing contingency budget. Report P43, P56
  • Legal: Approval supports the council's statutory duty as a waste collection authority, with a draft JCT Design and Build contract already prepared. Report P58, P59
  • Legal: Planning conditions, Section 106 and Section 278 agreements will need to be completed before any decision notice is issued. Report P27
  • Equalities: An Equality Impact Screening found no implications linked to the recommendations. Report P64
  • Climate: A Climate Impact Assessment was completed in November 2024 and the preferred bidder scored full marks on carbon reduction and energy experience. Report P60, P63
  • Risk: The project is one of the most significant items on the council's corporate risk register, with planning delay and failure to deliver the depot on time the main risks. Report P66, P67
  • Other: The new depot supports the Future Waste Services programme and strategic priorities on financial stability, climate and nature, and homes and infrastructure. Report P17, P18, P19, P20

Who and where

  • Vale of White Horse and South Oxfordshire residents receiving waste collection Report P22, P23
  • Joint waste service operation, currently run from the Culham Number One site leased from Biffa Report P22
  • Haseley Trading Estate site and the surrounding community engaged through parish council meetings Report P24, P68
  • The preferred design and build bidder and the District Network Operator Report P28, P32

Timeline

  • November 2024: Cabinet briefed on depot project Report P21
  • December 2024: Council approved Haseley as preferred location and allocated capital budget Report P21
  • 9 June 2025: Planning application P25/S1653/FUL registered Report P25
  • 8 October 2025: South Planning Committee expected to determine the application Report P26, P36
  • 10 October 2025: Cabinet considered and recommended budget increase Report P3
  • 22 October 2025: Council approved the budget increase Report P3
  • early November 2025: Completion of contractor procurement targeted Report P38
  • November 2025: Enabling and asbestos works to be completed Report P39
  • 1 December 2025 to 24 July 2026: Construction period planned Report P40
  • 13 July 2026 to 24 July 2026: Handover period planned Report P41

Plain English for the jargon

  • JCT Design and Build: A standard UK construction contract where one contractor designs and builds the project.
  • DNO: District Network Operator, the company that owns and runs the local electricity distribution network.
  • BNG: Biodiversity Net Gain, a policy requiring developments to leave biodiversity in a better state than before.
  • RIBA Plan of Work Stage 4: The Royal Institute of British Architects stage covering technical design before construction.
  • Section 106 / 278 Agreements: Legal agreements under planning law: Section 106 covers developer contributions, Section 278 covers works to the public highway.
  • SDLT: Stamp Duty Land Tax, the tax paid on property purchases.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item133

Resolved

RESOLVED : to proceed with increasing the capital budget envelope by £2.3m to provide a total budget of £15.9m, with 50 per cent of this total budget being the council’s share of the costs associated with delivering the waste vehicle depot and making it operational within the required timeframes.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Council

Cabinet Report

Report of Head of Development and Corporate Landlord Report Lead: Andrew Busby Report Author: Aileen Sparling, Place and Strategic Asset Management Team Leader E-mail: [email protected] Wards affected: All

Cabinet member responsible: Cllr Andy Crawford (Cabinet member for property and housing) E-mail: [email protected] To: CABINET Dates: 10 October 2025 To: COUNCIL Dates: 22 October 2025

Haseley Trading Estate

Recommendation(s) That Cabinet:

(a) recommends to Council to proceed with increasing the capital budget envelope by £2.3m to provide a total budget of £15.9m, with 50 per cent of this total budget being the council’s share of the costs associated with delivering the waste vehicle depot and making it operational within the required timeframes

(b) subject to Council approval of the increased budget envelope, award the JCT Design and Build contract to the preferred bidder to deliver the vehicle depot on the Haseley Trading Estate

(c) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, to approve terms and conditions to directly award a contract to the District Network Operator (DNO) for an upgraded electricity connection

(d) delegates to the Head of Development and Corporate Landlord, in consultation with the Head of Finance and Head of Legal, authority to secure a temporary vehicle depot site, as a contingency plan, and enter into the necessary leases and any ancillary agreements which will bind the council (jointly with Vale) for an agreed period, to be funded from contingency if required.

1 Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Yes Yes Yes

Signing off Anna Winship Nick Bennett Heather Lorne Grove officer Saunders

Purpose of report 1. This report updates Cabinet on the latest position with respect to the delivery of a waste vehicle depot at the Haseley Trading Estate site, and seeks approval by the relevant bodies to:

• increase the budget envelope based on the latest assessment of costs

• award the JCT Design and Build contract

• delegate the approval of terms and conditions to enter into a direct contract with the DNO, and

• to secure a contingency plan, in the event that the new depot is not ready for occupation at contract start date to ensure continued provision of the statutory waste service.

Strategic priorities 2. The provision of a new waste vehicle depot will assist in the delivery of the Future Waste Services programme, meeting the following strategic priorities:

• Financial stability and innovative transformation

• Action on climate change and nature recovery, and

• Providing the homes and infrastructure people need.

Background 3. Members were most recently briefed on work to deliver a new waste vehicle depot at Cabinet in November 2024 and Council in December 2024, where they approved the Haseley Trading Estate as the preferred location for the waste vehicle depot. At the same time, members also approved the allocation of a capital budget envelope for site purchase costs, and the transfer of additional funds from the provisional to approved capital programme to continue delivery of the project.

4. Delivery of the depot at the Haseley Trading Estate is required to meet the council’s statutory responsibilities in respect of waste collection. At present, South Oxfordshire and Vale of White Horse District Councils do not own or operate a waste vehicle depot in either district, with the current depot at the Culham Number One site being leased and operated by Biffa. The Culham Number One site is due for redevelopment as an allocated strategic site in the South Oxfordshire Local Plan

2 2035, and as such, there is a continued and urgent need to deliver a new vehicle depot to meet the council’s ongoing statutory responsibilities for waste collection.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haseley Trading EstateReport 221 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

31 of 42 attended
PB
Phil BarkerCouncil Staff, expected
BB
Becky BinsteadSecretary, expected
NB
Nick BennettCouncil Staff, expected
KB
Councillor Kiera BentleyCommittee Member, present
RB
Councillor Ron BatstoneCommittee Member, apologies
CB
Councillor Cheryl BriggsCommittee Member, apologies
SC
Councillor Sue CaulCommittee Member, apologies
RC
Councillor Robert CleggCommittee Member, present
MC
Councillor Mark ColemanCommittee Member, present
AC
Councillor Andy CookeCommittee Member, present
JC
Councillor James CoxCommittee Member, present
AC
Councillor Andy CrawfordCommittee Member, present

All 42 on the meeting page

More from Vale of White Horse Council

All decisions
MeetingDecisionOutcome
17 Jun 2026 South and Vale Local Development Schemea) To approve the revised Local Development Scheme, June 2026. b) To delegate the making of minor updates to the Join... Approved Open
17 Jun 2026 South and Vale Joint Local Plan 2045 (JLP2)to a) Agree, subject to the agreement of South Oxfordshire District Council, preparation of the next Joint Local Plan... Agreed Open
17 Jun 2026 Independent Persons - Proposed Extension to Term of OfficeTo appoint Mike Boon, Julie Byron, George Green, Andrew Mills-Hick, Chris Smith and Martin Wright as Independent Pers... Decided Open
17 Jun 2026 Appointments to committees, panels and joint committees for 2026/27that for the 2026/27 municipal year to: 1. Appoint the following committees and panels for the 2026/27 municipal year... Decided Open
17 Jun 2026 Councillors' allowances schemethat Council: 1. Accepts the recommendation of the Joint Independent Remuneration Panel; 2. Authorises the director o... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies