Warwickshire County Council
Cabinet, Thursday 15 October 2026

Update on the Children's Homes Strategy and Homes for children sufficiency

Decided Executive 1 paper

AI summaryWarwickshire Cabinet backs four new council-run children's homes between 2026 and 2030, with a detailed business case to follow. The council will also write to the Minister on Ofsted registration delays and excessive profiteering in the residential care market.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCouncil-run homes to be developed 2026 to 2030
Money£7.551m residential care overspendPart of £9.052m Children and Families forecast overspend
What happens nextDetailed business case from October 2026First two new homes operational by end 2028
Who it affectsLooked after children in WarwickshireEspecially those with complex emotional needs

What was decided

Cabinet supported a new phase of four council-run children's homes between 2026 and 2030, with separate investment decisions still to come. Report P3, 1.6, 4.7

The Executive Director for Children and Young People was authorised to progress a detailed business case with Warwickshire Property and Development Group and the wider developer market. Report P4, 2.3

The Executive Director, working with the Portfolio Holder for Children, Families, Education and SEND, was authorised to write to the Minister for Children and Families about Ofsted registration and profiteering in the residential care market. Report P5

Why

The Council has a duty under Section 22G of the Children Act 1989 to secure sufficient accommodation for looked after children, and demand for specialist provision continues to exceed supply. Report 1.1, 1.4, 4.6

Residential care costs are a major pressure, with an average weekly placement cost of £7,486 per child, and a forecast £7.551m of residential care overspend within a £9.052m Children and Families overspend. Report 1.5, 2.1

Existing provision does not fully meet the needs of children with emotional distress, exploitation risks, missing episodes and Deprivation of Liberty requirements, and the private market has grown without meeting local sufficiency needs. Report 4.6, 4.8

What happens next

From October 2026: develop a detailed business case to bring back to Cabinet for approval, alongside a Capital Investment Bid once due diligence is complete. Report 2.3, P33

January and February 2027: progress design, planning and partnership discussions with Warwickshire Property and Development Group and development partners. Report P33

By December 2028: deliver and operationalise the first two new council-run homes, with the remaining two homes completed by March 2030, and write to the Minister on Ofsted processes and profiteering. Report P5, P28, P33

The money

  • £7.551m Children and Families residential care forecast overspend Report 1.5, 2.1
  • £9.052m Total Children and Families forecast overspend at Quarter 1 Report 1.5, 2.1
  • £7,486 Average weekly cost of a residential placement per child Report 1.5, 2.1
  • £61,800 Current weekly cost of running the Council's children's homes Report 2.1
  • £77,000 Average external weekly cost for comparison Report 2.1

Options considered

  • Chosen: Develop four additional council-run children's homes between 2026 and 2030. To meet rising demand for specialist provision, improve value for money and reduce reliance on out-of-county placements. Report 1.6, 2.4, 4.7
  • Rejected: Continue relying on external and spot-purchased placements. Insufficient local provision continues to drive high-cost spot-purchased placements and budget pressure. Report 2.4

Implications

  • Financial: Expansion is expected to reduce reliance on external placements, support the Medium-Term Financial Strategy, and create savings against current average external costs of £77,000 per week. Report 2.1, 2.4, 2.5
  • Legal: Cabinet is asked to write to the Minister about Ofsted registration administration and excessive profiteering in the residential care market; Ofsted identifies Warwickshire as having sufficiency needs, which may support priority registration. Report P5, 4.5
  • Staffing: Workforce stability, recruitment and retention, and managing sickness absence are flagged as ongoing concerns across the service. Report 4.3
  • Climate: New homes will be designed with energy-efficient and sustainable principles, and will be more resilient to climate change impacts than adapted older housing stock. Report 3.2, 3.3
  • Risk: The Council needs sustained 75-80% occupancy across its homes to break even financially, and planning permission delays have affected progress. Report 4.1, 4.3
  • Other: More children will be able to live closer to family, schools and communities, reducing travel for children, families and the workforce. Report 3.1, 4.4

Who and where

  • Looked after children in Warwickshire, particularly those with complex emotional health needs, exploitation risks and Deprivation of Liberty requirements Report 1.1, 1.4, 4.6
  • Foster carers and the Council's fostering service, which is being expanded to support at least 18 children to transition from residential care by November 2027 Report 1.7
  • Children's Services workforce, including staff in the five existing council-run homes and the planned Willow Tree stabilisation home Report 4.3
  • Private residential providers in Warwickshire, which have grown from 12 homes in 2020 to at least 30 by 2026 Report 4.8

Timeline

  • Since 2020: Council's blended sufficiency approach in place, with progress on local residential, fostering and supported accommodation Report 1.2
  • 2025: The Council's five children's homes became fully operational and all achieved Ofsted 'Good' judgements Report 4.3
  • 29 September 2026: Update considered by the Children and Young People Overview and Scrutiny Committee Report 4.1
  • October 2026 onwards: Development of a detailed business case to return to Cabinet for approval Report P33
  • January/February 2027: Design, planning and partnership discussions with WPDG and development partners Report P33
  • March 2027: Willow Tree short-term stabilisation and transition home expected to become operational Report 4.3
  • November 2027: Target for at least 18 children to transition from residential care into family-based living Report 1.7
  • By December 2028: First two new council-run children's homes expected to be delivered and operational Report 1.6, P28, P33
  • March 2030: Remaining two homes within the programme to be completed Report P33

Plain English for the jargon

  • Sufficiency duty: Section 22G of the Children Act 1989 duty on councils to secure enough accommodation for looked after children in their area.
  • Deprivation of Liberty: Legal authorisation needed when a child's freedom of movement and daily activities must be significantly restricted to keep them safe or protect others.
  • WPDG: Warwickshire Property and Development Group Limited, the council's property development partner.
  • Ofsted Priority Application Route: Faster Ofsted registration route available where there is extremely high demand and insufficient placement options in an area.
  • Sufficiency Board: Multi-agency board that oversees delivery of the Homes for Children Sufficiency Strategy and monitors performance.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Resolved That Cabinet 1) Considers and comments on the progress made in delivering Warwickshire County Council's Homes for Children Sufficiency Strategy and the improvements achieved in local residential, fostering and supported accommodation provision; 2) Supports a new phase of Warwickshire County Council-run children's homes through the development of four additional homes between 2026 and 2030, noting that separate investment decisions will be required. 3) Authorises the Executive Director for Children & Young People to progress a detailed business case and development opportunities in partnership with Warwickshire Property and Development Group Limited (WPDG) and the wider developer market to support delivery of the proposed homes programme; and 4) Authorises the Executive Director for Children & Young People, in consultation with the Portfolio Holder for Children, Families, Education & SEND to write to the Minister for Children and Families seeking improvements to the administration of Ofsted registration processes and greater national action to address excessive profiteering within the children's residential care market.
Word for word from the decision Warwickshire published for this meeting. Source: democracy.warwickshire.gov.uk

Follow this further

Built from Warwickshire's papers

What the report saysPro

Report to Cabinet, 6 pages

Recommendations

That Cabinet:

1) Considers and comments on the progress made in delivering Warwickshire County Council's Homes for Children Sufficiency Strategy and the improvements achieved in local residential, fostering and supported accommodation provision;

2) Supports a new phase of Warwickshire County Council-run children's homes through the development of four additional homes between 2026 and 2030, noting that separate investment decisions will be required.

3) Authorises the Executive Director for Children & Young People to progress a detailed business case and development opportunities in partnership with Warwickshire Property and Development Group Limited (WPDG) and the wider developer market to support delivery of the proposed homes programme; and

4) Authorises the Executive Director for Children & Young People, in consultation with the Portfolio Holder for Children, Families, Education & SEND to write to the Minister for Children and Families seeking improvements to the administration of Ofsted registration processes and greater national action to address excessive profiteering within the children's residential care market.

Executive summary

1.1The County Council has a general duty under Section 22G of the Children Act 1989 to secure sufficient accommodation in its area for looked after children.

1.2Warwickshire County Council delivers its sufficiency duty for children in care through a blended approach of Council-run children's homes, a Council-run foster care service, local and regional contractual arrangements across fostering, residential and supported accommodation where internal provision cannot meet need. Since 2020, this approach has strengthened the availability of local homes and reduced reliance on expensive out-of-county provision. 1.3 The Council's five operational children's homes are all rated "Good" by Ofsted and currently provide accommodation for up to 15 children. Occupancy has increased steadily from 34% in 2023/24 to 78% during 2026/27 to date. However, more recently, internal homes have been used to provide stability for children awaiting foster care placements.

1.4Despite local market growth, the Council continues to experience significant sufficiency challenges, particularly for children with complex emotional health needs, exploitation risks and Deprivation of Liberty requirements. Deprivation of Liberty requirements relate to children whose care arrangements require legal authorisation because their freedom of movement and daily activities must be significantly restricted to keep them safe or to protect others. These children often require highly specialised and intensive placements, which are in very short supply both locally and nationally. Demand for specialist provision continues to exceed supply locally.

1.5Residential care costs continue to place significant pressure on the Council's budget, with £7.551m of the current £9.052m Children and Families’ forecast overspend attributable to residential care expenditure. The average weekly cost of a residential placement is now £7,486 per child.

1.6To address these challenges, Cabinet is being asked to approve the development of further Council-run children's homes between 2026 and 2030, including specialist provision for children experiencing significant emotional distress, exploitation risks and social, emotional and mental health needs. The first two homes are expected to be operational by the end of 2028.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on the Children's Homes Strategy and Homes for children sufficiencyReport 6 pages DownloadRead as text

More from Warwickshire Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Code of Corporate Governance (Update)Resolved That Cabinet 1) Approves the revised Code of Corporate Governance attached at Appendix 1 to the report; and ... Approved Open
15 Oct 2026 Warwickshire County Council - Assurance review of policies and processes in libraries and other public spacesResolved That Cabinet 1) Notes the findings of the Assurance Review of libraries and other public spaces and authoris... Decided Open
15 Oct 2026 Great Alne - proposals for siteResolved That Cabinet approves the use of the Great Alne Primary School site at School Road, Great Alne, Warwickshire... Approved Open
15 Oct 2026 Approval to proceed with Procurement - Renewal of Microsoft 365 LicencesResolved That Cabinet 1) Approves the commencement of a procurement exercise for Microsoft 365 licences to replace th... Approved Open
15 Oct 2026 Reports Containing Exempt or Confidential InformationResolved : That members of the public be excluded from the meeting for the items mentioned below on the grounds that ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies