AI summaryWarwickshire Cabinet approves converting the former Great Alne Primary School site into 40 specialist SEND places, with capital funding of £1.363m to be decided in December 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSite approved for specialist education provision
Money£1.363m capital, £1.322m annual revenueCapital from High Needs Capital Allocation
What happens nextDecember 2026Capital funding request to Cabinet
Who it affectsSEND primary children in Stratford district40 places for Autism, SLCN and SEMH needs
What was decided
Cabinet approved the use of the former Great Alne Primary School site at School Road, Great Alne, B49 6HQ for specialist education provision. Report P1
Cabinet noted that the capital funding allocation request will be brought to Cabinet for decision in December 2026 as part of the Education Capital Programme Report. Report P1, 2.1
Why
The site has been vacant since Great Alne Primary School closed in July 2026 due to declining pupil numbers, and Cabinet previously expressed a wish to retain it for educational use. Report 1.1, 4.1
The SEND Reform Plan identified a need for 170 additional specialist places in the county, and the Stratford district has a forecast shortfall in primary-phase specialist provision. Report 1.3, 5.5
A 40-place provision could avoid up to £1.701m of annual expenditure compared with independent specialist placements, with an indicative payback of around 1.5 years. Report 2.3, 2.4
What happens next
Officers will discuss the most appropriate delivery model with the Department for Education, including whether the site operates as a satellite of an existing special school or as a new stand-alone school. Report 1.4, 6.1
A public consultation will be required, led by the Trust if a satellite model is chosen, or by the Council if a stand-alone school is established. Report 1.7, 6.1
The capital funding request will go to Cabinet in December 2026, and any significant front-of-site engineering works are likely to need a Regulation 3 planning application determined by the Council's Regulatory Committee. Report 2.1, 6.2, 6.3
The money
£1.363m Estimated capital cost to re-purpose the site and buildings to BB104 standards, from the High Needs Capital Allocation Report 2.1
£1.322 million Estimated annual revenue cost of a fully occupied 40-place provision, met through the High Needs Block Report 2.2
£1.701 million Potential annual cost avoidance versus equivalent independent specialist placements at full occupancy Report 2.3
£42.5k Current estimated annual cost avoidance for each specialist place filled Report 2.4
£0.684m Indicative cost avoidance in Year 1 (16 places) Report 2.4
£1.361m Indicative cost avoidance in Year 2 (32 places) Report 2.4
Options considered
Under consideration: Use the site as a satellite of an existing special school, with the Trust leading consultation. Being explored with the Department for Education as a possible delivery route Report 1.4, 1.7, 6.1
Under consideration: Establish a new stand-alone special school on the site, with the Council leading consultation. Alternative route requiring DfE approval, being discussed Report 1.4, 1.7, 6.1
Implications
Financial: Cumulative cost avoidance is expected to exceed the £1.363m capital investment during Year 2, giving an indicative simple payback of around 1.5 years. Report 2.4
Financial: Demand for special school places is forecast to rise from 2,494 in 2026 to 2,989 in 2029, so cost avoidance rather than cash savings is expected. Report 2.4
Equalities: The provision is aimed at primary-aged children with Autism, Speech, Language and Communication Needs and/or Social, Emotional and Mental Health needs, addressing an identified gap in Stratford district. Report 1.2, 5.5
Climate: Refurbishment and any new-build elements will be designed to current building regulations, with opportunities to improve energy efficiency and reduce carbon emissions considered during design. Report 3.2
Legal: Public consultation and statutory processes are required before final establishment, and any significant front-of-site engineering works are likely to need a Regulation 3 planning application. Report 1.5, 1.7, 6.3
Risk: Drop-off and pick-up arrangements need resolving given the current site layout and adjacent land ownerships. Report 6.3
Who and where
Primary-aged children in Stratford district with Autism, SLCN and/or SEMH needs Report 1.2, 5.1
Families of children with Education Health and Care plans in Stratford district (1,175 children of statutory school age) Report 5.1
The Great Alne local community, as a former educational asset is retained for educational use Report 1.1, 4.3
Timeline
December 2025: SEND Sufficiency Analysis identified a gap in primary-phase specialist provision in Stratford district Report 5.5
Year 1 of operation: Aim to provide 16 specialist places Report 2.4
Year 2 of operation: Aim to provide 32 specialist places Report 2.4
Year 3 of operation: Aim to reach full 40 specialist places Report 2.4
July 2026: Great Alne Primary School closed following a Cabinet decision Report 4.1
December 2026: Capital funding allocation request to be brought to Cabinet as part of the Education Capital Programme Report Report P1, 2.1, 6.2
Plain English for the jargon
SEND: Special Educational Needs and Disabilities
SLCN: Speech, Language and Communication Needs
SEMH: Social, Emotional and Mental Health needs
EHC plan: Education Health and Care plan, a statutory plan for children and young people with SEND
BB104: Building Bulletin 104, the government standard for school design areas
High Needs Block: The part of the schools funding formula that supports pupils with SEND
Regulation 3 application: A planning application made by a local authority for its own development, determined by its own Regulatory Committee
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
Resolved That Cabinet approves the use of the Great Alne Primary School site at School Road, Great Alne, Warwickshire, B49 6HQ for specialist education provision and notes that the capital funding allocation request will be brought to Cabinet for decision in December 2026 as part of the Education Capital Programme Report.
Word for word from the decision Warwickshire published for this meeting.Source: democracy.warwickshire.gov.uk
That Cabinet approves the use of the Great Alne Primary School site at School Road, Great Alne, Warwickshire, B49 6HQ for specialist education provision and notes that the capital funding allocation request will be brought to Cabinet for decision in December 2026 as part of the Education Capital Programme Report.
Executive summary
1.1The former Great Alne Primary School site presents an opportunity to retain educational use within the community whilst also addressing a significant strategic need within Warwickshire's Special Educational Needs and Disability (SEND) system. The school closed due to declining pupil numbers and was no longer viable as a mainstream primary school. During consideration of the closure, Cabinet expressed a desire, where possible, to retain the site for educational purposes.
1.2The proposal would create 40 specialist places for primary-aged children with Autism, Speech, Language and Communication Needs (SLCN) and/or Social, Emotional and Mental Health (SEMH) needs. The proposal would therefore achieve two important objectives: preserving the site's educational function for the benefit of the local community and contributing towards addressing increasing demand for specialist placements for children with SEND.
1.3Warwickshire's SEND Reform Plan identified the need to increase specialist provision by 170 in the county and improve local sufficiency. This proposal contributes 40 places towards that ambition whilst ensuring that a valued community asset continues to serve children and families through an educational purpose.
1.4Discussions are taking place with the Department for Education (DfE) regarding the most appropriate delivery route and commissioning options, including whether the provision should operate as a satellite of an existing special school or through an alternative route requiring DfE approval.
1.5Subject to approval of final funding through the Education Capital Programme and completion of the necessary statutory, feasibility and consultation processes, the intention is to open the provision at the earliest practicable opportunity.
1.6Officers consider that continued educational use represents the most appropriate use of the site. The proposal responds directly to an identified gap in specialist provision within Stratford district, supports delivery of the Local SEND Reform Plan and aligns with the commitment made during the closure process to explore opportunities to retain the site for educational purposes wherever feasible.
1.7A public consultation will be required prior to any final decision to establish specialist education provision on the site. Depending on advice from the DfE this may be led either by a Trust or by the Council. If the site is used as a satellite site of an existing school, then the Trust will lead this process. If the site is used for a new stand-alone special school, then the Council will lead this process. The Council is in discussion with the Department for Education regarding the most sustainable solution. In association with local members, other engagement activities would also be undertaken.
Financial implications
2.1Capital funding will be required to adapt the former Great Alne Primary School site to meet the requirements of specialist provision, including compliance with BB104 standards. The project would be funded from the County Council's High Needs Capital Allocation. The survey and feasibility work has estimated a capital requirement of £1.363m to re-purpose the current site and buildings for specialist education. The capital request will be included in the Education Capital Programme Report to be brought to Cabinet for decision in December 2026.
2.2Revenue funding would be met through the High Needs Block using the existing Warwickshire special school funding methodology. Based on current funding arrangements, the estimated annual revenue cost of a 40-place provision would be £1.322 million.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Code of Corporate Governance (Update)Resolved That Cabinet 1) Approves the revised Code of Corporate Governance attached at Appendix 1 to the report; and ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.