The Executive agreed to 1. the short-term management plan for the site; and 2. a Special Interest Group (SIG) being established to assist the Portfolio Holder in reviewing the options and exploring alternative uses for the site in the longer term. [This item has already been considered by the Corporate ...
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
Item Abnormal development requirements Preliminary Budget Abnormal Costs Comments
(1) Assuming approximately 36000m3 of engineering clay imported; (2) Includes for mobilisation, supervision, welfare, site £2,400,000 - £2,600,000 maintenance and security, lanscaping works after placement of cap (3) Maximum cost includes for off site disposal of excavated material 1 Clay cap
(1) For Construction Quality Assurance, (2) Assumes 16 week programme; 2 visits per week during a 10 week period; £19,000 chemical testing and geotechnical testing
Land drainage (if final use is informal / formal public (1) Drain pipes with allowance for bends, junctions, saddles, tapers; and excavating trenches by machine (2) Surplus spoil 2 180,000 - £190,000 open space) removed off site to nearest tip
1 Storey: £6,600 - £8,400 (1) Assumed an area of 600m2 (2) Based on unit rates provided in Spon's Civil Engineering and Highway Works Price Book 20102 (3) Based on the difference between standard shallow strip foundations and raft foudations 2 Storeys: £30,000 - £33,600 Extra Storey: £42,000 - £66,000 3 Pavilion Foundations 1 Storey: £88,400 - £115,400 (1) Assumed an area of 600m2 (2) Based on unit rates provided in Spon's Civil Engineering and Highway Works Price Book 2012 (3) Based on the difference between standard shallow strip foundations and pile foundation foudations (4) 2 Storeys: £83,600 - £95,000 Includes for provision of a foundation risk assessment for submission to the Environment Agency (5) Excludes for disposal of excess arisings
(1) Assumes a floor slab area of 600m2 (2) Lower range assumes Monarperm 500 membrane, upper range assumes a 2000 gas membrane (3) Based on unit rates provided by Visqueen, Monarperm and in Spon's Civil Engineering and Highway 4 Gas / Damp Proof Membrane £1,000 - £2,000 Works Price Book 2012 (4) Excludes ancillary items such as jointing tape. (5) Choice between gas and damp proof membranes depend on the foundation and floor slab solutions (6) excludes installation, inspection and integrety testing.
5 Sub-floor ventilation £10,000 - £11,000 Based on cost estimate obtained from Cordek for 200mm thick void former, including air bricks and periscopic vents.
(1) Assumes an area of 8000m2 (2) Based on cost provided by Kestrel; a mix of Ketrel Options 2 and 3 to provide likely Grass Pitch: £210,000 - £240,000 preferred option (i.e. compacted granular subbase with a geotextile and geogrid layer beneath (3) Includes vegetation 6 Pitch construction clearance, drainage and 12 months maintenace (4) Upper range includes the provisional items recommended by Kestrel
(1) Assumes an area of 9000m2 (2) Based on cost provided by Kestrel (3) Includes vegetation clearance and drainage (4) 3G Artificial Pitch: £390,000 - £410,000 Upper range includes the provisional items recommended by Kestrel 7 Underground services Unable to provide a cost at this stage as layout and length of services not determined 8 Assessment of settlement of raft foundation £2,000 - £3,000 Final cost will depend on the results of the supplemenary site investigation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.