Waverley Borough Council
Executive, Tuesday 1 September 2026 at 7.00pm

Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027

Approved Executive 3 papers

AI summaryWaverley Executive approves start of procurement for over-£200k contracts in its 2026-27 pipeline and delegates award decisions to the Joint Strategic Director for Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement to begin for pipeline projects
MoneyOver £200kThreshold for items in the pipeline report
What happens nextProceed to marketProcurement team and service areas to tender
Who it affectsSuppliers and biddersFor projects listed in Appendix 1

What was decided

The Executive approved the start of procurement for the projects listed in Appendix 1 of the report. Report 2.1

Delegated authority was given to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance, to award those contracts once a successful contractor is selected, subject to any needed consent from the Shadow West Surrey Council. Report 2.1, 1.3

Why

The Council's Contract Procedure Rules require Executive permission before starting any procurement that could lead to a Key Decision, where the value is over £200k or it affects two or more wards. Report 1.1, 6.2

Planning procurements in advance is considered good governance, supports ethical and compliant buying, and avoids the need for multiple separate approval papers. Report P6, P7, P8, P9, P10, P11, P12

What happens next

The procurement team and the relevant service areas will go to market for the projects in Appendix 1, then move to the award stage and obtain the required approvals. Report 4.1

Each procurement will be checked against the Section 24 Direction, and any required consent from the Shadow West Surrey Council will be sought before a contract is awarded or entered into. Report 8.6, P41

The money

  • over £200k Threshold above which Executive approval is needed to start procurement Report 1.1
  • greater than £100m (inc VAT) Third-party spend level that triggers publication of pipeline notices under the Procurement Act 2023
  • over £2m (inc VAT) Value above which individual pipeline notices must be published
  • above £100,000 Property transactions needing Shadow West Surrey Council consent Report P27
  • over £1,000,000 Capital contracts needing Shadow West Surrey Council consent Report P28
  • above £100,000 Non-capital contracts of certain lengths needing Shadow West Surrey Council consent Report P29

Options considered

  • Chosen: Bring a consolidated procurement pipeline to the Executive at intervals. Saves officer and Executive time, reduces procurement time, supports a more strategic approach Report 11.1, P37
  • Rejected: Bring each individual procurement to the Executive. Incurs more time and cost writing separate reports Report 11.1, P37

Implications

  • Legal: The Section 24 Direction made under the Local Government and Public Involvement in Health Act 2007 is being considered; consent from the Shadow West Surrey Council is required for certain property, capital and non-capital contracts before they are entered into. Report P26, 8.6, P41
  • Risk: The new Contract Procedure Rules may need more resource from the procurement team and from service areas acting as subject experts. Report 10.1
  • Risk: Without planned pipelines, there is a higher risk of non-compliant spend if contracts expire before re-procurement, and reduced ability to engage the market early. Report 10.2
  • Other: Procurement design will consider access for small and medium enterprises and the voluntary, community and social enterprise sector, and opportunities to collaborate with Waverley Borough Council and others. Report 7.2, 8.1, P24

Who and where

  • Suppliers and potential bidders for contracts over £200k listed in Appendix 1 Report 1.1, 2.1
  • Waverley Borough Council service areas that will run the procurements Report 4.1, 6.3
  • Shadow West Surrey Council, which must give consent for certain contracts Report P27, P28, P29
  • Small and medium enterprises and the voluntary, community and social enterprise sector, to be considered in procurement design Report 7.2

Timeline

  • 10 March 2026: Surrey (Structural Changes) Order 2026 came into effect
  • 2 June 2026: Previous procurement pipeline report presented to the Executive Report 1.2
  • expected by 30 June 2026: Section 24 Direction to be issued
  • 1 April 2027: Vesting Day for West Surrey Council

Plain English for the jargon

  • Contract Procedure Rules (CPRs): The Council's internal rules governing how contracts are procured and awarded
  • Key Decision: A decision with significant financial or cross-ward impact, requiring Executive approval
  • Section 24 Direction: A direction under the Local Government and Public Involvement in Health Act 2007 requiring Shadow West Surrey Council consent for certain contracts during reorganisation
  • Shadow West Surrey Council: The shadow authority preparing to take on Waverley's functions from Vesting Day
  • Vesting Day: The date, 1 April 2027, when West Surrey Council takes on the Council's functions
  • VCSE: Voluntary, community and social enterprise sector
  • SME: Small and medium-sized enterprise
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 48/26

Resolved

that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contract break clause at the end of year 4 as set out in section 11.1 be approved. 2) The procure of a new fleet of vehicles to deliver the contract ... EXE 48/26
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Recommendations

That., the Executive resolves

(i) To agree an 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contract break clause at the end of year 4 as set out in section 11.1

(ii) To procure a new fleet of vehicles to deliver the contract for a maximum sum of £9.0M.

(iii) To Authorise the Joint Strategic Director – Housing & Communities (in consultation with the Executive Portfolio Holder Environment & Sustainability) to agree a revised street cleansing specification within the terms of the contract. 2 (iv) To agree that the decisions at (i), (ii) and (iii) shall not be implemented unless and until the Council has approved the addition of £9.0M to the capital programme for the procurement of the vehicle fleet, and West Surrey Council has given its consent under (vi) below

The Executive recommends to Council:-

(v) That £9.0M be added to the capital programme for the procurement of a vehicle fleet as set out in Section 5

The Executive recommends to West Surrey Council:-

(vi) That they give consent under the s24 Direction to enter into a contract for the provision of a vehicle fleet as set out in Section 5.

2.0Reason(s) for recommendation:

2.1The Council has a statutory duty as a Waste Collection Authority and its other general requirements to provide the services within this proposed permissible contract extension.

2.2The current contract provides for a permissible extension period of 8 years, and there are no alternative options to an extension which are deliverable or affordable within the required timescales. The council does have the ability to procure a new contract from November 2027 however there is only a small market. Additionally, the Council would need to procure a new contract for seven or eight years in length. The current contractor is willing to enter a contract extension of 8 years with a new option of a 4-year break clause.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Addendum 48/26Addendum 422 KB Download
PDF
Comparison of purchase of fleet vs fleet owned by contractor and savings 48/26Appendix 1 88 KB Download
PDF
Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027Report 783 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, apologies
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027This decision
  2. Procurement approach for provision of Waste, Recycling, Street Cleaning and Grounds Maintenance Services - Report of the Member Task & Finish GroupDecided
  3. NI 191 - Residual household waste per household (kg) NI 192 - Percentage of household waste sent for reuse, recycling and compostingAgreed

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Procurement Pipeline Report – over £200k (2026-27)that 1) Commencement of the procurement process for the projects listed in Appendix 1 to this report be approved. 2) ... Approved Open