The Executive has agreed to RECOMMEND to the COUNCIL that approval be given to a virement of £227,000 from the general buy-back budget within the New Affordable Homes Capital Programme, to pay for the additional costs associated with the Station Road development, as set out in the report. [This item ...
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
[Portfolio Holder: Cllr Stewart Stennett] [Ward Affected: Godalming Central and Ockford]
Summary and purpose:
The purpose of this report is to seek budget approval for abnormal costs at Station Road, Godalming.
How this report relates to the Council’s Corporate Priorities:
This report relates to the Council’s Corporate Priority of providing more affordable housing in the Borough for local people in housing need. Financial Implications: The Council has earmarked reserves for the provision of new affordable homes and associated costs. This report requests a further budget allocation to meet the costs of delays to the scheme due to additional archaeology works required.
Legal Implications: There are no direct legal implications associated with this report.
Background 1. In March 2014, the Ministry of Justice issued a licence to allow the excavation of the bones from the former burial ground at Station Road on the part of the site that will be occupied by residential buildings and the immediate surrounding area. The Executive approved an additional budget to enable Surrey County Archaeological Unit (SCAU) to be commissioned to carry out the excavation of this area. They excavated 85 skeletons, which exceeded their 50-60 estimate.
2. Prior to applying for the licence, Surrey County Archaeological Unit (SCAU) as the contractor has the general preference to remove all the bones within the identified former burial ground, whatever the cost or delay.
3. The options available were considered and it was decided to proceed on a pragmatic staged approach to avoid incurring unnecessary costs and time delays, in consultation with our Employers Agent, and started with the area of the site where all bones were required to be removed because its new use would be for housing. 4. At that stage, it was accepted that less archaeological works would be required in the adjoining area, which is to be used for gardens and car parking. The excavation that followed revealed that the bones were located closer to the surface in places, due to the sloping ground. As a result the Council has been informed that more extensive excavation is required in other parts of the former burial ground site to enable the construction vehicles and machinery to move around the site and materials to be stored as part of the development process.
5. In January 2015, Waverley received agreement from the Ministry of Justice to an extension of the current licence to enable the excavation of additional areas of the site and agreed for some of the archaeological remains in the car parking areas, below an approved level, to be left in situ and protected to enable construction. To ensure that things progress as quickly as possible, the Council has instructed W Stirland to appoint Surrey County Archaeological Unit (SCAU) to carry out the next phase of the archaeological excavation works.
6. Construction vehicles and materials could harm the archaeology so the Council has been required to put the main construction work on hold while this further stage of archaeological works is carried out. Work will re-commence as soon as possible once excavation in the key access areas has been completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.