The Executive has approved the submission of a planning application for the development of the land at Site A, Ockford Ridge, Godalming, to provide up to 40 new homes, to support the redevelopment and refurbishment programme on the estate. [CORPORATE OVERVIEW AND SCRUTINY COMMITTEE]
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
This report is to seek approval to submit a planning application for up to 40 units on site A compared to 34 units proposed originally. The cost of submitting a planning application comprises the planning fee of £15,400 and the cost of the consultant to prepare the submission which will be in the region of £64,000 for up to 40 units. This cost is provided for in the scheme budget in 2016/17. The additional build costs of 6 units will be detailed as the project progresses along with the increased revenue stream from the extra units.
Legal implications
The planning application would require consent under the Town and Country Planning Act 1990. Authority to approve the submission of a planning application on behalf of the Council lies with the Executive, while authority to consider and determine planning applications lies with the Council’s Area and Joint Planning Committees.
Background 1. In June 2013, the Council embarked on an ambitious investment programme to redevelop and refurbish homes at Ockford Ridge to enhance the estate for the benefit of current and future generations. 2. In August 2014, a (Hybrid) planning permission was granted for the redevelopment areas at Ockford Ridge, which included detailed consent for the development of 16 new social homes in Site D and outline consent for 83 additional social homes in Sites A, B and C. In addition, planning permission for two show homes (as part of Site C) was granted by the Local Planning Authority on 11 March 2015 and these are scheduled for completion and handover in August 2016.
3. Consultation continues with local residents with monthly newsletters and regular meetings with the Community Consultative Group.
4. As a result of new Government legislation, the Council reviewed its funding commitment to the Ockford Ridge enhancement and scaled back the scope of the investment, limiting the initial phase to Sites D and A with the two later phases (Sites B and C) being subject to detailed approval as and when sites D and A were completed. This revision was due to a combination of an increase in forecast, pre-tender costs and the impacts of the Government’s Housing and Planning Act 2016.
5. Revisions included the re-tendering of sites D and A separately from all four sites and the consideration of increasing the density of development on Site A in order to secure better value for money and enable the Council to accommodate more of its tenants on this site.
6. In addition to the strategic argument for increasing the number of units on Site A, seeking a detailed planning consent for Site A would also increase (once granted) the banding of tenants on that site, thereby increasing their likelihood of success in bidding to move off the estate: Detailed consent triggers a re-banding for those tenants on the Housing List on this site. Securing vacant possession more quickly would thus be encouraged.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.