The Executive has approved the appointment of the preferred Contractor 3, following the successful completion of the second stage of the tender process in accordance with the Council’s Contract Procedure Rules, subject to the final contract sum being within the approved budget and in consultation with the Director of Resources ...
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1. In April 2015, planning permission was granted for the redevelopment of the garage site at Nursery Hill, Shamley Green to provide five affordable homes for affordable rent and 15 parking spaces to meet local housing need. The approved layouts of the site and elevation drawings are shown in Annexe 1. 2. Pre-development services have been provided by Nye Saunders Architects and several other consultancies that have undertaken surveys and delivered reports to support the planning application.
3. Pulse Associates have been appointed to undertake the role of Employers Agent (EA) on the project and have worked on build contractor tender documents preparation and assessment.
4. Significant pre-development preparation works have been undertaken ahead of a build contractor’s appointment, including site clearance, asbestos removal, security and ground investigation.
5. Progress to appoint a build contractor has been slower than anticipated because the first request for expressions of interest in January 2016 resulted in no returns. As a result, the approach was reviewed and on the advice from Pulse Associates it was decided to use a two-stage tendering process. 6. The first stage tender pack was issued in April 2016 through the Council’s procurement system and five returns have been received. All five tenders have been analysed and evaluated against the criteria defined in the tender documents.
7. Pulse Associates issued a tender report recommending that the three contractors: Contractor 1, Contractor 2 and Contractor 3 were interviewed. Interviews were held on 6 June 2016 with a view to selecting one build contractor to work with, to produce full cost calculations and full design preparation for the project.
8. Following the interview and after completion of the assessment process Pulse Associates have recommended Contractor 3 as a preferred build contractor for the project. Budget
9. Pulse Associates have produced preliminary budget cost estimates for the scheme, including indicative build costs, utility connection costs and contingency, which are set out in (Exempt Annexe 2). The anticipated build programme is 10 months, split over the next two financial years.
Timetable
10. The indicative timetable for the development is shown in the table below:
Key activities Indicative Date First Stage Tenders received May 2016 Interviews following first stage submissions June 2016 Second Stage Tendering process October- December 2016 Build contractor’s appointment December 2016 Start on site January 2016 Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.