Resolved
RESOLVED that the scope of Local Plan Part 2, as set out in Annexe 1 to the agenda report, be approved. [Reason: to agree the scope of Part 2 of the Local Plan]
Executive approved this item on Tuesday 29 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the scope of Local Plan Part 2, as set out in Annexe 1 to the agenda report, be approved. [Reason: to agree the scope of Part 2 of the Local Plan]
The Council has agreed a supplementary estimate of £200,000 to fund the additional resources necessary to support the acceleration of the production of Local Plan Part 2.
There are no legal implications arising specifically from this report.
Introduction
1. The review of the 2002 Waverley Borough Local Plan is taking place in two parts:- Local Plan Part 1: Strategic Policies and Sites; and Local Plan Part 2: Non-strategic Policies and Sites
2. The Council has recently published Local Plan Part 1 for public consultation. Once the comments have been considered as a result of this consultation, the Council will submit Local Plan Part 1 to the Secretary of State for its formal examination.
3. In July 2016 the Council agreed the new Local Development Scheme (LDS). This sets out the timetable for the completion of Local Plan Part 1 and the provisional timetable for the preparation of Local Plan Part 2. In particular, the key milestones for the preparation of Local Plan Part 2, as set out in the LDS are: Aug – Sept 2017: Consultation on preferred options and draft policies (Regulation 18) April 2018: Publication and Regulation 19 consultation July 2018: Submission for examination March 2019: Adoption
4. Officers have already commenced work on the preparation of Local Plan Part 2, particularly in relation to the scope of the document. The intention is to progress the production of Local Plan Part 2 as quickly as reasonably possible. In particular, much of the work to prepare the draft of Local Plan Part 2 will be taking place alongside the examination of Local Plan Part 1. Given that some of the policies and site allocations contained within Local Plan Part 2 are directly linked to the strategy set out in Local Plan Part 1, progress with the work on Local Plan Part 2 will clearly be dependent on the progress of Local Plan Part 1 through examination.
5. A further consideration that will affect the scope and potentially the timetable for Local Plan Part 2 will be progress with the various neighbourhood plans that are being prepared for a number of the towns and parishes in Waverley. The neighbourhood plans in preparation are at various stages. These include the Farnham Neighbourhood Plan, which has already reached the examination stage. The intention is that Local Plan Part 1 will set out the overall strategy and in some cases the specific housing allocation to inform the development of neighbourhood plans and the potential allocation of sites to deliver the development needs of the town/parish. In such cases, there may not be the need for allocations and some development management policies in Local Plan Part 2, if the related neighbourhood plan is dealing with these matters.
The Scope of Local Plan Part 2
6. Attached as Annexe 1 to this report is a table setting out the key matters that Local Plan Part 2 is likely to cover. This is not an exhaustive list and there may be the need to address other matters as a result of any changes to national policy/guidance.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Report on scope of LP Part 2: Annexe 1Appendix | 70 KB | Download |
PDF |
THE SCOPE OF LOCAL PLAN PART 2: NON-STRATEGIC SITES AND POLICIESReport | 62 KB | DownloadRead as text |
Follow Executive at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... | Agreed | Open |
| 1 Sep 2026 | New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... | Decided | Open |
| 1 Sep 2026 | Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... | Agreed | Open |
| 1 Sep 2026 | Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... | Approved | Open |
| 1 Sep 2026 | Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.