RESOLVED that 1. the latest position against the budget in 2017/18 be noted; 2. delegated authority be given to the Chief Finance Officer in consultation with the Leader and the Portfolio Holder for Finance to agree the Government’s required Memorandum of Understanding in order for the business rate pilot to ... view the full minutes text for item 98.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
There are no direct legal implications relating to this report.
Introduction
1. Throughout 2017/18, performance against budget is monitored on a monthly basis.
2. Financial position reporting will also focus on performance against financial targets such as income, establishment and savings targets. Financial risk is always inherent in service delivery and service managers will be assisted in the identification, evaluation and mitigation of significant risks and these will be reported throughout budget management as necessary.
3. Explanations for variations have been provided in the previous budget management reports. Where a new significant variation has appeared, an explanation is provided in this report. General Fund
4. The General Fund has a net budget of £13.4m in 2017/18 and the latest forecast does not identify any material deviations from budget however there are some areas to note, as detailed below.
5. The significant variations arising since the previous report to note and monitor are given below:
Finance
6. The interest on investments has continued to be positive to date. It is expected that the income budget will be exceeded by a further £20,000 in the year. This is partially due to the increase in base rate but also careful investment by officers through the year.
7. External audit costs are due to underspend by £20,000 against budget. Waverley have benefitted from a credit of £8,000 from the audit commission due to any surplus being returned to local authorities following the closure of the service. Additionally, the external audit budget was set prudently to cover estimated costs, however costs have come in lower due to the Public Sector Audit Appointments (PSAA) capping the fees payable.
Elections
8. A risk of an unavoidable additional cost on updating the register of electors may be incurred this financial year. Waverley has experienced reduced funding from central government to deliver this statutory service, increases in postage costs, an increase in electorate and a large increase in registrations due to the June 2017 general election. Officers have submitted a justification led bid for additional funding from the Cabinet Office, however the outcome of this is not yet known and is unlikely to cover the full additional cost incurred due to restrictions on funding use.
Planning
9. Within the Building Control service income levels to date have been lower than budgeted. The business plan has now been implemented by officers and income performance has started to improve, however it is expected that budget will not be achieved this financial year. Current estimates suggest income will be down on budget by £40,000.
10. Development Management income continued to be lower than expected this year and the current projected forecast is for an additional £20,000 underachievement of income. Therefore the total underachievement of income for the year is forecast to be £70,000. The 2018/19 Budget has been adjusted to reflect the lower expectation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.