WAVERLEY BOROUGH COUNCIL
HOUSING OVERVIEW & SCRUTINY COMMITTEE
27 NOVEMBER 2018
Title:
OCKFORD RIDGE UPDATE
[Portfolio Holder: Cllr Carole King] [Wards Affected: Godalming Central and Ockford]
Project overview
102 new homes – demolition of 64 homes – net gain of 38
Site A: 37 new homes
Site B: 17 new homes
Site C: 30 new homes
Site D: 16 new homes
Show homes: 2 new homes
New build: £15,688,357
Refurbishment: £7,011,704
Existing risks are managed in accordance with the defined risk mitigation (action) plan that forms part of the Risk Register.
Site A
The site is cleared and hoarded awaiting redevelopment.
The new roads have been officially named as ‘Whitebeam Way’ and a numbering system has now been agreed and confirmed with the relevant authorities.
The council remains on programme to commence construction works in spring next year. As part of the tender process potential contractors were asked to prepare a phase delivery programme which would enable early handover of some new homes. This would facilitate bringing forward other sites on the estate. Procurement
The tender period has ended and returns assessed. A preferred contractor has been identified and the council is in a 30 day standstill period, after which the council will be in a position, assuming no formal challenges, to make an appointment. Contract Award is planned for November and a start on site in March 2019.
Site B
Decanting strategy is being reviewed in light of a phase handover proposed by the preferred contractor for site A. This should allow tenants to be moved to new homes earlier, and enable start on site before planning permission lapses in November 2020.
The next phase of project planning will be the procurement of service disconnection and diversion works. Both these activities will take place during the early part of 2019 so that the site can be brought forward for demolition and redevelopment in 2020.
Work will continue in the background to complete the financial appraisal, obtain budget approval and Stopping Up Order in preparation for action. Decanting strategy continues to be worked on by the Tenant Liaison Officer.
The Pre development budget 18/19 will cover interim costs until full budget approval is obtained from a future meeting of the Executive.
Site C
An application for outline consent was submitted on 12 October. Validation is expected to be completed by Planning Services by Friday 26 October, after which formal public consultation will commence.
Three of the existing void properties on this site are to be leased to Ethical Lettings prior to redevelopment of the site.
The next phase of project planning will be the procurement of service disconnection and diversion works which will take place during the early part of 2019 so that following discharge of reserve matters the site can be brought forward for demolition and redevelopment in 2020.
Site D
W Stirland handed over the new homes on the 31 July 2018. A Formal opening ceremony was held on the 20 September 2018 and attended by the Mayor, other Ward Councillors, local residents, W Stirland (contractor) and Waverley staff. The 12 month defect period will end 31 July 2019.
Refurbishment
Phase 1
Waverley Officers and our appointed Contract Administrator continue to monitor the completion of the final snagging works at one property. The final account will be agreed with a retention held for a further twelve months.
Phase 2 & 3 Properties have been identified and survey works completed to inform the next two phases of refurbishment. Phase 2 is an externals only phase of refurbishment. Phase 3 is a full refurbishment phase with only one tenant decanted from their home to facilitate refurbishment. The remaining properties have become void following former tenants move to new build homes on Site D. One property will provide adapted ground floor accommodation for an existing tenant at Ockford Ridge with a long term health condition.
Community consultation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 6: Housing OS Ockford Ridge Programme: Annexe 2Appendix | 67 KB | Download |
PDF |
Item 6: Ockford Ridge October 18: Annexe 1(updated)Appendix | 58 KB | Download |
PDF |
OCKFORD RIDGE UPDATEReport | 74 KB | DownloadRead as text |
Follow Overview & Scrutiny Committee - Housing at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2021 | Scrutiny reportRESOLVED That the Committee endorsed the Biennial Scrutiny Report. | Decided | Open |
| 8 Jun 2021 | Annual kpi reviewRESOLVED That: Housing Delivery and Communities (Housing Delivery only) – The Committee agreed to no changes to indic... | Agreed | Open |
| 8 Jun 2021 | Report from the housing design standards task and finish groupRESOLVED That the Committee were happy for the report to go forward to the Executive. | Decided | Open |
| 9 Mar 2021 | Tenants panel updateRESOLVED To highlight the committee’s concerns regarding the isolation of elderly people to the Community and Wellbei... | Decided | Open |
| 26 Jan 2021 | Asset management strategy 2021/22RESOLVED That a verbal update on the Asset Management Strategy would be a standing item on subsequent Housing Overvie... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.