Resolved
Decision RESOLVED that the application be DEFERRED to enable the applicant to provide more information.
Area Planning Committee (Eastern) deferred this item on Wednesday 10 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision RESOLVED that the application be DEFERRED to enable the applicant to provide more information.
B1 WA/2019/0677 Application under Section 73A to Vary Condition Waverley Borough Council 5 of WA/2018/1555 regarding the provision of 2 12/04/2019 electric vehicle charging points. at Land At Queensway, Cranleigh
Committee: Eastern Area Meeting Date: 12/07/2019
Public Notice: Was Public Notice required and posted: N/A Grid Reference: E: 506707 N: 138843
Parish/Town: Cranleigh Ward: Cranleigh East Case Officer: Jessica Robinson Expiry Date: 06/06/2019 Time Extended Date: 14/07/2019 Neighbour Notification Expiry Date: 11/06/2019
RECOMMENDATION That, subject to conditions, permission be GRANTED.
Introduction
The application has been brought before the Area Committee because the application is made by Waverley Borough Council, as landowner.
Location Plan Approved Plan (WA/2018/1555)
Site Description
The application site comprises two grassed areas adjacent to either side of the existing highway, Queensway.
Proposal
This application seeks to vary Condition 5 of WA/2018/1555 which states:
Condition The development hereby approved shall not be occupied unless and until at least 2 of the available parking spaces are provided with a fast charge socket (current minimum requirement: 7kw Mode 3 with Type 2 connector - 230 v AC 32 amp single phase dedicated supply) in accordance with a scheme to be submitted to and approved in writing by the Local Planning Authority.
The varied condition would read: Condition The development hereby approved shall not be first used unless and until at least 2 of the available parking spaces are provided with underground cabling and associated infrastructure below ground to ensure that a fast charge socket (current minimum requirement: 7kw Mode 3 with Type 2 connector - 230 v AC 32 amp single phase dedicated supply) can be installed within 1 year of this decision notice in accordance with a scheme to be submitted to and approved in writing by the Local Planning Authority.
The variation of the condition is to allow the Council’s Housing Operations Team to develop a strategy for a Borough wide Electric Vehicle Charging scheme.
Relevant Planning History
WA/2018/1555 Application under Regulation 3 of the Approved Town and Country Planning General 18/01/2019 Regulations 1992 for construction of new parking areas and access path WA/2018/0701 Application under Regulation 3 of the Withdrawn Town and Country Planning General 06/06/2018 Regulations 1992 for construction of a dropped kerb and hardstanding to provide 12 parking spaces. HM/R11766 Land at rear of Kings Road and New Park Approved Road Cranleigh 09/06/1961 Housing estate
Planning Policy Constraints
Developed area of Cranleigh Environment Agency - Risk from Surface Flooding (high, Medium & Low) Cranleigh Design Statement (2008) Low Pressure Pipeline (GPL)
Development Plan Policies and Proposals
The Development Plan comprises:
Waverley Borough Local Plan, Part 1: Strategic Policies and Sites (adopted February 2018) Waverley Borough Local Plan 2002 (retained policies February 2018) In accordance with paragraph of the National Planning Policy Framework (NPPF) due weight has been given to relevant retained policies in the Waverley Borough Local Plan 2002
Other guidance:
National Planning Policy Framework (2019) National Planning Practice Guidance (2014) Statement of Community Involvement (2014 Revision) Cycling Plan SPD (April 2005) Council’s Parking Guidelines (2013) Vehicular and Cycle Parking Guidance (Surrey County Council 2012) Waverley Local Plan Strategic Highway Assessment (Surrey County Council, 2016) Surrey Design Guide (2002) Cranleigh Design Statement (2008)
The relevant policies to this application are:
Local Plan, Part 1: Strategic Policies and Sites (adopted February 2018): TD1: Townscape and Design SP1: Presumption in favour of Sustainable Development ST1: Sustainable Transport
Local Plan 2002 (retained policies February 2018): D1: Environmental Implications of Development D4: Design and Layout D7: Trees, Hedgerows and Development
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item B1, WA/2019/0677: Land at Queensway, CranleighReport | 465 KB | DownloadRead as text |
Follow Area Planning Committee (Eastern) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jan 2020 | Applications for Planning PermissionRESOLVED that the applications for planning permission be determined as set out below. | Decided | Open |
| 22 Jan 2020 | Item A1, WA/2019/1410 - Dibdene, The Green, Shamley GreenProposal A replacement dwelling within the Rural Settlement of Shamley Green is proposed. Whilst of an acceptable des... | Refused | Open |
| 16 Oct 2019 | Applications for Planning PermissionRESOLVED that the applications for planning permission be determined as set out below. | Decided | Open |
| 16 Oct 2019 | Item B1, WA/2019/0790 - Darien, Links Road, Bramley, GU5 0ALDecision RESOLVED that permission be REFUSED for the following reasons: 1. Reason The proposal, by reason of the size... | Refused | Open |
| 11 Sep 2019 | Applications for Planning PermissionRESOLVED that the applications for planning permission be determined as set out below. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.