Resolved
Decision RESOLVED that permission be GRANTED, subject to conditions 1 – 4 and amended condition 5 set out in the update sheet, as well as informative 1.
Area Planning Committee (Eastern) decided this item on Wednesday 11 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision RESOLVED that permission be GRANTED, subject to conditions 1 – 4 and amended condition 5 set out in the update sheet, as well as informative 1.
The application has been brought before the Area Committee because the application is made by Waverley Borough Council, as landowner.
This application was DEFERRED from the meeting held on the 12th July 2019 as there was insufficient information to determine the application at that time. Specifically further information was deemed necessary in relation to the following points:
The extent of infrastructure/cabling already implemented; The capability of providing further Electric Vehicle Charging Points (EVCP) in the future; and Restriction of parking bays for the public or tenants.
Officers have been in discussions with the applicant to provide the requested information.
It is to be noted that this is an application under Section 73A which relates to development which has already been implemented. Officers confirm that the proposed development has been implemented. However, the proposed cabling for the EVCPs has not yet been installed. Officer understand that this is a relatively straight forward task that would involve digging a shallow trench from the existing power line shown in blue/pink (figure 1 below) to the two end spaces to the west of the bay spaces. This application seeks to secure the underground cables which would be installed and capped at ground level as shown in picture A. No above ground unit would be implemented at this stage.
(fig 1)
(picture A)
The bays would remain unrestricted until such a time that the EVCP is installed, at which point they would become exclusively for the use of tenants. All other bays would remain unrestricted. There is potential for further bays to be fitted with EVCPs in the future if such a need was to arise. It is also noted that the most easterly bay to the south of Queensway is adjacent to a lamp post and could, in the future, form part of a wider County level strategic strategy to provide on street EVCPs.
Officers consider that the additional information required has now been received and there is now sufficient information to allow members to resolve a decision on this application.
2. Location Plan Approved Plan (WA/2018/1555)
3. Site Description
The application site comprises two grassed areas adjacent to either side of the existing highway, Queensway.
4. Proposal
This application seeks to vary Condition 5 of WA/2018/1555 which states:
Condition The development hereby approved shall not be occupied unless and until at least 2 of the available parking spaces are provided with a fast charge socket (current minimum requirement: 7kw Mode 3 with Type 2 connector - 230 v AC 32 amp single phase dedicated supply) in accordance with a scheme to be submitted to and approved in writing by the Local Planning Authority.
The varied condition would read: Condition The development hereby approved shall not be first used unless and until at least 2 of the available parking spaces are provided with underground cabling and associated infrastructure below ground to ensure that a fast charge socket can be installed (current minimum requirement: 7kw Mode 3 with Type 2 connector - 230 v AC 32 amp single phase dedicated supply), which shall thereafter be installed and become operational within 1 year of this decision notice in accordance with a scheme to be submitted to and approved in writing by the Local Planning Authority.
The variation of the condition is to allow the Council’s Housing Operations Team to develop a strategy for a Borough-wide Electric Vehicle Charging scheme.
5. Relevant Planning History
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item B1, WA/2019/0677: Land At Queensway, CranleighReport | 664 KB | DownloadRead as text |
Follow Area Planning Committee (Eastern) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jan 2020 | Applications for Planning PermissionRESOLVED that the applications for planning permission be determined as set out below. | Decided | Open |
| 22 Jan 2020 | Item A1, WA/2019/1410 - Dibdene, The Green, Shamley GreenProposal A replacement dwelling within the Rural Settlement of Shamley Green is proposed. Whilst of an acceptable des... | Refused | Open |
| 16 Oct 2019 | Applications for Planning PermissionRESOLVED that the applications for planning permission be determined as set out below. | Decided | Open |
| 16 Oct 2019 | Item B1, WA/2019/0790 - Darien, Links Road, Bramley, GU5 0ALDecision RESOLVED that permission be REFUSED for the following reasons: 1. Reason The proposal, by reason of the size... | Refused | Open |
| 11 Sep 2019 | Applications for Planning PermissionRESOLVED that the applications for planning permission be determined as set out below. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.