Waverley Borough Council
Executive, Tuesday 5 October 2021 at 6.00pm

The Burys Development Options Appraisal Stage 1

Noted Executive 2 papers

Executive noted this item on Tuesday 5 October 2021. Below is the council's own wording, with the papers it was decided on.

ItemEXE 37/21

Resolved

RESOLVED 1. That the progress made on the Burys Development Project to date, as detailed in Annexe 1, be noted; and 2. That a further budget of £15,000 to progress to Stage 2 be approved, to be met from the balance on the original approval and the Property Investment Reserve. ... EXE 37/21
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Recommendation

It is recommended that the Executive

 Note the progress made on the Burys Development Project to date, as detailed in Annexe 1.

 Approve a further budget of £15,000 to progress to Stage 2, to be met from the balance on the original approval and the Property Investment Reserve.

Reason for the recommendation

To comply with approval and governance arrangements as defined within the PID.

Background

A project for the Burys site was first considered in 2018 when external agents were commissioned to undertake a Strategy and Options Evaluation of office accommodation for the Council. The report concluded that a development on the site was financially viable and a significant return could be generated as well as making major improvements to the customer experience. The Burys site is a Council owned asset and, as such, the development of the site has been put under the remit of the Property Investment Advisory Board to ensure best use of Council assets.

On the 7 January 2020, at Executive, approval was granted to fund £40,000 from the Property Investment Reserve for the completion of an options appraisal to assess the investment opportunities of the Waverley owned key sites in Godalming.

The Project Board appointed HLM Architects to complete the options appraisal following a lengthy and full tender process. Since their appointment, the Project Board has met with HLM Architects three times, once before they started work on the project, once in week 5 of the project to discuss the first stage of options, and once at week 8, to listen to HLM present the final Options Appraisal (stage 1). Officers have also met HLM on site to discuss and walk the three agreed sites for inclusion in the appraisal.

5. Relationship to the Corporate Strategy and Service Plan

5.1This project supports many of the Council’s aspirations contained within the Corporate Strategy 2020-25. The project promotes a financially sound Waverley, with infrastructure and services fit for the future. A development scheme supports the Medium- Term Financial Plan through efficiency savings and income generation.

5.2The project also aims to deliver a positive contribution to Godalming by enhancing the key sites as a place for work, leisure and to live; being sympathetic to the surrounding area, the conservation area and nearby listed buildings supporting the surrounding environment delivering housing including social housing the potential to deliver a mixed development scheme including leisure facilities.

6. Implications of decision

6.1Resource (Finance, procurement, staffing, IT)

Funding for the further options appraisal was agreed by Executive at its meeting on 07 January 2020. Commissioning of this work has been undertaken in accordance with the Council’s Contract Procedure Rules.

The next stage of the project, Stage 2, will cost £15,000. This can be met from a balance on the original approval, and the Property Investment Reserve. Project Management staff are in place to complete the project.

Risk management

Risk will be assessed in line with the Council’s Risk Management Framework and Risk Appetite Statement and in accordance with the Property Investment Strategy’s requirements with regard to risk.

This includes ensuring comprehensive due diligence is undertaken in all projects and the use of external agents to give expert and independent opinion. A risk register has been drafted and discussed at Management Board. It will be monitored by the Project Manager and Project Board.

6.3Legal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXEC 05.10.2021: Annexe 1: Stage 1 summary 37/21Appendix 408 KB Download
PDF
The Burys Development Options Appraisal Stage 1Report 145 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
PF
Councillor Paul FollowsChair, present
PC
Councillor Peter ClarkVice Chair, present
AM
Councillor Andy MacLeodCommittee Member, present
PM
Councillor Penny MarriottCommittee Member, apologies
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
NP
Councillor Nick PalmerCommittee Member, apologies
AR
Councillor Anne-Marie RosomanCommittee Member, present
LT
Councillor Liz TownsendCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present
JE
Councillor Jenny ElseGuest, in attendance
JH
Councillor Jerry HymanGuest, in attendance

All 13 on the meeting page

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies