RESOLVED that virements [1] of budgets within the HRA to realign the budget to need as detailed in Annexe 1 to the report be approved. Reason: To update the HRA budgets according to needs and ensure services and works continue to be delivered during 2021/22. The original HRA budget for ... EXE 73/21
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
It is recommended that the Executive approves virements1 of budgets within the HRA to realign the budget to need as detailed in Annexe 1.
Reason for the recommendation
To update the HRA budgets according to needs and ensure services and works continue to be delivered during 2021/22. The original HRA budget for 2021/22 was agreed by Council in February 2021 during the Covid-19 pandemic. In light of the changes in needs from tenants, access to suppliers, contractors etc. this report seeks to provide an update to the landlord services advisory board and realign budgets in line with the current
1 To move funds from one budget to another identified needs.
Background
Performance against Budget – period to end of October 2021
4.1Waverley Borough Council’s HRA has an income budget in 2021/22 of £31,727,000. This is allocated in the budget to four main areas of expenditure:
Revenue expenditure to manage and maintain housing stock - £12.5m Contributions to Core Capital works - £5.8m Contributions to New Build Reserve - £3m Repayment of Debt - £4.9m Interest Payments on Debt - £5.5m
4.2The overall forecast of the position at the financial year-end is an underspend of £22,000. However, within this forecast there are a few significant underspends and overspends. The details of the significant items are listed below.
4.3Revenue overspend:
Area of spend 2021/22 2021/22 actual to Forecast 2021/22 approved budget 31/10/21 overspend Voids works £595,400 £719,900 £692,000 Underachievement (£352,700) (£182,500) £36,300 of rental income from Garages Occupied – £1,489,000 £858,100 £123,000 responsive repairs
Senior Living £140,000 £112,500 £150,000 Accommodation Agency Budget
Voids works –The budget was significantly under-estimated for this year. Delays in capital works due to contractor issues around Brexit and Covid are causing an increase in the need for responsive revenue works.
Rental income from garages is less than anticipated in the budget. The initiative to increase the income from the garages by making them fit for rent and promoting them was impacted by the pandemic and has been put on hold in this financial year due to greater priorities for repairs to homes.
Occupied Responsive Repairs – delays in the planned maintenance capital works due to contractor issues have meant that the requirement to address repairs from the revenue budget has increased in this year
Senior living agency budgets – an increase to costs due to the Fire Risk assessment for a senior living accommodation, which identified a need for fire wardens to be on site to assist residents in the event of a fire, until such time that the works can be done to make the building safe.
4.4Revenue underspend:
Area of spend 2021/22 2021/22 actual to Forecast 2021/22 approved budget 31/10/21 underspend Additional Rental £28,784,000 £16,708,000 £377,300 income Cyclical £1,215,000 £307,200 £175,400 maintenance Reduce HRA £103,520 £900 £102,620 extraordinary cost budget Reduce £5,825,450 £5,478,550 £345,980 contribution to core capital expenditure
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.