Godalming Regeneration Project

Approved Executive 1 paper

Executive approved this item on Tuesday 5 July 2022. Below is the council's own wording, with the papers it was decided on.

ItemEXE 17/22

Resolved

RESOLVED that i. the name of the Burys Development Project be changed to the Central ; ii. Council be recommended to approve a supplementary estimate of £164,000 to progress the project to the next phase (3), including preliminary public engagement, to be funded from the Property Investment reserve; ... EXE 17/22
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Recommendation

It is recommended that the Executive:

i. Agree to change the name of the Burys Development Project to the Central Godalming Regeneration Project

ii. Recommends to Council to approve a supplementary estimate of £164,000 to progress the project to the next phase (3), including preliminary public engagement, to be funded from the Property Investment reserve.

iii Note that phase 3 of the scheme will progress to a formal planning pre-application submission that, subject to the outcome of the engagement process, may include the following elements:

. 1 - A residential scheme and public car parking at Crown Court Car Park to bring much needed housing into the centre of Godalming - A retrofit of The Burys for office working space to reflect new ways of working, and increased car parking provision at The Burys site to allow for loss of car parking at Crown Court Car Park - A residential and/or car parking scheme at the Wharf Car Park on Woolsack Way

Reason for the recommendation

3.1The project offers an opportunity for regeneration of three Council owned sites within the Central Godalming area. The project proposes to bring underutilised elements of the sites forward to generate much needed town centre housing, improve the access of the Council offices at Bridge Street and ensure the office space is utilised to the maximum in a period of hybrid working. These elements will in turn benefit the town centre and bring footfall to local businesses, therefore bringing forward an opportunity for all three sites to be part of a regeneration project and thus the new name for the project.

3.2To respond to the Phase 2 findings that demonstrates that viable schemes are possible on the nominated 3 sites whilst understanding that more detail is required to move them forward.

3.3The Council offices at the Burys in Godalming are unfit for purpose: they have been expensive to heat and maintain, due to the building’s low energy efficiency, for many years and they are excess to the Council’s post-Covid requirements. Absent this project, Waverley will have to spend a significant amount of scarce revenue funding to operate, repair and maintain the current building over the coming years. It is an extremely inefficient building in layout and energy use accounting for 10% of Waverley buildings carbon output, and work is required to rectify this to meet our Climate Emergency objectives. The current layout does not allow for the decreased numbers of staff working in the building due to the implementation of hybrid working and the new Agile Working Policy.

3.4Phase 3 will allow the Council to fully understand the potential for the delivery of much needed housing in Godalming and to engage with the local economy in Godalming.

3.5By completing the pre-application stage, it will give the Council an understanding of whether the project deliverables can be met and to help to understand in detail any future planning risks, whilst bringing forward solutions to mitigate those risks.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Godalming Regeneration ProjectReport 169 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
PC
Councillor Peter ClarkVice Chair, present
AM
Councillor Andy MacLeodCommittee Member, present
PM
Councillor Penny MarriottCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
NP
Councillor Nick PalmerCommittee Member, present
PR
Councillor Paul RiversCommittee Member, apologies
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

On this subject at Waverley

Search all
  1. Godalming Regeneration ProjectThis decision
  2. WA/2026/00460 - Regeneration Area, The Green, Ockford Ridge, GodalmingDecided
  3. Wa/2025/00727 - site f regeneration area, ockford ridge, godalmingRefused
  4. EXE 17/22 Godalming Regeneration ProjectNoted
  5. Godalming Regeneration Project: Update (To Follow)Agreed
  6. Item B1, WA/2018/1853 - Site C, Regeneration Area, Ockford Ridge, GodalmingDecided

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies