Approval to Award Interim Domestic Gas Heating Contract
ApprovedExecutive2 papers
Executive Co-Portfolio Holder for Housing Decisions approved this item on Wednesday 30 November 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1. that the Co-Portfolio Holder for Housing approved that officers proceed to the award of the Domestic Gas Heating, Servicing and Maintenance contract; and 2. that it be noted that the tender evaluation report is attached at Annexe 1 to the report. Reason: On 12 th October 2022 the Council formally issued a letter of termination to Central Heating Services Ltd and its parent company, Greenview Gas, under the “no blame” clause within the TPC contract. The termination gave notice that the contract would formally end on 31 January 2023 - a period just over the contractually required 90 days’ notice. In the intervening period officers have been intensively contract managing the incumbent contractor to ensure that statutory requirements and service to our tenants is not negatively affected. Officers have also engaged in a procurement exercise through a framework organisation to award an interim contract to manage the domestic gas heating, servicing and maintenance works for our tenants. A procurement exercise was conducted and due diligence carried out and an organisation - Smith & Byford – selected as the preferred bidder. To ensure adequate mobilisation and handover time, facilitate TUPE transfer arrangements and enable the contract investment costs to be agreed the incoming contractor required a signed document in order to proceed. To meet the mobilisation and contract ‘go live’ timescales, the contract must be sealed by 30 November 2022. [This decision was taken under the Council’s urgency procedures and therefore not subject to call-in]
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
Report to Executive Co-Portfolio Holder for Housing Decisions
Recommendation
2.1It is recommended that Co-Portfolio Holder for Housing approves that officers can proceed to the award of the Domestic Gas Heating, Servicing and Maintenance contract. 2.2 The tender evaluation report is attached in Annex 1
Background
4.1On 12th October 2022 the Council formally issued a letter of termination to Central Heating Services Ltd and its parent company, Greenview Gas, under the “no blame” clause within the TPC contract. 4.2 The termination gave notice that the contract would formally end on 31 January 2023 - a period just over the contractually required 90 days’ notice.
4.3In the intervening period officers have been intensively contract managing the incumbent contractor to ensure that statutory requirements and service to our tenants is not negatively affected. 4.3 Officers have also engaged in a procurement exercise through a framework organisation to award an interim contract to manage the domestic gas heating, servicing and maintenance works for our tenants.
4.4A procurement exercise was conducted and due diligence carried out and an organisation - Smith & Byford – selected as the preferred bidder.
4.5To ensure adequate mobilisation and handover time, facilitate TUPE transfer arrangements and enable the contract investment costs to be agreed the incoming contractor required a signed document in order to proceed.
4.6To meet the mobilisation and contract ‘go live’ timescales, the contract must be sealed by 30 November 2022.
4.7Following discussing with Legal colleagues and review of the scheme of delegation and Contract Procurement Regulations Co-Portfolio Holder for Housing is being asked to exercise powers delegated under the Constitution to allow for the award of this contract.
5. Relationship to the Corporate Strategy and Service Plan
The report supports the Council’s Corporate commitment to promote “Good quality housing for all income levels and age groups”
6. Implications of decision
6.1Resource (Finance, procurement, staffing, IT)
The budget is available within the Housing Revenue Account (HRA) to cover the additional contract costs in 2022/23. The service has requested growth in the Domestic Gas Heating, Servicing and Maintenance budget for 2023/24 which will cover the cost of this contract. The budget for 2023/24 is due to go to Council in February 2023 for approval.
6.2Risk management Risks for the service are classified as Financial, Legal/Regulatory, Safety, Service Delivery or Reputational. The Corporate Risk Register reports, manages and mitigates risks to the HRA.
6.3Legal
6.3.1 It is understood the procurement process was compliant with relevant legislation and the Council’s contract procedure rules.
6.3.2 The Executive Co-Portfolio Holder for Housing (Operations) has delegated authority to approve all matters falling within the Housing Landlord Service and within the agreed Budget and Policy Framework and has delegated authority to make the decision.
6.4Equality, diversity and inclusion NA 6.5 Climate emergency declaration NA
7. Consultation and engagement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
7Approval to Award Interim Domestic Gas Heating ContractThis decision
Who was there
2 of 5 attended
PR
Councillor Paul RiversCommittee Member, present
R
ReceptionPublic, expected
PF
Councillor Paul FollowsGuest, in attendance
PR
Councillor Penny RiversGuest, in attendance
JH
Councillor Jerry HymanCommittee Member, present, as expected, virtual
Hear about the next one first
Follow Executive Co-Portfolio Holder for Housing Decisions at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.