This application was considered by the Western Planning Committee on 14 th December 2022 and it was resolved to grant the application as below: RECOMMENDATION A That, subject to the applicant entering into appropriate legal agreement within 6 months of the resolution to grant, to secure the implementation and future maintenance of the drainage facilities, and subject to the conditions listed below, permission be GRANTED RECOMMEDATION B That, in the event that a Section 106 Agreement required by Recommendation A is not completed within 6 months of the date of the resolution to grant, permission be REFUSED . The application is being referred back to the Planning Committee as the S106 agreement has not been completed within the 6 months period. The Section 106 has been progressed but a further 3 months is required to conclude the Agreement . REVISED DECISION As a result of the changes outlined, the amended decision is: DECISION A Subject to the applicant entering into appropriate legal agreement by 26/10/2023 (unless an alternative date is subsequently agreed by the Chair and Vice Chair of the Planning Committee), to secure the implementation and future maintenance of the drainage facilities, and subject to conditions 1-27 and informatives 1-8, permission is GRANTED DECISION B In the event that the requirements of Decision A are not met, permission is REFUSED .
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
This application was considered by the Western Planning Committee on 14 th December 2022 and it was resolved to grant the application as below:
RECOMMENDATION A That, subject to the applicant entering into appropriate legal agreement within 6 months of the resolution to grant, to secure the implementation and future maintenance of the drainage facilities, and subject to the conditions listed below, permission be GRANTED RECOMMEDATION B That, in the event that a Section 106 Agreement required by Recommendation A is not completed within 6 months of the date of the resolution to grant, permission be REFUSED.
The application is being referred back to the Planning Committee as the S106 agreement has not been completed within the 6 months period. The Section 106 has been progressed but a further 3 months is required to conclude the Agreement.
2. Post December 2022 Review
Due to the length of time that has elapsed since the December 2022 resolution officers have carried out a review of changes in legislation and policy. Since the resolution to grant permission, the Council has adopted Local Plan (Part 2): Site Allocations and Development Management Policies (adopted March 2023). This report lists the policies that are relevant to this proposal and advises that adoption of these policies will not require any material change to the resolution as there is no conflict with these policies. The Committee is advised in light of the above situation that this is not an opportunity to re-open the debate about the acceptability of the scheme, merely to consider the changes that are set out in detail in the remainder of this report.
3. Compliance with Local Plan (Part 2) 2023
For the purposes of the current application, it is necessary to consider whether the development conflicts with any of these new policies. The relevant policies are as follows:
DM1: Environmental Implications of Development DM2: Energy Efficiency DM4: Quality Places through Design DM5: Safeguarding Amenity DM9: Accessibility and transport DM11: Trees, Woodland, Hedgerows and Landscaping DM14: Extensions, alterations, replacement buildings & limited infilling in the Green Belt DM24: Historic Landscapes and Gardens
With regard to Policy DM1, in light of the assessment set out in the Officer Report (Appendix A), Officers are satisfied that the proposed development would be in accordance with this policy. A number of conditions were recommended which required the submission of a number of landscape and construction environmental management plans. The S106 itself will secure the implementation and future maintenance of the drainage facilities.
Policy DM1 requires that developments: i. avoid negative impacts upon biodiversity deliver the minimum biodiversity net gain of 10% as required by the Environment Act 2021. The biodiversity net gain should be compared to the baseline and calculated using the most up to date national Biodiversity Metric; ii. protect and enhance geological assets.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
WA/2025/00805 - Ruffold Farm CranleighRESOLVED that, delegated authority is granted to the Assistant Director of Planning to GRANT outline planning permiss...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.