Appeals Decisions

Noted Planning 6 papers

AI summaryWaverley Planning Committee noted a Planning Inspector's dismissal of an appeal for a new dwelling in the Green Belt at 2 Sunnyside Cottages, Bramley, because the site is not in a sustainable location and would harm Green Belt openness.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedInspector found inappropriate development in the Green Belt
MoneyNot stated
What happens nextCommittee noted the decisionFor information in determining future applications
Who it affectsGreen Belt planning decisions in WaverleyMaterial consideration for similar applications

What was decided

The committee noted the appeal decision set out in the agenda pack.

The Planning Inspector dismissed the appeal for a new dwelling at 2 Sunnyside Cottages, Rushett Common, Bramley. Report P2, P3

Why

The site fails the paragraph 155 exceptions to inappropriate Green Belt development, primarily because it is not in a sustainable location: bus services are limited, footpaths are poor, and most journeys would be by car. Report P3, P6, P8

The proposed dwelling would reduce both visual and spatial openness of the Green Belt by extending built form into open countryside. Report P10

The benefits of providing one dwelling, modest socio-economic gains, and limited biodiversity improvements do not clearly outweigh the harm to amount to very special circumstances. Report P10, P12

What happens next

The committee noted the appeal decisions, which should be borne in mind when determining future applications in the Borough.

Options considered

  • Rejected: Allow the appeal and grant permission in principle for a dwelling. Site is inappropriate development in the Green Belt, unsustainable location, harm to openness not outweighed by other considerations Report P3, P12

Implications

  • Legal: The appeal decision is a material consideration for future planning applications in the Borough, showing how the Planning Inspectorate applies local and national Green Belt policies. Report P3
  • Other: The Council cannot demonstrate a five-year housing land supply (1.28 years identified in April 2024), yet the tilted balance in paragraph 11d) of the Framework did not apply because Green Belt harm was decisive. Report P10, P12

Who and where

  • The applicant for the dwelling Report P2
  • Future applicants for residential development on previously developed Green Belt land in Waverley Report P3

Timeline

  • April 2024: Council's five-year housing land supply position published, identifying 1.28 years of supply Report P10
  • 11 March 2026: Inspector site visit Report P1
  • 28th May 2026: Inspector decision date, appeal dismissed Report P1, P3
  • 2026-07-08: Planning Committee noted the appeal decision

Plain English for the jargon

  • Permission in principle: An alternative planning consent route for housing-led development with two stages: first stage assesses location, land use and amount; second stage assesses technical details.
  • Grey belt: Previously developed land in the Green Belt that meets criteria in paragraph 155 of the National Planning Policy Framework, where homes may not be inappropriate.
  • Very special circumstances: The test required to justify inappropriate development in the Green Belt, where harm must be clearly outweighed by other considerations.
  • Five-year housing land supply: A council's identified supply of deliverable housing sites over a five-year period; failure to demonstrate this triggers the presumption in favour of sustainable development.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

RESOLVED that the appeals decisions set out in the agenda pack were noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Planning Committee

Appeal Decision Site visit made on 11 March 2026 by Timothy Parton BA(Hons) MPLAN MRTPI an Inspector appointed by the Secretary of State Decision date: 28th May 2026

Appeal Ref: APP/R3650/W/26/3377249 2 Sunnyside Cottages, Rushett Common, Bramley, GUILDFORD GU5 0LG • The appeal is made under section 78 of the Town and Country Planning Act 1990 (as amended) against a refusal to grant permission in principle. • The appeal is made by [name removed] against the decision of Waverley Borough Council. • The application Ref is PIP/2025/01354. • The development proposed is the erection of dwelling.

Decision 1. The appeal is dismissed. Preliminary Matters 2. The proposal is for permission in principle. The Planning Practice Guidance advises that this is an alternative way of obtaining planning permission for housing-led development. The permission in principle consent route has two stages: the first stage (or permission in principle stage) establishes whether a site is suitable in-principle, and the second ‘technical details consent’ stage is when the detailed development proposals are assessed. This appeal relates to the first of these two stages, and so my scope is limited to matters relevant to location, land use, and the amount of development proposed. The appeal proceeds on this basis. 3. A location plan showing the proposed site layout has been submitted. This is treated as illustrative only. 4. The Council’s Decision reason for refusal 2 makes reference to Policy DM4 of the Waverley Borough Local Plan Part 2 (2023) (the Part 2 Plan). This Policy relates to high quality design and is not therefore relevant for this appeal. Main Issue 5. The main issue is whether the site is suitable for residential development, having regard to its location, land use, and the amount of development, with particular regard to: • whether the proposal is grey belt land and whether the proposal would be inappropriate development in the Green Belt having regard to the National Planning Policy Framework and any relevant development plan policies; • the effect on the openness of the Green Belt; • accessibility to services and facilities;

https://www.gov.uk/planning-inspectorate Appeal Decision APP/R3650/W/26/3377249

• access to the site; and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1.Appeal Decision: 3377249Decisions 172 KB DownloadRead as text
PDF
2.Appeal Decision: 6005279Decisions 179 KB Download
PDF
3.Appeal Decision: 6004554Decisions 200 KB Download
PDF
4,Appeal Decision: 6004933Decisions 173 KB Download
PDF
5.Appeal Decision: 6006270Decisions 197 KB Download
PDF
Appeals DecisionsDecisions 229 KB Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
PR
Councillor Penny RiversChair, present
TW
Councillor Terry WeldonVice Chair, present
PC
Councillor Peter ClarkCommittee Member, present
CC
Councillor Carole Cockburn BEMCommittee Member, present
MG
Councillor Maxine GaleCommittee Member, present
DH
Councillor Daniel HusseiniCommittee Member, apologies
JK
Councillor Jacquie KeenCommittee Member, apologies
AL
Councillor Andrew LaughtonCommittee Member, present
AM
Councillor Andy MacLeodCommittee Member, present
DM
Councillor David MunroCommittee Member, apologies
JS
Councillor Julian SpenceCommittee Member, present
RS
Councillor Richard SteijgerCommittee Member, apologies

All 15 on the meeting page

More from Waverley Planning Committee

All decisions
MeetingDecisionOutcome
5 Aug 2026 WA/2026/00844 Chennels Cottage, The Green, DunsfoldRESOLVED that OUTLINE APPROVAL be granted subject to conditions Approved Open
5 Aug 2026 TPO 06-26 Trees on Land at Londene House, Hedgehog Lane, HaslemereRESOLVED that, Tree Preservation Order 06/26 be CONFIRMED without modification. Decided Open
8 Jul 2026 WA/2025/00805 - Ruffold Farm CranleighRESOLVED that, delegated authority is granted to the Assistant Director of Planning to GRANT outline planning permiss... Agreed Open
8 Jul 2026 WA/2026/00450 - Briar Cottage Bowlhead Green Road Brook Godalming GU8 5UWRESOLVED that planning permission be REFUSED for the following reasons: The retention of the ancillary outbuilding du... Refused Open
8 Jul 2026 WA/2026/00451 - Ock Way Godalming (SoS call in)RESOLVED that planning permission be REFUSED for the following reasons: The creation of the proposed access would gen... Refused Open