ItemEXE 86/23

Resolved

I. That the contract in respect of the Council’s Regulatory Services IT Management System be awarded to Idox; II. That the Council’s Contract Procedure Rules in respect of tendering be waived in respect of this procurement; III. That authority to spend the funding allocated to this IT system replacement in ... EXE 86/23
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The existing supplier of the Council’s Regulatory Services IT Management System has formally issued notice withdrawing their support of the current IT system as of 31 March 2024. Corporate Management Board (CMB) has previously approved a capital bid of £50,000 for system replacement, and a project team has been tasked with finding a suitable cost-effective replacement. The project team has undertaken pre-market engagement with suppliers, as well as collaborative consultation with Guildford Borough Council Regulatory Service teams to ascertain the best option for replacement.

1.2This report serves as a progress report regarding the replacement of the Regulatory Services IT Management System. It also seeks approval to waive the tender process and move forward with a service contract with the preferred software replacement provider, and authority to spend the funding allocated in the capital programme.

2.0Recommendation to Executive

That the Executive approves:

2.1That the contract in respect of the Council’s Regulatory Services IT Management System be awarded to the preferred supplier;

2.2That the Council’s Contract Procedure Rules in respect of tendering be waived in respect of this procurement;

2.3That authority to spend the funding allocated to this IT system replacement in the 2023/24 capital programme be granted;

2.4That authority be delegated to the Head of Regulatory Services, in consultation with the Joint Executive Head of Legal and Democratic Services, to complete and execute the necessary contractual documents

3.0Reason(s) for Recommendation:

3.1To take advantage of the offer of significant free support for data migration elements of the implementation of the new system, and align systems with Guildford Borough Council to facilitate future collaboration. 3.2 To enable the procurement of the new system to proceed.

4.0Exemption from publication

4.1The exempt annexe to this report contains financial information.

(a) The content is to be treated as exempt from the Access to Information publication rules because it contains financial information and is therefore exempt by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972.

Purpose of report

5.1To seek authority to waive the tender process in respect of the procurement of the replacement IT management system for Regulatory Services.

5.2To seek authority to spend the funds allocated for the project in the 2023/24 capital programme.

6.0Strategic Priorities

6.1The Council is committed to supporting the health and wellbeing of residents (Corporate Strategy 2020-25). Regulatory Services including the Environmental Health, Environmental Protection, Licencing and the Environmental Enforcement teams provide an effective mechanism to do this. The implementation of the new Regulatory Services IT system will promote efficient management of these work streams.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Software Contract for Regulatory ServicesReport 474 KB DownloadRead as text

At this meeting

Whole meeting
EXE 80/23MinutesOn the agenda
EXE 86/23Software Contract for Regulatory ServicesThis decision
EXE 88/23Supplementary EstimatePrivate

Who was there

8 of 10 attended
PF
Councillor Paul FollowsChair, present
PC
Councillor Peter ClarkVice Chair, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, apologies
KM
Councillor Kika MiryleesCommittee Member, apologies
NP
Councillor Nick PalmerCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies