The Executive RESOLVED to: I. Use the current Latent Defects budget to procure a Contractor to carry out the required remedial works. II. Allocate a £114,225 budget from Latent Defects budget that exists within the Housing Revenue Account Delivery Budget. III. Delegate authority to the Executive Head of Legal and ... EXE 128/23
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1The purpose of this report is to seek Executive approval to formally allocate the current Latent Defects budget to complete the phased remedial works to existing first floor level and associated repairs in three homes at Cedar Close, Farnham. 2. Recommendation to Executive
It is recommended that the Executive approves:
i. Use of the current Latent Defects budget to procure a Contractor to carry out the required remedial works. ii. The allocation of an £114,225 budget from Latent Defects budget that exists within the Housing Revenue Account Delivery Budget. iii. Delegate authority to the Executive Head of Legal and Democratic Services to approve the final form of any legal agreement including JCT Contract. iv. Delegated authority to the Strategic Director (Wellbeing) to enter into any related contract documentation or ancillary agreements required to the remedying of these latent defects.
Reason for recommendations
3.1The defects in these properties are long standing and will only be permanently resolved by the proposed type of intervention.
3.2The Waverley Corporate Strategy 2020-2025 sets out the Vision and Strategic Priorities for the Council. One of the strategic priorities is to ‘provide good quality housing for all income levels.’
4. Exemption from publication
4.1Open Report
Purpose of report
5.1To obtain approval for the Latent Defects budget to be spent on these phased remedial works to existing floor level and associated repairs within the occupied properties of 1,2 and 3 Cedar Close, Farnham. 6. Strategic Priorities
6.1Affordable housing is central to community well-being. It is consistent with the Council’s Corporate Strategy 2020 – 2025, strategic priority to deliver ‘good quality housing for all income levels and age groups’ and ‘effective strategic planning and development management to meet the needs of our communities.’
Background
7.1Properties at 1,2, 3 and 4 Cedar Close were delivered as part of the new build housing delivery programme and completed in 2017. These homes have developed latent building defects which have resulted in noisy floor joists and uneven first floor levels.
7.2The original contractor went into administration after the initial 12- month defect period and officers have pursued the invocation of Local Authority Building Control Warranty (LABC), was refused by LABC.
7.3The defects were present in No 4 Cedar Close but were successfully resolved in July 2019. The remaining three properties were due to be completed earlier but the impact of COVID meant that access became impossible.
7.4Officers have procured and appointed a Contract Administrator and Principal Designer to prepare revised cost estimates and the documentation for tender to procure a contractor to effectively deliver these remedial works over an expected programme of nine- weeks.
7.5The works will include removal and reinstallation of sanitaryware, lifting and relaying floor boarding and installation of noggins to joists and making good.
7.6Officers will continue to work with the Contract Administrator, Principal Designer and Housing Management Team to effectively resolve these latent defects with the minimum disruption/ impact on our residents.
8. Procurement
8.1Subject to the approval of recommendations made at 2 (i-iv) of the report, Officers will procure a Contractor to deliver these remedial works to permanently resolve the defects.
9. Key Risks
9.1Delay in resolving these defects will mean the continued dissatisfaction of residents living in these properties and the potential of future repair costs rising.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.