Farnham Leisure Centre decarbonisation

Approved Executive 1 paper

Executive approved this item on Tuesday 7 May 2024. Below is the council's own wording, with the papers it was decided on.

ItemEXE 173/23

Resolved

The Executive RESOLVED to: I. Approve the use of the £1.545 million grant funding from the Public Sector Decarbonisation Scheme and contribution of £330K from the Empty Homes Grant to install air source heat pumps at Farnham Leisure Centre, and; II. Delegate authority to the Strategic Director - Place to ... EXE 173/23
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

Farnham Leisure Centre is currently heated by end-of-life gas boilers. An Energy Audit was carried out by Everyone Active’s appointed consultants, Leisure Energy. The energy report identified a wide range of energy efficiency improvements including the replacement of the boilers with Air Source Heat Pumps. This proposal would reduce the carbon emissions at the leisure centre by 186.7 tonnes of CO2e a year at a cost of £1,765,000. This project supports Waverley Borough Council's (WBC) and Everyone Active’s ambition to become carbon neutral by 2030. Farnham Leisure Centre accounts for 9% of WBC’s carbon emissions and Farnham Leisure Centres will be one of the identified priority projects in the Carbon Neutrality Action Plan.

A successful bid was made under the Public Sector Decarbonisation Scheme for £1.545 million to fund the air source heat pumps and £330K from the 2023/24 Empty Homes Grant for the required match funding. This would be a two-year project with a completion date of 30th March 2026. This bid was successful, and approval is now being sought to use that grant to deliver the proposed work on Farnham Leisure Centre.

2. Recommendation to Executive

It is recommended that the Executive;

2.1Approves the use of the £1.545 million grant funding from the Public Sector Decarbonisation Scheme and contribution of £330K from the Empty Homes Grant to install air source heat pumps at Farnham Leisure Centre, and;

2.2Delegates authority to the Strategic Director - Place to appoint a contractor and enter into the necessary design and build contractual agreement(s) in accordance with the requirements of the Council’s Contract Procurement Rules.

3. Reason(s) for Recommendation:

3.1The boilers at Farnham Leisure Centre need to be replaced as they are at the end of their life.

3.2WBC has made a successful bid for £1.545 million from the Public Sector Decarbonisation Scheme and secured a £330K contribution from the Empty Homes Grant to fund the replacement of those boilers with air source heat pumps.

4. Exemption from publication

4.1No 5. Purpose of Report

5.1To seek approval to use of the £1,545,000 grant funding secured from the Public Sector Decarbonisation Scheme and £330k contribution from the Empty Homes Grant to deliver the proposed work on Farnham Leisure Centre.

6. Strategic Priorities

6.1This report is directly linked to the delivery of the aims of the Climate Emergency, one of the WBC’s key priorities, which is part of the service delivery plan.

Background

7.1Farnham Leisure Centre is currently heated by end-of-life gas boilers. An Energy Audit was carried out by Everyone Active’s appointed consultants, Leisure Energy. They prepared an energy report identifying a wide range of energy efficiency improvements including improvements to the insulation, AHU and pump, the replacement of the boilers with Air Source Heat Pumps (air to Water) and the installation of Solar PV. These measures would actively support WBC's and Everyone Active’s ambition to become carbon neutral by 2030. Farnham Leisure Centre accounts for 9% of Waverley Borough Council’s carbon emissions and will be one of the identified priority projects in the Carbon Neutrality Action Plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Farnham Leisure Centre decarbonisationReport 480 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, apologies
VK
Councillor Victoria KiehlCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
GM
Councillor George MurrayCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present
MG
Councillor Maxine GaleGuest, present
JS
Councillor Julian SpenceGuest, present

On this subject at Waverley

Search all
  1. Farnham Leisure Centre decarbonisationThis decision
  2. Farnham & Godalming Leisure Centre - Refurbishments and The Edge Leisure Centre - Contract positionAgreed

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies