Quarterly Internal Audit Report - (Q1 and Q2) (Standing Item)

Approved Finance 2 papers

Audit & Risk Committee approved this item on Monday 17 June 2024. Below is the council's own wording, with the papers it was decided on.

ItemAUD 12/24

Resolved

Decision The Audit and Risk Committee APPROVED the new proposal for quarterly reporting.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Audit & Risk Committee

WAVERLEY BOROUGH COUNCIL INTERNAL AUDIT PLAN 2024-25 (Q1 AND Q2)

Prepared by: Neil Pitman, Head of Partnership & Iona Bond, Assistant Head of Partnership May 2024 Internal Audit Plan 2024-25 (Q1 and Q2)

Introduction

The role of internal audit is that of an:

‘Independent, objective assurance and consulting activity designed to add value and improve an organisation’s operations. It helps an organisation accomplish its objectives by bringing a systematic, disciplined approach to evaluate and improve the effectiveness of risk management, control and governance processes’.

The Council is responsible for establishing and maintaining appropriate risk management processes, control systems, accounting records and governance arrangements. Internal audit plays a vital role in advising the Council that these arrangements are in place and operating effectively.

The Council’s response to internal audit activity should lead to the strengthening of the control environment and, therefore, contribute to the achievement of the organisation’s objectives.

The aim of internal audit’s work programme is to provide independent and objective assurance to management, in relation to the business activities; systems or processes under review that: • the framework of internal control, risk management and governance is appropriate and operating effectively; and • risk to the achievement of the Council’s objectives is identified, assessed and managed to a defined acceptable level.

The internal audit plan provides the mechanism through which the Chief Internal Auditor can ensure most appropriate use of Internal Audit resources to provide a clear statement of assurance on risk management, internal control and governance arrangements.

Internal Audit focus should be proportionate and appropriately aligned. The plan will remain fluid and subject to on-going review and amendment, in consultation with the relevant Directors and Audit Sponsors, to ensure it continues to reflect the needs of the Council. Amendments to the plan will be identified through the Southern Internal Audit Partnership’s continued contact and liaison with those responsible for the governance of the Council.

2 Internal Audit Plan 2024-25 (Q1 and Q2)

Your Internal Audit Team

Your internal audit service is provided by the Southern Internal Audit Partnership. The strategic lead will be Iona Bond, Assistant Head of Partnership, supported by Jade Lakeland, Audit Manager.

Conformance with internal auditing standards

The Southern Internal Audit Partnership service is designed to conform to the Public Sector Internal Audit Standards (PSIAS). Under the PSIAS there is a requirement for audit services to have an external quality assessment every five years. In September 2020 the Institute of Internal Auditors were commissioned to complete an external quality assessment of the Southern Internal Audit Partnership against the PSIAS, Local Government Application Note and the International Professional Practices Framework.

In selecting the Institute of Internal Auditors (IIA) a conscious effort was taken to ensure the external assessment was undertaken by the most credible source. As the authors of the Standards and the leading Internal Audit authority nationally and internationally the IIA were excellently positioned to undertake the external assessment.

In considering all sources of evidence the external assessment team concluded:

‘The mandatory elements of the IPPF include the Definition of Internal Auditing, Code of Ethics, Core Principles and International Standards. There are 64 fundamental principles to achieve with 118 points of recommended practice. We assess against the principles. It is our view that the Southern Internal Audit Partnership conforms to all 64 of these principles.

We have also reviewed SIAP conformance with the Public Sector Internal Audit Standards (PSIAS) and Local Government Application Note (LGAN). We are pleased to report that SIAP conform with all relevant, associated elements.’

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarterly Internal Audit Report: (Q1 and Q2) (Standing Item)Plan 589 KB Download
PDF
WBC Internal Audit Plan 2024-25 (Q1 and Q2) 12/24Report 455 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 7 attended
JS
Councillor Julian SpenceChair, present
MH
Councillor Michael HigginsVice Chair, present
JD
Councillor Jerome DavidsonCommittee Member, present
AE
Councillor Alan EarwakerCommittee Member, present
DB
Councillor David BeamanCommittee Member, present
ZB
Councillor Zoe Barker-LomaxCommittee Member, present
MG
Councillor Maxine GaleCommittee Member, apologies

On this subject at Waverley

Search all
  1. Quarterly Internal Audit Report - (Q1 and Q2) (Standing Item)This decision
  2. Quarterly Internal Audit Progress ReportNoted
  3. Quarterly Internal Audit PlanApproved

More from Waverley Audit & Risk Committee

All decisions
MeetingDecisionOutcome
27 Jul 2026 Management of Asbestos containing Material in Corporate Property and AssetsRESOLVED that the Management of Asbestos containing Material in Corporate Property or Assets be noted. Noted Open
27 Jul 2026 Whistleblowing PolicyRESOLVED that the be adopted. Approved Open
27 Jul 2026 Annual Information Governance and Data Transparency ReportRESOLVED that the Annual Information Governance and Data Transparency report be noted. Noted Open
27 Jul 2026 Local Code of Corporate GovernanceRESOLVED that the Local Code of Corporate Governance be approved and adopted. Approved Open
27 Jul 2026 Data Protection Annual ReportRESOLVED that: · The Data Protection Annual report be noted. · A further report be brought to the final meeting of Wa... Noted Open