Waverley Borough Council
Audit & Risk Committee, Wednesday 28 January 2026 at 7.00pm

Quarterly Internal Audit Progress Report

Noted Finance 2 papers

AI summaryWaverley Audit & Risk Committee noted the December 2025 Internal Audit Progress Report, which lists 16 live reviews, several with overdue actions, and flags a Limited assurance opinion on Water Safety.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action required by committee
MoneyNo sums of money stated in the report
What happens nextContinue tracking overdue actionsMany revised due dates extend into 2026
Who it affectsCouncil services under internal audit reviewIncluding housing, finance, procurement, legal, and waste

What was decided

The committee noted the Internal Audit Progress Report and the outstanding actions raised by Internal Audit across service areas. Report P1

Why

The Chief Internal Auditor is required to provide a written status report under the Global Internal Audit Standards and the Internal Audit Charter, covering progress against the audit plan and any impairments to independence. Report P1, P9, P11

The report enables the committee to consider action on overdue items or those likely to miss their target date.

What happens next

Outstanding high and medium priority management actions will be tracked to revised due dates, several of which run to 31 March 2026. Report P39, P43, P46, P50, P55, P58, P60

Several audits remain in fieldwork or scoping stages, with reviews on Programme and Project Management, Charitable Trusts, Cyber, Tree Management, Anti-Social Behaviour, and Asbestos scheduled for Q4 of the plan year. Report P14

Options considered

  • Chosen: Add a Procurement review to the 2025/26 plan. To realise the Finance Provision review commitment. Report P20
  • Chosen: Withdraw the Organisational Capacity review from the plan. Capacity is needed for Damp and Mould work and Awaab's Law implementation; to be reconsidered in the 2026/27 plan. Report P20

Implications

  • Risk: A Limited assurance opinion on Regulatory Compliance - Water Safety identified 658 overdue remedial actions (53.9%), 219 of them high risk, with 72 outstanding over 12 months. The Legionella Policy and Management Plan are past their review dates. Report P28, P30
  • Risk: An Annual Governance Statement review received a No assurance opinion, with high and medium priority actions still outstanding. Report P34
  • Legal: Information Governance testing found a SAR response exceeding the one calendar month statutory deadline, and the Council has no formal data breach procedure in place, relying on an interim SharePoint link. Report P57, P59
  • Equalities: Water safety documents only partially address the Tenancy and Tenant Involvement and Empowerment Standards, with limited reference to tenant consultation and feedback mechanisms. Report P30
  • Climate: Waste services account for 43% of Council emissions, and net zero targets differ between the Council (2030) and contractor Biffa (2050); 6 of 14 work plan actions lack target dates. Report P48, P49, P50
  • Staffing: Two Property Terrier high priority actions are on hold until permanent legal staff are in place. Report P39, P43

Who and where

  • Waverley Borough Council service areas with live or completed internal audit reviews Report P14, P34
  • Tenants in the 591 directly owned dwellings subject to water safety risk assessments Report P28
  • Council members, for whom mandatory training records are not being kept Report P45, P46
  • Biffa, the waste services contractor Report P48, P49

Timeline

  • March 2025: The 2025/26 internal audit plan was approved by the Audit & Risk Committee. Report P14
  • 06.10.25: Water Safety audit final report issued with Limited assurance. Report P14, P28
  • 17.12.25: Safeguarding final report issued with Reasonable assurance. Report P14
  • 19.12.25: Regulatory Compliance - Electrical Safety final report issued with Reasonable assurance. Report P14
  • 31.03.26: Revised due date for Information Governance, SAR procedure, data breach procedure, and councillor mandatory training actions. Report P55, P58, P60, P46
  • Q4 (plan year): Programme and Project Management, Charitable Trusts, Cyber, Tree Management, Anti-Social Behaviour, and Asbestos reviews due. Report P14

Plain English for the jargon

  • Limited assurance: Significant gaps, weaknesses or non-compliance were identified; improvement is required to the system of governance, risk management and control.
  • No assurance: Immediate action is required to address fundamental gaps, weaknesses or non-compliance; the system of governance, risk management and control is inadequate.
  • SAR: Subject Access Request, a statutory request under UK data protection law requiring a response within one calendar month.
  • SIAP: Southern Internal Audit Partnership, the body that delivers the Council's internal audit function.
  • Awaab's Law: New legislation referenced as the reason for withdrawing the Organisational Capacity review from the 2025/26 plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAUD 48/25

Resolved

RESOLVED that: the report and outstanding actions be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Audit & Risk Committee

Purpose of report

In accordance with proper internal audit practices (Global Internal Audit Standards in the UK Public Sector), and the Internal Audit Charter the Chief Internal Auditor is required to provide a written status report to Senior Management and the Audit & Risk Committee, summarising: o The monitoring of ‘live’ internal audit reports o an update on progress against the annual audit plan and any subsequent revisions o acknowledgement of any actual or perceived impairments to internal audit independence o internal audit performance, planning and resourcing issues o results of audit assignments and insights.

Internal audit reviews culminate in an opinion on the assurance that can be placed on the effectiveness of controls in place focusing on those designed to mitigate risks to the achievement of management objectives of the service area under review. Assurance opinions are categorised as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Progress Report v2- December 2025 48/25Report 558 KB DownloadRead as text
PDF
Quarterly Internal Audit Progress ReportReport 285 KB Download

At this meeting

Whole meeting

Who was there

7 of 7 attended
JS
Councillor Julian SpenceChair, present
MH
Councillor Michael HigginsVice Chair, present
ZB
Councillor Zoe Barker-LomaxCommittee Member, present
DB
Councillor David BeamanCommittee Member, present
JD
Councillor Jerome DavidsonCommittee Member, present
MG
Councillor Maxine GaleCommittee Member, present
GM
Councillor George MurrayCommittee Member, present

On this subject at Waverley

Search all
  1. Quarterly Internal Audit Progress ReportThis decision
  2. Quarterly Internal Audit PlanApproved
  3. Quarterly Internal Audit Report - (Q1 and Q2) (Standing Item)Approved

More from Waverley Audit & Risk Committee

All decisions
MeetingDecisionOutcome
27 Jul 2026 Management of Asbestos containing Material in Corporate Property and AssetsRESOLVED that the Management of Asbestos containing Material in Corporate Property or Assets be noted. Noted Open
27 Jul 2026 Whistleblowing PolicyRESOLVED that the be adopted. Approved Open
27 Jul 2026 Annual Information Governance and Data Transparency ReportRESOLVED that the Annual Information Governance and Data Transparency report be noted. Noted Open
27 Jul 2026 Local Code of Corporate GovernanceRESOLVED that the Local Code of Corporate Governance be approved and adopted. Approved Open
27 Jul 2026 Data Protection Annual ReportRESOLVED that: · The Data Protection Annual report be noted. · A further report be brought to the final meeting of Wa... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies