The Executive RESOLVED to: 1. Delegate authority to the Strategic Director of Housing and Environment for the procurement of a contractor via open tender to construct the western section of the Godalming Greenway Gateway through Phillips Memorial Park.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
5.1To present Executive with the updates on project progress 5.2 To seek approval for delegated authority to project a construction contractor for the Philips Memorial Park section of the Godalming Greenway Gateway.
6. Strategic Priorities
6.1This report is directly linked to the delivery of three key priorities of the Councils corporate strategy: taking action on the Climate Emergency, improving Health and Wellbeing for residents and supporting a stronger, more resilient local economy.
Background
7.1The Godalming Gateway will facilitate and improve the capacity for cycling whilst preserving the comfort of pedestrian and mobility users. Specifically, it will facilitate: access to the northeast of the town centre (Waitrose, Bridge Street, Sainsburys) from the northwest of Godalming (Hurtmore, Charterhouse, Frith Hill, etc.); travel to/from Godalming Railway Station from/to the residential and business areas on Cattershall Lane.
7.2The 5th July 2022 Executive meeting approved an alignment through Phillips Memorial Park that routed cyclists away from the bandstand and open greenspace / sitting area. 7.3 Following Executive approval on 5th July 2022, an open tender was put out to procurement a detailed design, costing and construction management contractor. This contract was awarded to Bailey Partners in April 2023.
7.4As design contractor, Bailey Partners commissioned topographic, ground condition, heritage and ecology surveys. As well as detailed design and costings, Bailey Partners have also prepared the planning application and written the technical specification to support procurement of a construction contractor.
7.5Detailed design for Phillips Memorial Park has been coordinated with the SCC Highways design team to ensure a smooth transition to The Burys ‘cycle street’ section of the Greenway Gateway.
7.6Construction over the winter of FY 24-25 will minimise any disruption to use of Phillips Memorial Park, particularly avoiding the summer events programme.
8. Consultations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.