Application under section 73 to vary the wording of condition 2 (Materials), Condition 4 (Parking) and Condition 9 (Ecology) of WA/2021/0212 to allow for demolition work and main construction work to be separated and to reflect updated Ecology Assessment Report, partial discharge of condition 4 (Parking) and full discharge of Condition 8 (tree protection). Decision Subject to conditions 1-11, permission is GRANTED
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
The application has been referred to the Planning Committee because this is a Regulation 3 application submitted by Waverley BC Housing Department.
Planning permission was granted on 23rd September 2021 following committee approval for the redevelopment of the site for 4 houses. The 3-year time limited permission is due to expire shortly in approximately two months’ time. In order to keep the permission alive and implement the development a variation is sought to pre-commencement conditions as set out in the proposal section and clarified in section 3 below.
The full background to the approved development is clarified in the original report to the planning committee and is attached in Appendix 1.
This report will not repeat the previous assessment and will focus only on the relevant issues which are for consideration now.
2. Site Description
The site contains a community building and first floor residential unit, with associated area of hard surfacing. Vehicular access to the site is via a private driveway accessed from Parkhurst Fields. There are residential properties surrounding the site.
3. Proposal
Application under section 73 to vary the wording of condition 2 (Materials), Condition 4 (Parking) and Condition 9 (Ecology) of WA/2021/0212 to allow for demolition work and main construction work to be separated and to reflect updated Ecology Assessment Report, partial discharge of condition 4 (Parking) and full discharge of Condition 8 (tree protection).
The table below clarifies the wording of the original conditions and the variation sought shown in italics with part discharge of condition 4i) as varied and full discharge of condition 8.
CONDITION CURRENT WORDING REQUESTED CHANGES 2 ‘No development shall take place until No development, with the exception (SAMPLES OF samples of the materials to be used in of demolition works, excavation and MATERIALS) the construction of the external associated ground works shall take surfaces of the development hereby place until samples of the materials permitted have been submitted to and to be used in the construction of the approved in writing by the Local external surfaces of the development Planning Authority. Development shall hereby permitted have been be carried out in accordance with the submitted to and approved in writing approved details’ by the Local Planning Authority. Development shall be carried out in accordance with the approved details. 4 ‘No development shall commence until No development shall commence (PARKING) details of parking for vehicles of site until details of parking for vehicles of personnel, operatives and visitors and site personnel, operatives and storage of plant and materials has visitors and storage of plant and been submitted to and approved in materials for i) demolition and writing by the Local Planning Authority. groundworks; and ii) above ground Only the approved details shall be works; has been submitted to and implemented during the construction of approved in writing by the Local the development.’ Planning Authority. Only the approved details shall be implemented during i) demolition and groundworks; and ii) above ground works’.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
WA/2025/00805 - Ruffold Farm CranleighRESOLVED that, delegated authority is granted to the Assistant Director of Planning to GRANT outline planning permiss...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.