CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Waverley Borough Council
Executive, Tuesday 3 September 2024 at 7.00pm

Weydon Lane Landfill

Approved Executive 1 paper

Executive approved this item on Tuesday 3 September 2024. Below is the council's own wording, with the papers it was decided on.

ItemEXE 19/24

Resolved

That the Executive approves: 1. A project to repair the existing monitoring solution at Weydon Lane, to enable the site to be fully monitored for gas and groundwater quality, by bringing compromised vents and monitoring wells back into use. 2. A supplementary estimate of £65,000 required for construction costs and ... EXE 19/24
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1Waverley Borough Council owns the former landfill site at Weydon Lane, Farnham, which was decommissioned in the 1980’s and given a shallow clay cap with vent trench system. The site is approximately 39,000 square metres and generally covered with grass and a variety of trees and shrubs. It is not officially open to the public but is widely used by local residents as a shortcut and for dog walking.

1.2There are the following issues with the site:

- Boreholes/vents require re-establishing, and a significant amount of vegetation needs to be cleared from them to enable the overall site to be monitored properly.

- The clay cap needs to be fixed / replaced in some areas.

1.3Restoration of the site would resolve these issues and there is an opportunity in the longer term to provide a usable green space; residents have made representations to the council with ideas.

1.4A project initiation document (PID) was prepared in 2021 setting out options for restoring/developing the site. A Request for Information (RFI) was put out to the market to inform our understanding of the viability of developing the site at zero net capital cost, based on soil receipts. Although the Project Coordinating Group gave the go ahead to progress the project in 2022 it was subsequently put on hold due to re-prioritisation. The PID was updated in January 2024.

1.5Four options have been assessed including short-term fixes and longer-term development of the site, for example as a green space or bike track. The recommended option is to fix the issues with the monitoring solution in the short-term so that the condition of the landfill can be properly assessed, providing a basis for future development options.

1.6The Executive is requested to approve £65,000 of funding for a monitoring improvement project to be carried out in the short term and for the employment of consultants in due course to progress the long-term project for the development of the site for formal recreational / leisure use.

2. Recommendation to Executive

That the Executive approves:

2.1A project to repair the existing monitoring solution at Weydon Lane, to enable the site to be fully monitored for gas and groundwater quality, by bringing compromised vents and monitoring wells back into use. 2.2 A supplementary estimate of £65,000 required for construction costs and the appointment of consultants to support the redevelopment of the site.

That the Executive endorses:

2.3The intention to redevelop the site in the long-term for recreational and leisure use.

3. Reason(s) for Recommendation:

3.1The monitoring solution at the Weydon Lane Landfill site is not able to monitor gas emissions across the whole site due to issues with the vents and monitoring wells, which compromises Waverley’s duty of care to residents.

3.2By improving the monitoring system through the proposed works, we will be able to assess the performance of the Landfill comprehensively. This will allow corrective actions to be identified if required and provide a firm basis for future decisions on the development of the site.

3.3To appoint consultants to pursue the longer-term project, but in conjunction with the redevelopment of the Council’s other land fill site at Broadwater Park in Godalming, allowing for economies of scale.

4. Exemption from publication

4.1The report is not exempt from publication.

Purpose of report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Weydon Lane LandfillReport 481 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PF
Councillor Paul FollowsChair, apologies
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
GM
Councillor George MurrayCommittee Member, apologies
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

On this subject at Waverley

Search all
  1. Weydon Lane LandfillThis decision
  2. A1 - WA/2018/0348 - The Workshop, Weydon Mill Lane, Farnham GU9 7QLRefused
  3. Lease Extension: Flat 1 Forburys, 5 Weydon Lane, FarnhamApproved
  4. Weydon Lane Former Landfill Site - Future Use and Site ManagementAgreed
  5. A1 - WA/2015/1746 - The Workshop, Weydon Mill Lane, Farnham GU9 7QLAgreed
  6. B2 - WA/2015/2294 - 40 Weydon Lane, Farnham GU9 8UPAgreed

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies