CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Waverley Borough Council
Council, Monday 16 September 2024 at 7.00pm

Museum of Farnham MEND Project: Budget Approval

Approved Committee 1 paper

Council approved this item on Monday 16 September 2024. Below is the council's own wording, with the papers it was decided on.

ItemCNL40/24

Resolved

RESOLVED unanimously to approve: 1. An increase of £230,310 to the capital budget which is the amount awarded to the Council by the National Lottery Heritage Fund. 2. To increase the capital budget by a further £213,000 from Capital Contingency Reserve.3. 3. An overall project budget of £1,471,713, these figures include a sum of £237,000 which represents the contingency budget and provisional sum.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Council

Executive summary

1.1The process of procuring a principal contractor for the conservation and repair contract for the Museum of Farnham is now complete. In accordance with threshold four, the tender was advertised on the Intend e-sourcing platform and has been administered by the Procurement team. The winning bidder is Management and Construction Services (MCS) and the price tendered is £1,286,713.74 excluding VAT. This figure includes a contingency budget and provisional sums totalling £237,000.

1.2The report provides a current budget for the project since previously reported costs were based on pre-tender estimates for the purposes of applying to the MEND Fund in September 2022. Total project costs have increased considerably since then. The intended contract has contributed to this increase because there may be a requirement for additional and unforeseen works to be carried out depending on the condition of the building. These works are listed in the main body of the report under the heading of provisional sums and contingency. The Council has been advised that it would be judicious to make a case for budgetary provision for these items, though they can only be expended following approval from the Council (the client).

1.3The financial position of the project has been adversely affected by the wider economic climate, but this should not detract from the Council’s significant achievement in securing £985,000 of external grant funding towards the costs of the project. The main body of the report sets out the main reasons for the cost increase.

1.4It should be noted that the contract sum tendered by MCS includes an additional sum of £140,000 for joinery repairs and redecoration of the fourteen original sash windows and the main entrance doorway on the front façade. The repair cost of £140,000 includes a provisional sum of £18,000 for unforeseen repairs which can only be expended following the Council’s approval. The window repairs and redecoration were not included in the repair scope put forward and funded by MEND as the Arts Council were explicit about their funding being directed to the gauged brickwork repairs. However, the works were accounted for in the National Heritage Lottery funding.

1.5The chartered surveyor for the project has advised the council of the significant risks associated with a delay in appointing a principal contractor, which will also affect the contracting of the specialist subcontractors. To reduce the risk of delay the Council alongside the lead consultant for the project will work with the contractor to identify pre-contract lead in activities that would be beneficial to get underway while the Council executes the JCT contract.

These activities include:

 Attending a pre contract meeting with stakeholders  Engagement with the Council’s legal team to finalise the amended JCT Contract  Preparation of a Construction Phase Plan  Preparation of a planning application for remote welfare at Upper Hart Car Park (if required)  Preparation of a traffic management plan  Applying to Surrey Highways for the suspension of parking bays and to obtain the scaffold license

1.6At its meeting on 3 September 2024, The Executive approved awarding the contract to Management and Construction Services as the main contractor for the brickwork repairs and conservation works to the front façade of Willmer House with Simpson Brickwork Conservation Limited being a named sub-contractor.

1.7At the same meeting, the Executive made 3 recommendations to Council set out at 2 below.

2. Recommendation to Council

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Museum of Farnham MEND Project: Budget ApprovalReport 549 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

39 of 49 attended
JW
Councillor John WardMayor, present
PR
Councillor Penny RiversDeputy Mayor, present
LA
Councillor Lauren AtkinsCommittee Member, apologies
JA
Councillor Jane AustinCommittee Member, present
ZB
Councillor Zoe Barker-LomaxCommittee Member, present
DB
Councillor David BeamanCommittee Member, present
DB
Councillor Dave BusbyCommittee Member, present
LC
Councillor Laura CavaliereCommittee Member, present
PC
Councillor Peter ClarkCommittee Member, apologies
CC
Councillor Carole Cockburn BEMCommittee Member, present
JC
Councillor Janet CroweCommittee Member, present
JD
Councillor Jerome DavidsonCommittee Member, present

All 49 on the meeting page

On this subject at Waverley

Search all
  1. Museum of Farnham MEND Project: Budget ApprovalThis decision
  2. Wa/2025/01772 - land at farnham museum 38 west street farnham gu9 7dxDecided
  3. WA/2025/01208 - Land at Farnham Museum, 38 West Street, Farnham, GU9 7DXDecided
  4. Progress report on the essential repair and conservation works to Grade 1 Willmer House, Museum of FarnhamApproved
  5. Museum of Farnham MEND Project: Approval to enter a contract with the nominated contractor.Approved
  6. Acceptance of a grant from the National Heritage Lottery Fund for capital repair of the Museum of FarnhamApproved

More from Waverley Council

All decisions
MeetingDecisionOutcome
29 Jul 2026 Annual Standards Report 2025-26RESOLVED that the Annual Report 2025-26 of the Joint Standards Committee be deferred to a future meeting. Deferred Open
29 Jul 2026 Member Questions at MeetingsThat 1. The amended Council Procedure Rule 12 as set out in Appendix 2 to this report, be adopted 2. The Monitoring O... Approved Open
30 Jun 2026 Amended Redundancy Policy - Pension Strain CostsThat 1. the amendment to the redundancy policy to remove the deduction of pension strain costs from redundancy paymen... Approved Open
30 Jun 2026 Councillor Connor Relleen - Approval of Reason for Non-attendance at meetingsThat 1. the reason for Councillor Connor Relleen’s failure to attend any meeting of the Council or any of its committ... Agreed Open
30 Jun 2026 Waverley Householder CIL - Lack of ProgressRESOLVED that the motion as set out in agenda report be supported. The Chamber adjourned for a 10 minute comfort brea... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies