Progress report on the essential repair and conservation works to Grade 1 Willmer House, Museum of Farnham

Approved Executive 1 paper

Executive approved this item on Tuesday 3 June 2025. Below is the council's own wording, with the papers it was decided on.

ItemEXE 12/25

Resolved

The Executive resolved to approve: (i) a supplementary estimate of £248,374.80 for the Willmer House repair programme to be funded from the Waverley MTFP risk reserve. (ii) that authority is given to the Assistant Director of Commercial Services to extend the contract with MCS to allow for the chimney repairs ... EXE 12/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.0This report updates Members on the essential repair and conservation works to Grade 1 Listed Willmer House. It reports the findings of recent site inspections and detailed surveys, which have been carried out from the scaffold. 1.1 The main purpose of the report is to seek the Executive’s approval to increase the final account for the project by £248,374.80. This additional funding is required to address two issues:

1.2Firstly, the unexpected cost of rebuilding two chimney stacks and the parapet wall on the east elevation of the building, adjacent to Bishops Mead.

1.3Secondly, the later than planned start date for the project combined with additional work requirements has extended the duration of the tender programme from 69 to 83 weeks. As a result, the contractor has applied an extension of time claim for 14 weeks to complete the works.

2. Recommendation to Executive

That the Executive approves:

2.1a supplementary estimate of £248,374.80 for the Willmer House repair programme to be funded from the Waverley MTFP risk reserve.

2.2that authority is given to the Assistant Director of Commercial Services to extend the contract with MCS to allow for the chimney repairs and to approve an extension of time request within the approved budget.

3. Reason(s) for Recommendation:

3.0The unsafe and deteriorating condition of two chimney stacks on the building’s east elevation are posing a significant health and safety risk to the users of Bishops Mead. To remove the safety risk the conservation consultant has advised the council to dismantle the defective chimneys in line with the roof gutter and to rebuild them matching the original details of Willmer House.

3.1The chimneys must be rebuilt, as there is no listed building legislation for temporary work to a Grade 1 Listed building without a legally binding commitment to rebuild. The council’s Principal Conservation Officer has advised that taking the chimneys down without Listed Building Consent is a criminal offence that could lead to prosecution. If this were to happen a listed building enforcement notice would be served requiring the chimneys to be rebuilt within a certain timeframe. Failure to comply with the enforcement notice would be a breach of the consent, which could lead to criminal prosecution proceedings.

3.2The programme must accommodate a 20-week winter shut down period when activity on site is paused. This is because lime putty mortar is used, which requires specific temperature and humidity levels to harden. Using lime mortar in colder temperatures can lead to catastrophic failure as the new brick face would not bond to the backing brickwork. The January start date has involved significant alterations to the programme sequence which has led to an unavoidable prolongation of the contract.

4. Exemption from publication

4.0No

Purpose of report

5.0To report two significant variations to the agreed contract, which are unavoidable and unexpected. Unfortunately, the cost of this additional work cannot be met by the contingency and provisional sums allowed for in the tendered contract.

6. Strategic Priorities

6.1The Museum of Farnham contributes to the strategic priority of a more inclusive borough as it is free at the point of entry to any member of the public wanting to visit or engage with its services. 7. Background

7.0Construction progress to date – April 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Progress report on the essential repair and conservation works to Grade 1 Willmer House, Museum of FarnhamReport 541 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies