Approval to enter into contract for Electrical Testing services and works

Approved Executive 2 papers

Executive approved this item on Monday 7 July 2025. Below is the council's own wording, with the papers it was decided on.

ItemEXE 37/25

Resolved

The Executive resolved to: (i) Approve the award to Pilon for EICR inspections and remedial works for a period of three years, at a cost of £961,590.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Purpose of report

5.1The purpose of this report is to obtain authority from the Executive to enter into a contract worth more than £200,000 in line with the Council’s Contract Procedure Rules (CPR 8.6).

6. Strategic Priorities

6.1This procurement supports the Council’s objectives of:

 A resilient and well managed council as the consideration of the contract being procured provides best value and use of council resources.  Decent and affordable homes 7. Background

7.1The Council has a responsibility to carry out Electrical Installation & Condition Reports (EICR) every five years for its social housing. Waverley and Guildford Borough Councils invited bids under a collaborative procurement for a single supplier to provide EICR inspections and remedial works for their homes.

7.2The successful tenderer will enter into separate contracts, with each contracting Authority. Contract performance will be managed separately by each Council.

7.3Inspections will not include Leaseholder and Shared Ownership dwellings.

7.3A tender pack was published in late March 25, with solicited bids from the market through a further competition under a framework. 20 tenderers were invited to bid, with 10 tender applications received.

7.4Following the evaluation process stated in the tender documents, Pilon were determined to be the most economically advantageous bidder based on 70%/30% quality/cost award criteria, achieving an overall score of 95.1%

7.5The successful contractor will enter into separate contractual agreements with each Council.

8. Consultations

8.1Procurement and Legal were consulted throughout the process.

9. Key Risks

9.1Pilon fail to deliver to the required quality and/or number of inspections required. This will be managed by strong contract management. There will be monthly contract meetings, with performance monitored through Key Performance Indicators. The contract will allow for suitable remedies.

9.2Timescales: delays to milestones met will risk project overrun and risk completion of the full cycle of inspections required within the contract term (3+1+1 years). This will be managed by strong contract management. There will be monthly contract meetings, with performance monitored through Key Performance Indicators. The contract will allow for suitable remedies.

Financial implications

10.1The total cost of the contract will be met from existing budgets, over the three year term is £961,590 and for a 5 year term is £1,300,000 for Waverley Borough Council. This budget was contained within the 30 year business plan presented to Council in February 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RTA -EICR inspections and remedial works 37/25Appendix 1 878 KB Download
PDF
Approval to enter into contract for Electrical Testing services and worksReport 484 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, apologies
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, apologies
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

On this subject at Waverley

Search all
  1. Approval to enter into contract for Electrical Testing services and worksThis decision
  2. Approval to enter into contract for HRA Stock Condition Survey ServiceApproved
  3. Approval to enter into contract with Leaseholder Insurance Provider 2025-28Approved
  4. Museum of Farnham MEND Project: Approval to enter a contract with the nominated contractor.Approved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies