Resolved
RESOLVED that: (i) A Supplementary Budget of £110,000, to be funded from Strategic CIL for the purpose of progressing the Sandy Hill Pump Track project, be approved.
Executive approved this item on Tuesday 5 August 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: (i) A Supplementary Budget of £110,000, to be funded from Strategic CIL for the purpose of progressing the Sandy Hill Pump Track project, be approved.
2.1That the Executive resolves to approve: 2.1.1 A Supplementary Budget of £110,000 to be funded from Strategic CIL for the purpose of progressing the Sandy Hill Pump Track project. 3 Reasons for recommendation
3.1Securing a Supplementary Estimate for this project will allow the Council to proceed with the project and tender for a contractor to design and build the pump track.
3.2A design is required for inclusion in the planning permission application. Planning permission for the Pump Track must be secured by 1 April 2026 in order for the CIL funding to remain available, as the award of Strategic CIL to the project is subject to a resolution to grant planning permission being achieved within 12 months of the Executive decision (i.e. by 1 April 2026). The Supplementary Estimate will allow the Council to apply for planning permission towards the end of this calendar year.
4 Next steps
4.1Should the Supplementary Estimate be approved, the Parks & Countryside team will be in a position to prepare the procurement for a contractor to deliver the design and build of the Pump Track. 4.2 Council officers, under the Assistant Director for Environment’s ‘Scheme of Authorisation’ will submit a planning permission before the 1 April 2026 deadline when the CIL funding offer would expire (if planning permission was not granted by this date).
5 Exemption from publication 2 5.1 Not exempt from publication.
6 Background and Proposal 6.1 At present there is no pump track or similar facility within the Borough. The provision of such a facility is much needed by Waverley’s local communities and will deliver new services to its ever-increasing resident population.
6.2Sandy Hill is one of the most deprived areas in the Borough, where improvements to local facilities and equipment would provide the local residents with a boost and play an important role in the social development of children living in this community.
6.3The proposed track will also attract users from all parts of Farnham and further afield. It will provide a unique recreational facility to the residents and communities of the town, and will give people of all ages, backgrounds and abilities the opportunity to exercise and enjoy a safe outdoor space, ultimately promoting health and wellbeing.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Equality Impact Assessment 49/25Appendix 1 | 668 KB | Download |
PDF |
Supplementary Estimate request for Sandy Hill Pump TrackSupplementary | 236 KB | DownloadRead as text |
Follow Executive at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... | Agreed | Open |
| 1 Sep 2026 | New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... | Decided | Open |
| 1 Sep 2026 | Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... | Agreed | Open |
| 1 Sep 2026 | Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... | Approved | Open |
| 1 Sep 2026 | Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.